|
From: Ronnie Smith,
Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #11
Posted: February 24, 2006
Mardi Gras update! With a little good
fortune, we are on the verge of being able to reopen the MEB and the
Lion’s/LSU Clinics buildings. The environmental remediation in the upper
floors of the MEB has been completed and preliminary air monitoring
results are good. Final test results are due back early next week and no
problems are anticipated. The State Fire Marshal is expected to complete
his inspection on Wednesday, March 1st and no problems are
expected. Reopening of the building with a manual fire watch is
anticipated on Monday, March 6th.
The last repaired main breaker for the electrical
switchgear at the Lion’s/LSU Clinics building has been received. Within
the next 4-5 days, the power in the building will be taken down, the
switchgear cleaned, the refurbished main breaker replaced and permanent
power restored.
If the planned cleaning of the switchgear and the
reinstallation of the refurbished main breaker goes as planned, we
anticipate the reopening of the Lion’s/LSU Clinic Building on Monday,
March 6th as well.
Progress on making repairs to the elevators in the
downtown campus buildings has been accelerating. Most of the parts
required for the repairs have now arrived and the additional out of state
crews dedicated to the LSUHSC repair work are expediting the completion of
this work. The repairs to the emergency power generators that serve the
downtown campus buildings are under contract and work on the repairs
begins early next week.
The architect/engineering firm responsible for the
Dental School campus is completing specifications for temporary repairs to
key building systems that, when completed, will allow the re-occupancy of
upper floors of the Clinic and Administration buildings. The repairs
will focus on the building switch gear, chillers, key building pumps,
clinic systems, and safety systems. The architects are currently using
expedited procurement processes to secure contractors to complete this
temporary repair work. The first of the bid packages has been prepared
and released to prospective contractors. This will address the temporary
repairs to the building electrical systems.
Work on the environmental remediation contract for
the CSRB, MEB and Lion’s Eye Center has progressed rapidly. The
contractor has multiple teams working in the buildings simultaneously.
Significant portions of the upper floor cleaning required by State
protocols has been completed. The more time consuming work in the 1st
floor spaces is well underway.
Pricing is currently being solicited by the downtown
campus architect for the second environmental remediation contract. It
will address the Residence Hall, Stanislaus Hall, the Nursing/Allied
Health Building, and the Resource Center. The architect currently
anticipates that work under this contract will begin during the week
following Mardi Gras. Similar contracts will be issued at later dates to
address the Dental School Clinic and Administration Buildings and 1542
Tulane Ave. and other smaller structures.
The following is a brief description of the basic
work that will be done by the environmental remediation contractors:
- The environmental
remediation process provides for the demolition, removal and disposal of
building materials that were flooded or found to harbor mold spores or
other biological hazards. This is in addition to all of the cleaning
and disposal of flood damage materials that has already been
accomplished through earlier contracts.
- The standard protocol
for environmental remediation also provides for the cleaning and
disinfecting of the interior spaces; wiping down hard surfaces (walls,
doors, stairwells, light fixtures, ceilings, etc.), vacuuming, etc.
They will also be replacing filters, cleaning and disinfecting the air
handling unit coils and the interiors of air handling units.
- On the 1st
floors or in basements where flood water was present, the demolition
will typically include removal of drywall to a height of 7 feet, floor
coverings as needed (that were not previously removed by an earlier
contract), ceiling tiles as needed, etc. Removal of asbestos tiles and
the mastic is also included as necessary. Floors and solid walls
(masonry & granite) will be cored to determine if water penetrated and
remediation is required. Metal studs and other structural walls will
initially remain and be cleaned and disinfected. Many metal studs will
require replacement, but that will be done as part of the permanent
repairs. Before the demolition begins, the 1st floor spaces
will be sealed off to prevent migration of any contaminants that may
become airborne during the demolition.
- When completed, the
contract will provide us with unrestricted access to the cleaned spaces
in the upper floors, and spaces on the 1st floors will be
clean and ready for the permanent renovation work.
Telephone Services: Auxiliary Enterprises has been
assessing the telephone services at the various campus buildings. Working
in concert with the State’s Office of Telecommunications Management (OTM)
and BellSouth, the damage is being identified and repairs have begun as
reflected below:
- The testing of BellSouth trunk lines serving the
major buildings has been completed. Repair needs have been identified
and BellSouth is scheduling the needed work.
- The connection panels (demarks) in each building
between the trunk lines and the individual lines feeding the offices and
spaces in the buildings have been inspected. BellSouth has identified
those demarks that they require to be elevated when they are repaired or
reinstalled.
- Where telephone service is currently available to
a building, testing of individual circuits (telephones) will begin.
Where necessary, individual repair tickets will be opened with OTM.
Data Network: Computer Services has been testing the
network infrastructure that connects the data center to the various
downtown campus buildings and provides data circuits to individual
offices, labs, and other spaces.
- The fiber (or cable) that connects each building
has been tested and verified as operable.
- The core switches in each major downtown campus
building have been inspected and proposals to secure new core switches
(where necessary) are being prepared.
- CSRB: The core switches were damaged, but the
repairs have been completed and connectivity has been restored to the
building.
- Lion’s Eye Center: The core switches were
damaged and must be replaced. A proposal to affect the needed repairs
has been completed and the parts will be ordered soon.
- MEB: The core switches were not damaged by the
flood waters and connectivity can be reestablished as soon as the HVAC
is made available to the telecom closet.
- Residence Hall: Network connectivity is
available to the building.
- Stanislaus Hall: Wireless access point on the
roof was damaged, but has been repaired. Connectivity has been
restored.
- Nursing/Allied Health: The network is intact
and connectivity can be re-established as soon as stable electricity
and HVAC are available to the telecom closets.
- Resource Center: The core switches were located
on the 7th floor and were not damaged.
- Dental School Campus: The visual inspection of
the core switches has just begun.
Campus Housing: We recognize the importance of
making the two campus residence facilities available as quickly as
possible. Particularly in the case of the Residence Hall, the challenges
represented by older building designs and systems are unique and
different. Some of these factors may impact on the time to complete the
work necessary to allow the building to be reoccupied. However,
significant progress has been made in preparing both the Residence Hall
and Stanislaus Hall for reoccupation. For example:
- Both buildings are part of the 2nd
environmental remediation contract that is currently out on bid.
Current plans are to have the contract in place and work underway during
the week after Mardi Gras. The Residence Hall is to be the 1st
priority for the contractor, followed by Stanislaus Hall and the
Nursing/Allied Health Building, and finally the Resource Center.
- Elevator repairs have been underway at both
facilities for some time and continue to be monitored closely. The
repairs to all 4 elevators at Stanislaus Hall are substantially complete
and the State Elevator Inspector will be asked to conduct the
inspections soon. One of the tower elevators is working at the
Residence Hall, but has not yet been certified for passenger use.
- The electrical switchgear repairs have been
completed at the Residence Hall. The switchgear at Stanislaus Hall was
not damaged.
- Repairs to the fire pump at the Residence Hall
have been completed. The fire alarm panel was not damaged.
- Repairs to the fire alarm system at Stanislaus
Hall have been completed. The fire pump was not damaged.
- The repairs to the emergency generators serving
the downtown campus (including both of these buildings) have been placed
under contract. Work should begin on Monday, 2/27/06.
- Heating and cooling are available in the Residence
Hall. Domestic hot and cold water is also available.
- Heating and cooling are available in Stanislaus
Hall. The domestic (hot and cold) water pump is on order and shipment
of the pump is scheduled for 3/13. The new basement sump pumps are
being installed.
- Network connectivity has been restored to the
upper floors of Stanislaus Hall.
Here are highlights of work that has been
accomplished since our last update was posted on Friday, February 10th.
- The solicitation for a second environmental
remediation contract addressing the Nursing/Allied Health Building, the
Residence Hall, Stanislaus Hall and the Resource Center has been issued
by the architect. At the direction of the Office of Facility Planning &
Control, they are utilizing an expedited solicitation process, so a
contract award may be made quickly. We are hopeful that work may begin
on this contract during the week following Mardi Gras.
- Most of the repair parts for elevators at the
downtown campus have arrived and the permanent repairs to individual
elevators continue at an accelerated pace. Two of the major elevator
contractors have brought in additional manpower from out of state to
dedicate to completing repairs at the Health Sciences Center. The
elevator contractors continue their work at:
- CSRB
- MEB
- Lion’s Eye Center
- Nursing/Allied Health
- Resource Center (two have been certified for
use)
- Stanislaus Hall (work completed on all 4
elevators, and the inspection will be requested shortly)
- Residence Hall
- Entergy/Gravier St. Garage
Until permanent repairs
are completed and elevators certified by the State Elevator Inspector,
routine use has been discontinued. Restricting the use of elevators in
buildings where the environmental remediation has not been completed will
help to minimize further spreading of mold to upper floors.
- The contractor completed the work in the Dental
School basement to remove flood damaged building materials, where
particularly challenging conditions were present. We are now able to
enter the basement without wearing any personal protective equipment.
- Work has been completed under the contract to make
permanent repairs to the switchgear in the CSRB, MEB, Nursing/Allied
Health Building and the Residence Hall. Only the final repairs to the
Lion’s Eye Center remain to be done. The status of repairs in each
building are listed below:
- CSRB: Completed.
- MEB: Completed.
- Nursing/Allied Health: Completed.
- Residence Hall: Completed.
- Lion’s Eye Center: The last of the two main
switchgear breakers has been refurbished and delivered. Within the
next 4-5 days the power to the building will be brought down, the
switchgear cleaned, the refurbished main breaker installed and
permanent building power restored.
- School of Dentistry restoration: Regular weekly
meetings with representatives from the architectural/engineering firms,
the Office of Facility Planning & Control, FEMA and LSUHSC have
continued and will remain as a scheduled item for some time.
- The architect/engineering firm responsible for
the Dental School campus has completed specifications for temporary
repairs to key building systems that, when completed, will allow the
re-occupancy of upper floors of the Clinic and Administration
buildings. The repairs will focus on the building switch gear,
chillers, key building pumps, clinic systems, and safety systems. The
architects are currently using an expedited procurement process to
secure contractors to complete this temporary repair work.
- The 1st of the bid packages for
temporary repairs to building systems at the Dental School has been
completed. It addresses the basic repairs to the building electrical
systems. An expedited procurement process is being used and the
pre-bid walk through was held on site today.
- The initial focus for the project continues to
be the rapid design and completion of emergency work necessary to
allow the rapid re-occupation of upper floors of the Administration
and Clinic buildings.
- Downtown campus restoration: Regular weekly
meetings with representatives from the architectural/engineering firms,
the Office of Facility Planning & Control, FEMA and LSUHSC have
continued and will remain as a scheduled item for some time.
- Significant efforts have been made recently to
develop potential options for hazard mitigation. Initial discussions
with FEMA about some of the concepts proposed have occurred and were
well received. We anticipate that a decision between two primary
options for hazard mitigation of the flood damaged animal care spaces
and critical mechanical & electrical systems of several buildings
should be made soon. Once the decision has been made, the architects
& engineers will begin refining their designs/plans and develop the
necessary cost estimates to allow FEMA to more carefully review the
proposal.
- Pricing is currently being solicited by the
architect for the second environmental remediation contract. It will
address the Residence Hall, Stanislaus Hall, the Nursing/Allied Health
Building, and the Resource Center. The architect currently
anticipates that work under this contract will begin during the week
following Mardi Gras.
- Contracts have been awarded for the repairs to
various types of pumps to supply water and heat to the Residence Hall,
MEB, CSRB, Lion’s Eye Center, Nursing/Allied Health, and Resource
Center. Parts have been ordered and work is expected to begin on the
repairs as parts begin to arrive in late February and early March.
LSUHSC has provided the contractors with the list of priorities by
building for these repairs; however the availability of some parts may
impact on the ability to strictly adhere to the priorities.
- The contract for the repair/replacement of fire
pumps in the Nursing/Allied Health Bldg, the Residence Hall, the
Resource Center, the CSRB, the Lion’s Eye Center and the MEB is
complete. The status of repairs in each building are listed below:
- CSRB: Completed and inspected.
- MEB: Completed and inspected.
- Lion’s Eye Center: Completed and inspected.
- Nursing/Allied Health: Completed and inspected.
- Resource Center: Completed and inspected.
- Residence Hall: Completed and inspected.
- Contracts to repair the fire alarm systems and
their components in downtown campus buildings have been awarded to the
vendors who currently provide annual maintenance to the systems. This
approach will insure that the systems can be re-certified and remain
under the existing maintenance contract. Several of the systems have
been repaired and inspected and work continues in the remaining
buildings.
- Stanislaus Hall: Completed and inspected.
- CSRB: Completed and inspected.
- MEB: Work has been started and is scheduled to
be completed by March 10th.
- Lion’s Eye Center: Completed and inspected.
- Nursing/Allied Health: The contract has been
awarded for the repairs to the fire alarm system. Work is expected to
being shortly as parts become available.
- Resource Center: The repairs required for the
fire alarm system have been identified and the contract has been
issued.
- A contract remains in place to address the repairs
to Animal Care cage washers, bottle washers and sterilizers at the CSRB.
The work on the repairs is almost complete. The steam generators have
been installed and the contract has begun troubleshooting the systems.
Additional damage to a pump in the system has been discovered and a
Change Order to the original contract has been issued.
- The contract for the repairs to the emergency
generators at the CSRB, MEB, Lion’s Eye Center, Nursing/Allied Health
Bldg., Resource Center and the Residence Hall has been awarded. Work on
the repairs will begin on Monday, 2/27/06.
- A contract has been issued for repairs to the
medical air compressors, vacuum pumps and water purifiers at the CSRB,
Lion’s Eye Center and the MEB. Parts are on order and repairs will
begin as soon as the parts begin to arrive.
We hope that you continue to find this information
helpful. Don’t forget that Daily Updates are also posted on the web site
so that you can follow the recovery progress more closely.
|