|
From: Ronnie Smith,
Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #4
Posted: November 11, 2005
During the past two
weeks, we have continued to press towards the completion of the various
tasks undertaken to complete the initial clean up, make temporary repairs,
and to reduce or eliminate additional damage to facilities (from water,
mold growth, etc.). We have also begun to carve out specific permanent
repair work that focuses on key components of the buildings’
infrastructure. Finally, we continue to work closely with a team of
people representing the State’s Offices of Facility Planning & Control and
Risk Management, FEMA and the LSU Systems Office to monitor, prioritize
and push forward key elements of the permanent recovery work.
Understandably, the
attention of many faculty members, staff and students has shifted from the
some of the immediate and pressing questions of temporary housing and
restarting classes to the possible timeline for our return to the New
Orleans campus buildings and all the logistics that will entail.
Significant “unknowns” still remain so providing specific projections
isn’t yet feasible, but we thought it would be helpful to describe the
basic elements that must be addressed before permanent re-occupancy of a
typical building can occur.
Switchgear:
Each building receives its electrical power from Entergy through the
city-wide power grid. As the power enters a building, it is routed
through a variety of centralized electrical equipment called
“switchgear”. The switchgear receives the power, routes it to a series of
other electrical panels, circuit breakers, etc. elsewhere in the building
which eventually delivers the power ceiling lights, elevators, blowers,
wall sockets, etc. When immersed under water (especially salt water), the
switchgear becomes corroded and fails. Power can no longer be delivered
to the building.
- The switchgear in
each building has been damaged. Before a building can be occupied, all
of its switchgear must be inspected, permanent repairs made and tested,
and the repairs inspected.
- Once the
switchgear is operational, the rest of the electrical system throughout
the building must be tested and repaired as needed, although occupancy
of the building may not require that all of this work be completed
(depending on the specifics of the failures discovered.)
Fire Pump Systems:
Fire codes (generally) require that large buildings have water systems
(separate from normal building water) supplying the sprinkler systems and
fire hose water supply connections on every floor. Water pressure
requirements cannot be met in upper floors through the basic city water
supply system. Separate, electrically powered water pumps to pressurize
the fire system water supply are required to meet fire codes. These
systems also include pump control panels and fire alarm panels. Without
fully functioning fire pump systems, the State Fire Marshal will not issue
the necessary occupancy permits.
- All of the fire
pumps in campus buildings were immersed in the flood waters and
damaged. The State Fire Marshal is requiring that all of the fire pumps
and related components be replaced to insure that they will operate
reliably in an emergency.
Domestic Water Pumps:
The regular water supply to large buildings (providing water to toilets,
faucets, etc.) must also be pressurized to provide sufficient water
pressure to upper floors. Electrically powered water pumps are connected
to the city water as it enters the building and pressurizes it
sufficiently to supply the upper floors. Health codes require
functioning restrooms, etc. before a building can be occupied.
- All of the
domestic water pumps were exposed to the flood waters. Each pump must
be inspected, repairs made or pumps replaced (as needed) and the
building water system tested before occupancy will be allowed.
Environmental
Remediation: The
extended exposure of basements and 1st floors to standing flood
water introduced a number of potential environmental threats. The
presence of mold, trace chemicals, petroleum products, and other issues
(some as a result of our particular use of certain buildings) must be
identified and addressed before a building can be safely occupied.
- An extensive,
initial assessment of every building is required; usually by an
industrial hygienist. Based on the sampling and testing, specific
environmental issues are identified. A detailed plan and bid
specification for premeditating the identified issues is developed; a
bid issued and a contractor hired. Once the remediation work has been
completed, an independent environmental assessment is conducted again to
verify that all of the environmental issues have been addressed. This
assessment must be performed in all areas of the building; even areas
not thought to have been directly impacted by water or wind damage.
Elevators:
Although all of the buildings include internal stairwells for emergency
work, the elevators must be in proper working order and have passed
inspection before a building can be reopened. A variety of building codes
come into play, including issues of accessibility (ADA compliance).
- Most of the
elevators were set to automatically return to their 1st floor
location when power was lost. This resulted in those elevator cars
being exposed to the flood waters. Water also entered and remained in
the elevator pits. Damage often includes damage to elevator doors,
safety switches, car rollers, pit buffers and other electrical
components.
- Every elevator in
the building must be inspected, damaged components repaired or replaced,
and the elevators inspected by the State Elevator Inspector before the
building can be re-occupied.
Other Repair/Reconstruction:
The final element of re-occupancy would be the needed repairs or
reconstruction of spaces that were damaged by the disaster. Most of the
damage to flooring, walls, ceiling tiles, etc. occurred in the spaces
where flood waters intruded, although some buildings also experienced
water intrusion through broken and damaged windows, and through roofs that
were damaged by wind and debris. However, it may be possible that these
specific repairs may not need to be completed before the otherwise
undamaged portions of the building may be returned to use. It will still
be necessary for the elements listed above to be successfully addressed
(apart from the repairs of damaged areas) for this approach to be
successful.
Strategies
In light of the
above, we have developed a set of strategies that we believe will help to
bring major buildings back on line as quickly as possible. We have
identified logical, separate bodies of work related to these key elements
and sought the concurrence of the Office of Facility Planning to break key
tasks out into separate contracts. This has allowed some of the strategic
work to get underway as quickly as possible. The following are specific
examples of these strategies in action:
- Work on completing
permanent switchgear repairs has been underway at the Resource Center
since mid-October and will be completed shortly.
- Work to make
permanent repairs to switchgear at the MEB has recently been completed.
- A contract to
effect permanent switchgear repairs at the Residence Hall, CSRB, Lions
Eye Center and Nursing/Allied Health Buildings is currently out on bid.
- A contract was
issued on 10/12/05 to make the permanent repairs to domestic water pumps
in the Resource Center, Residence Hall and MEB.
- A bid solicitation
has been issued on 11/10/05 to make permanent repairs to various types
of pumps to supply water and heat to the Residence Hall, MEB, CSRB,
Lions Eye Center, Nursing/Allied Health, and Resource Center.
- Early in October,
the existing elevator maintenance contracts were amended to the
contractors to make the permanent repairs to the building elevators.
Work began on assessing specific damages to each individual elevator,
cost estimates have been developed, parts are being ordered and repairs
are beginning as parts are delivered.
- A contract has
been issued to remove and dispose of flood-damaged movable equipment and
furnishing (which may be sources of mold, etc.) and work has been
underway since 11/4/05.
- Two bid
solicitations were issued on 11/2/05 to remove flood-damaged carpet,
wall coverings, etc., which may also be sources of mold and other
environmental contaminants. One addressed the Dental School (which was
complicated by the presence of asbestos in the basement) and the other
is for the rest of the campus buildings. Bids are due back on 11/18/05.
- The Office of
Facility Planning & Control has agreed to allow us to use an existing
contract with an architect/engineering firm and explore the possibility
of (environmentally) sealing off the 1st floor areas of the
three primary research buildings (MEB, CSRB, and Lions Eye Center);
allowing more rapid occupation of upper floors while the major repair
work on the 1st floors is planned, bid and completed.
In the 10/28/05
update, we also shared the general pattern that we anticipate following
for completing the major building repairs. As a reminder, here is a
summary of that pattern and notes on work underway:
-
Architect Selection.
OFPC is using an expedited process to select architect(s).
- NOTE: LSUHSC
has recently prepared two information packages that are being used to
advertise for and select the architect(s) for the major building
repairs and remediation. We have divided the major repair work into
two projects; one for the Dental School campus work and one for the
downtown campus.
-
Develop Bid Package(s) For Building
Repair. The architect(s)
selected will begin developing the bid packages for the repairs needed
in each building.
-
Develop Environmental Remediation Plans
and Specifications.
Concurrent with the above, the selected architect(s) will also develop
plans and specifications for the work needed to perform any
environmental remediation in the flood damaged buildings.
-
Bid and Award Contract(s).
The bid packages for building repairs and the plans/specifications for
the environmental remediation will be advertised, bids received, and the
contracts awarded.
-
Construction, Repair & Remediation.
The contractor(s) selected will complete the repairs required. The
environmental remediation work will also be completed during this phase.
-
Final Inspections.
As a contractor completes the work for a building, the final inspections
will be scheduled and completed.
Here are highlights
of work that has been accomplished since our update from Friday, October
28th:
- The contract with
the architectural/engineering firms to assess the damage to the campus
buildings is coming to a close, as they work to complete the extensive
written documentation and photographic evidence of the damage to campus
buildings. This information will be used to develop the specifications
for the permanent repairs (see above), and will also help to document
claims for reimbursement with ORM and FEMA.
- NOTE: This
contract may be amended to allow for the design of plans to
environmentally seal off the 1st floors of the MEB, CSRB,
and Lions Eye Center buildings, in hopes of expediting re-occupancy of
the upper floors.
- The temporary IT
data center at the Department of Public Safety continues to be stable
and supports key software applications. Selected Exchange (email)
servers have been upgraded to a newer version of the software which
supports spam blocking. This should result in a significant reduction
in unsolicited email reaching email users.
- A contract has
been awarded to provide temporary power (as needed) and emergency air
conditioning to the Dental School Clinic and Administration buildings.
The contractor completed all of the installation work and temporary air
conditioning was provided to both buildings on 11/8/05.
- The contractor who
was hired to power-wash the building exteriors and to clean/disinfect
the basements and selected 1st floor rooms has completed all
of the work.
- The assessment of
the damage to elevators across the campus continues. As repair parts
are secured, permanent repairs to individual elevators will begin. The
contractors have continued to assist in making temporary repairs to get
selected elevators in buildings operating.
- Implementation of
the plans for providing temporary housing in Baton Rouge for students,
faculty and staff continue to progress. Room assignments on the FinnJet
ship continue being made for faculty and staff. Forty (40) of the new
house trailers have electricity connected. Final inspections are
underway and trailers are being assigned as inspections are successfully
completed. Students with children who requested temporary housing are
being accommodated first.
- The contract to
clean various portions of selected campus buildings (bathrooms, kitchens
and public spaces) was completed on 11/8/05. LSUHSC Facilities staff
continues to complete the more routine cleaning.
- Movable equipment
and furnishings in basements and 1st floors has been assessed
by LSUHSC staff and work under the contract for the removal and disposal
of the items that are not salvageable has begun. Work has been
completed at the Resource Center and at the Lions Eye Center and rapid
progress continues.
- Work on the
permanent repair/rebuilding of domestic water pumps in three of the
downtown campus buildings continues. The initial pumps removed from the
MEB and the Resource Center (2 from each building) have been rebuilt and
reinstalled. One of the pumps has been removed from the Residence Hall
and has been sent for rebuilding.
- The bid
solicitation for the emergency removal and disposal of carpet, wall
board, and other porous & semi-porous materials from basements & 1st
floors to prevent further spread of mold was released on 11/3/05. Bids
are due on 11/18/05.
- A bid solicitation
to make permanent repairs to the switchgear in the Residence Hall, CSRB,
Lions Eye Center and Nursing/Allied Health Buildings was released on
10/27 and advertised. The pre-bid walk through was completed on
11/7/05. An addendum was issued on 11/9/05 and bids are due on
11/11/05.
- The fire pump
controller panel at the Residence Hall was replaced and the system is
being tested.
- Permanent repairs
to the MEB switchgear have been completed and temporary power has been
restored to the building, except for one quadrant. LSUHSC Facilities
staff are now testing various circuits throughout the building.
- On 11/10 the
Office of Facility Planning & Control approved the LSUHSC program
materials for use in advertising the architect selection process. Ads
are being placed and an expedited selection process has been approved.
- A bid solicitation
has been issued on 11/10/05 to make permanent repairs to various types
of pumps to supply water and heat to the Residence Hall, MEB, CSRB,
Lions Eye Center, Nursing/Allied Health, and Resource Center.
We trust that you
continue to find this information helpful. You may also want to read the
Daily Updates posted on the web site to received more frequent information
on progress.
|