|
From: Ronnie Smith,
Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #15
Posted: April 22, 2006
The preparations for the return of the Schools of
Medicine, Allied Health and Nursing and the reopening of Stanislaus Hall
and the Residence Hall continue. We remain cautiously optimistic that
these goals will be accomplished as contractors strive to complete their
work and new contracts are issued for critical repairs.
The Office of Facility Planning & Control is continuing to
work closely with us to "carve out" and expedite some key permanent
repairs to portions of the MEB needed to support the return of the Schools
of Medicine, Nursing and Allied Health before the incoming classes begin.
The architects have recently completed plans and specifications for a
project to restore the two large lecture halls, the morgue, the Gross
Anatomy Labs, and the Multidisciplinary Labs and Facility Planning has
approved the use of an expedited process to solicit pricing. Completion of
work under this contract is currently projected for about July 1.
The environmental remediation in the Nursing/Allied Health
Building is progressing on schedule and the work is substantially complete
throughout the building. Repairs to building elevators continue and are
projected to be completed within the next few weeks. Repairs to the
build’s fire alarm system are 95% complete and should be finished shortly.
We are cautiously optimistic that the building will reopen in late April
as planned.
Stanislaus Hall is also targeted to reopen in late April.
The environmental remediation is substantially completed throughout the
building. The repairs to the building elevators are complete and the
inspection of the State elevator inspector has just certified them for
general use. The majority of the build’s pumps are operational; the city
water pumps have recently been installed and the sump pumps are being
connected to building power.
We are continuing to receive shipments of new fitness
equipment for the Wellness Center. The majority of the equipment should be
delivered and installed within the next few weeks. The software for
operating the Center has been installed and is being configured. Supplies
necessary for the operation of the Center are being ordered. Cleaning of
the spaces (floors, bathrooms, etc.) to prepare the Center for use is
underway. We continue to plan to have this new facility available to
faculty, staff and students this summer.
Due to the need to replace a large portion of the floor
tiles in the building, the environmental remediation in the Residence Hall
is a more time consuming process. The old tile has been removed and the
new tile is being installed. The other remediation work in the building is
substantially complete. Elevator repairs continue in the building. Repairs
to the "A" and "C" Towers elevators are substantially complete and the
contractor is now focusing on the "B" Tower. Final inspections will occur
when the repairs on all towers have been finished. The repairs to the fire
alarm system are substantially complete. New refrigerators for the rooms
have been ordered and deliveries will begin shortly. The target for
reopening the building remains mid-May.
The work in the Resource Center has progressed well and
plans are to be able to reoccupy the upper floors in early June. Two
elevators are already certified for use and the remaining repairs are
underway. The environmental remediation is largely completed throughout
the building. Work on the fire alarm system is under contract and work has
begun on preliminary tasks while parts are being delivered. The domestic
water pumps have been delivered and installation will be completed
shortly. We’ve also taken this opportunity (while the Ische Library
collection has been removed for cleaning) to replace the 20 year old
carpet on all three floors. The 4th floor has been completed
and the carpet is being removed and replaced on the 3rd floor
at this time.
Many of the parking lot controls; gates, card readers,
etc. were damaged during the storm. In anticipation of the return of
larger numbers of faculty, staff and students, contracts have been issued
to complete the needed repairs. This will allow us to secure and control
the lots as we had in the past. Work will begin on the larger, closer in
lots to insure the availability of safe and convenient parking.
While the various lots have been closed, we have also
taken this opportunity to make improvements to the Residence Hall parking
lot and to the Student Lots 2 & 3 before we open them up for use again.
Resurfacing of the Residence Hall lot is well underway. New limestone and
concrete "bumpers" will be installed in Lots 2 & 3. The need for
additional lighting in the parking lots is also being evaluated.
The architect/engineering firm responsible for the Dental
School campus completed their 2nd set of specifications for
additional, temporary repairs to key building systems and bids have been
received. The contract for this second set of temporary repairs to the
buildings’ mechanical systems has been awarded and work should begin
within a few days.
Here are highlights of work that has been accomplished
since our last update was posted on Tuesday, April 11th.
- The work on the 2nd contract for environmental remediation contract
addressing the Nursing/Allied Health Building, the Residence Hall,
Stanislaus Hall and the Resource Center has been underway since
mid-March. Progress reports on each building follows:
- Residence Hall: Installation of the replacement floor tiles is
proceeding. The remaining cleaning/remediation required in other parts
of the building is substantially complete.
- Stanislaus Hall: All of the cleaning has been completed on every
floor above the basement. Cleaning of the stairwells and mechanical
rooms is substantially complete. Work continues in the basement spaces
and is anticipated to be completed shortly.
- Nursing/Allied Health: The cleaning has been completed from the
top floor down to the 1st floor. The work required in this
building is substantially completed, except for cleaning required in
the room housing the fire alarm controls. It will be cleaned when the
fire alarm contractor is out of that space.
- Resource Center: All of the upper floors (2nd through 8th)
have been cleaned. Work on removal of sheet rock, etc. on the 1st
floor is almost finished. Work throughout the building is approaching
substantial completion rapidly.
- The accelerated pace of repairs to building elevators continue.
Inspections by the State Elevator Inspector have been requested or will
be requested shortly for the passenger elevators at the MEB, the
Lion’s/LSU Clinic Building and Stanislaus Hall.
- All of the Stanislaus Hall elevators have been certified for
general use.
- All five of the elevators in the Lion’s/LSU Clinic Building have
passed inspection and are now certified for general use.
- The installation of new emergency telephones in the MEB elevators
is underway. As the phones are installed and tested, another
inspection will be scheduled and certification of the elevators will
be requested.
- The contractor has completed repairs to the "A" and "C" Tower
elevators in the Residence Hall, except for the buffers. The
contractor is focused on completing the "B" Tower elevator and will be
working over the weekend.
- Walk To Wellness & Gravier St. Garage: Work has begun on repairs
to the elevators serving both structures. The change out of damaged
elevator pit devices in the Walk to Wellness and the Gravier Street
Garage elevators began on Monday, April 17th.
- The contractor will be replacing the 1st floor elevator
doors on all of the elevators in the Resource Center. The hoist cable
on elevator #3 is undersized and was cited by the State Elevator
Inspector prior to the current contactor receiving the annual
maintenance contract. The former contractor is paying for the
replacement cable and the current contractor will install it. The
replacement cable is in the contractor’s shop.
- School of Dentistry restoration: Regular weekly meetings with
representatives from the architectural/engineering firms, the Office of
Facility Planning & Control, FEMA and LSUHSC continue.
- The 1st of the bid packages for temporary repairs to
building electrical systems and for temporary air conditioning at the
Dental School has been awarded and work has recently begun.
- The temporary chiller and generators are on line at the Dental
School Clinic and Administration buildings and the buildings are
being cooled. The electrical contractor is working on a temporary
electrical power feed.
- The 2nd of the bid packages for temporary repairs to
the buildings’ critical mechanical systems has been developed and the
solicitation of bids has been completed. The bids have been evaluated
by both the architect and LSUHSC and the Office of Facility Planning &
Control has approved the award. The contractor is currently securing
their bonds and insurance and we anticipate that work will begin soon.
- Downtown campus restoration: Regular weekly meetings with
representatives from the architectural/engineering firms, the Office of
Facility Planning & Control, FEMA and LSUHSC have continued and will
remain as a scheduled item for some time.
- The 2nd environmental remediation contact has been
awarded and much of the work has been completed.
- The 3rd environmental remediation contact has now been
awarded and will address the remaining buildings and structures on the
downtown campus. Work should begin shortly as crews completing the 2nd
contract are being freed up.
- The architects are working on a series of smaller projects that
have been "carved out" of the larger permanent repair work to
facilitate the return of the Medical School classes to campus.
- Permanent repairs to building windows are out on bid and are due
by the end of April.
- The replacements for the flood damaged MEB Lecture Rooms seating
have been ordered.
- The contracts for repairs to the parking lot control systems
have been awarded.
- A bid package is being finalized for the permanent repairs to
the MEB Lecture Rooms, the Gross Anatomy Lab, the Morgue, and the
Multidisciplinary Labs. The Office of Facility Planning and Control
has approved an expedited process for securing competitive pricing
so that the award can be completed quickly.
- Contracts have been awarded for the repairs to various types of
pumps to supply water and heat to the Residence Hall, Stanislaus Hall,
the MEB, CSRB, Lion’s Eye Center, Nursing/Allied Health Building, and
Resource Center. The following is the status of progress in each
building:
- Stanislaus Hall:
- All the sump pumps have been installed and have been connected
to building power. The sump pits are being cleaned, so the pumps can
be started.
- City water pumps have been delivered and have been installed.
However, the electronic disconnect needs to be replaced. LSUHSC
Property & Facilities staff is handling this.
- CSRB:
- Domestic hot and cold water pumps have been installed and are
operating.
- The heating hot water pumps have been installed and will be
tested shortly.
- MEB:
- The 3 boiler feed water pumps have been installed and are now
operating.
- The two chemical feed water pumps have been installed and are
operating.
- The brine pumps in the MEB have been installed and are
operating.
- The heating hot water pumps have been installed and successfully
tested.
- We are still waiting on receipt of the rebuilt condensate return
pumps.
- The domestic hot water return pump has been removed for
testing/evaluation.
- Nursing/Allied Health:
- The hot water recirculating pumps have been installed.
- The domestic hot water pumps in the Nursing/Allied Health
Building are being installed.
- We are waiting on the delivery of the city water pumps for this
building.
- Lion’s/LSU Clinic:
- The hot water recirculating pumps have been installed.
- Resource Center:
- Two hot water recirculating pumps have been installed, but the
electrical connections must still be made
- Contracts to repair the fire alarm systems and their components in
downtown campus buildings have been awarded to the vendors who currently
provide annual maintenance to the systems. This approach will insure
that the systems can be re-certified and remain under the existing
maintenance contract. Several of the systems have been repaired and
inspected and work continues in the remaining buildings.
- Stanislaus Hall, CSRB, Lion’s/LSU Clinic Building and the MEB:
Completed and inspected.
- Nursing/Allied Health: Approximately 95% of the repair work has
been completed. Some minor equipment/parts needed to complete work
remain on backorder.
- Residence Hall: The repairs have been substantially completed and
a punch list has been developed. When the punch list is complete, the
State Fire Marshal will be asked to inspect the building.
- Resource Center: The contractor is completing the preliminary work
required while waiting for the remainder of the parts to arrive.
- The contract for the repairs to the emergency generators at the CSRB,
MEB, Lion’s Eye Center, Nursing/Allied Health Bldg., Resource Center and
the Residence Hall has been awarded. Work has begun on several of the
generators, and parts are on order.
- The repairs have been completed on the roof mounted generator at
the MEB. This provides emergency power to the majority of the
researcher’s freezers and walk in coolers in that building.
- All of the damaged stators have been removed and sent to be
rebuilt.
- The contractor has inspected all of the automatic transfer
switches (ATS) in each of the buildings to determine what repairs are
needed.
- The Nursing/Allied Health Building will require a shutdown of
electrical power to the building to work on ATS. This will be
scheduled.
- CSRB: The repair work is complete on the generator. Diesel fuel is
needed and LSUHSC has placed the order.
- Lion’s/LSU Clinic: Most of the repairs have been completed,
however a panel needed for the repairs has not yet arrived. Diesel
fuel is also needed here and will be ordered.
- The MEB, the Residence Hall, the Nursing/Allied Health Building
and the Resource Center are waiting on repairs to be completed to the
stators of their respective generators. As the repaired stators are
delivered, they will be installed.
- A contract has been issued for repairs to the medical air
compressors, vacuum pumps and water purifiers at the CSRB, Lion’s Eye
Center and the MEB. Parts are on order and repairs will begin as soon as
the parts begin to arrive.
- Work under a contract to clean, decontaminate and re-certify the
biosafety cabinets in research labs began on March 15th.
There are 100 cabinets covered under the contract and work is underway.
The Purchasing Department is contacting the departments and coordinating
this work as specific cabinets are identified.
- After experiencing 2 short term power outages in the CSRB, the
switch gear manufacturer’s representative is coming out to perform
further tests of the switchgear to determine the need for additional
temporary repairs. Additional work needed will be defined and submitted
to FEMA, the Office of Facility Planning & Control and ORM.
- Processing of the building content losses submitted to FEMA is in
progress. As additional data on losses is gathered and verified, more
claims will be submitted.
- FEMA has recently eased the burden of documenting the portion of
claims related to supplies/consumables. They will allow us to certify
that the items listed were owned by LSUHSC at the time of the storm,
and will separately determine the "reasonableness" of the replacement
cost estimates.
- Capitalized assets will still require validating documentation for
a 20% sample of the items claimed.
- The replacement of 20 year old carpeting in the Resource Center is
proceeding. The installation of carpeting is complete on the 4th
floor and the installation of the new carpet on the 3rd well
underway. The remainder of the new carpet should be delivered next week.
The scaffold needed to do the carpet replacement on the Library stairs
has been delivered.
We hope that you continue to find this information
helpful. Don’t forget that Daily Updates are also posted on the web site
so that you can follow the recovery progress more closely.
|