|
From: Ronnie Smith,
Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #17
Posted: May 27, 2006
During the three weeks since the last update was
published, two critical buildings have re-opened! St. Stanislaus
Hall, one of the two student residence facilities, reopened on Friday, May
19th as the few remaining issues in that building were
successfully resolved. The Residence Hall began accepting students on
Friday, May 26th as the LSUHSC Facilities and Auxiliaries staff
pushed hard to complete the final cleaning and to get replacement
refrigerators installed in rooms to be occupied. With these two
milestones reached, we have our student housing back to full capacity in
time for the return of students from the Schools of Allied Health,
Medicine and Nursing to the downtown campus as they prepare for their
summer classes. Just nine months after Hurricane Katrina forced the
institution to temporarily relocate all of its classes and operations, the
majority of the downtown campus functions have returned.
The work in the
Resource Center has continued to progress well and plans are to be able to
reoccupy the upper floors around the beginning of June. The environmental
remediation work has been completed throughout the building. Work on the
fire alarm system is largely complete and the few remaining items should
be completed shortly. The carpet replacement in the Library has been
substantially completed and the re-shelving of the Library collection is
nearing completion. While two passenger elevators have been certified
for some time now, work on the final repairs to the remaining elevators is
well underway. The State Fire Marshal has been asked to inspect the
building on Wednesday, May 31st.
If progress continues as hoped, we will have all of the
downtown campus buildings (except for 1542 Tulane) opened and back in use
by the beginning of June. As additional buildings come back into service,
we wish to remind you that we have a very limited number of building
maintenance and custodian staff. The understanding, patience and support
of all faculty, staff and students of this reality is appreciated.
The planned
improvements to selected parking lots are proceeding. The resurfacing of
the Residence Hall lot and the improvements to Student Lot #2 and #3 are
substantially complete. All that remains is completing the installation
of wheel stops. Repairs to the parking lot access control systems have
also begun.
The substantial
temporary repairs to the Clinic and Administration Buildings at the Dental
School continue at a rapid pace. Two contractors have received contracts;
one is addressing the buildings’ electrical systems and the 2nd
is responsible for the other critical mechanical systems. Both
contractors have been instructed to complete their work by June 30th,
although selected equipment items needed may not be available from
manufacturers within that timeframe. Regardless, the contractors are
doing all that they can to meet this aggressive schedule. Details on
their progress are provided below.
The environmental
remediation work has been underway at 1542 Tulane for approximately three
weeks and is on schedule so far. The contract for temporary repairs to
the building electrical and key mechanical systems at 1542 Tulane has
recently been bid and awarded. This contract will provide electrical
power to the upper floors and to help stabilize conditions within the
building.
Here are
highlights of work that has been accomplished since our last update was
posted on Friday, May 5th.
- The work on the 2nd contract
for environmental remediation contract addressing the Nursing/Allied
Health Building, the Residence Hall, Stanislaus Hall and the Resource
Center has been underway since mid-March and work has been completed in
all of the buildings. The new tile installation is substantially
complete, the new tile is being sealed and the finishing work is
underway.
- Work on the 3rd
environmental remediation contract addressing the balance of the
buildings and facilities on the downtown campus is underway. The
contractor has started the remediation work in the basement, 7th
and 8th floor of 1542 Tulane Ave. The basement is expected
to require the majority of the 45 day contract to complete, while work
on the upper floors should average approximately 10 days per floor.
While remediation is underway, access to the basement, 1st
floor and the upper floor(s) being cleaned will be restricted.
- The accelerated pace of repairs
to building elevators continue. Elevators that have been repaired,
inspected and certified for passenger use include:
- All of the Stanislaus Hall
elevators.
- All five of the elevators in
the Lion’s/LSU Clinic Building.
- The MEB elevators.
- The elevators in the
Residence Hall.
- Elevators 3, 4 & 5 in the
Nursing/Allied Health Building.
- Two passenger elevators in
the Resource Center.
- The temporary repairs to the
School of Dentistry Clinic and Administration buildings continue.
- The temporary chiller and
generators are on line at the Dental School Clinic and Administration
buildings and the buildings are being cooled.
- Demolition of flood damaged
building materials related to the environmental remediation is well
underway in the basements (estimated to be 90% complete) and on the 1st
floors of both the Clinic and Administration buildings (estimated to
be more than 50% complete).
- Installation of critical pipe
insulation in the basement is complete.
- The electrical contractor is
continuing to progress with the work on a temporary electrical power
feeds and the installation of temporary conduit, etc.
- The temporary emergency
generator is in place and ready for operation once the connections
are completed.
- The transfer switch and
transformer for normal building power is in place.
- All of the tap boxes have
been received and all but one has been installed.
- All five of the buss ducts
providing power to the upper floors are powered up.
- Temporary power from the
generator is now available in the building.
- The temporary switch gear
has been delivered and installation is approximately 50% complete.
- The air compressor has been
received on site.
- Demolition of housekeeping
pad is well underway – estimated to be 70% complete.
- The domestic water pumps are
installed and operating at the Dental School and the two main
buildings have partial water pressure. (The City has been notified of
the low pressure to the buildings.) Domestic water is still off while
isolation valves being installed to isolate damaged sinks on 7th
floor.
- Concrete pads removed for air
compressors in Power Plant.
- Housekeeping pads for
temporary equipment being placed in the basement are being poured –
50% complete.
- Valves for CHW system have
been installed. The system is being checked for leaks and will then
be refilled.
- The floor is being leveled
for the channel line to be poured to support the temporary building
switchgear.
- A PO is being issued to empty
flooded elevator pits in anticipation of repairs to begin to the
building elevators.
- The temporary boiler has been
delivered to the site and installation has begun.
- Permanent repairs to building
windows on the downtown campus have been bid and the contract has been
awarded. The contractor is now on site and beginning work.
- A bid package for the permanent
repairs to the MEB Lecture Rooms, the Gross Anatomy Lab, the Morgue, and
the Multidisciplinary Labs has been awarded, with the assistance of the
Office of Facility Planning and Control. The pre-construction meeting
was held on 5/25 and the work will begin on 5/30. The contract requires
completion of the work within 45 days.
- Contracts have been awarded for
the repairs to various types of pumps to supply water and heat to the
Residence Hall, Stanislaus Hall, the MEB, CSRB, Lion’s Eye Center,
Nursing/Allied Health Building, and Resource Center. The following is
the status of progress in each building:
- Stanislaus Hall:
- The sump pumps have been
installed and are operating.
- The chilled water system
has been refilled and air conditioning is available in the building
again.
- City water pumps have been
delivered and have been installed and are operating.
- The domestic hot water
pumps are installed and operating normally.
- CSRB:
- Domestic hot and cold water
pumps have been installed and are operating.
- The heating hot water pumps
have been installed and have been tested.
- MEB:
- The 3 boiler feed water
pumps have been installed and are now operating.
- The two chemical feed water
pumps have been installed and are operating.
- The brine pumps in the MEB
have been installed and are operating.
- The heating hot water pumps
have been installed and successfully tested.
- We are still waiting on
receipt of the rebuilt condensate return pumps.
- The domestic hot water
return pump has been removed for testing/evaluation.
- Nursing/Allied Health:
- The hot water recirculating
pumps have been installed.
- The city water pumps have
been installed.
- The domestic hot water
pumps have been installed and are operating in the Nursing/Allied
Health Building.
- Lion’s/LSU Clinic:
- The hot water recirculating
pumps have been installed.
- Resource Center:
- Two hot water recirculating
pumps have been installed and are operating.
- The domestic hot water
return pump has been installed and is operating.
- Contracts to repair the fire
alarm systems and their components in downtown campus buildings have
been awarded to the vendors who currently provide annual maintenance to
the systems. This approach will insure that the systems can be
re-certified and remain under the existing maintenance contract.
Several of the systems have been repaired and inspected and work
continues in the remaining buildings.
- CSRB, Lion’s/LSU Clinic
Building and the MEB: Completed and inspected.
- Stanislaus Hall: A temporary
occupancy permit has been issued and the list of deficiencies is being
addressed and will be resolved shortly.
- Nursing/Allied Health: A
temporary occupancy permit has been issued and the identified
deficiencies will be addressed within the next few weeks.
- Residence Hall: The repairs
have been substantially completed. Final repairs have been made to
door closers and the State Fire Marshal has inspected the building and
approved reoccupancy.
- Resource Center: Only minor
issues remain to be addressed by the contractor and they are expected
to be resolved shortly. The State Fire Marshal has been asked to
inspect the building on May 31st.
- The contract for the repairs to
the emergency generators at the CSRB, MEB, Lion’s Eye Center,
Nursing/Allied Health Bldg., Resource Center and the Residence Hall has
been awarded. The following is the most recent status of the repairs:
- The repairs have been
completed on the roof mounted generator at the MEB. This provides
emergency power to the majority of the researcher’s freezers and walk
in coolers in that building.
- CSRB – the generator has been
repaired, fueled, and is ready for use as needed.
- Lion’s/LSU Clinic Building –
the generator has been repaired, fueled, and is ready for use as
needed.
- Residence Hall – Both of the
emergency generators for the Residence Hall have been installed and
are being connected to the building’s electrical systems.
- The rebuilt stators for the
MEB, Resource Center and Nursing/Allied Health have been delivered.
Installations are complete at the Nursing/Allied Health and Resource
Center buildings and the MEB installation should be completed early
next week. The electrical connections to the respective building
systems must still be made.
- The contractor has inspected
all of the automatic transfer switches (ATS) in each of the buildings
to determine what repairs are needed.
- The Nursing/Allied Health
Building will require a shutdown of electrical power to the building
to work on ATS. This will be scheduled.
- After experiencing 2 short term
power outages in the CSRB, the switch gear manufacturer’s representative
was requested to perform further tests of the switchgear to determine
the need for additional temporary repairs.
- With switchgear elements
tested and calibrated and all CSRB installed systems isolated or
tested, testing of the CSRB internal electrical feeders was
undertaken. These tests revealed 3 damaged electrical feeders. They
included the feeders for the Lake and River side riser feeders (one
200 foot and one 50 foot run which provides lighting and receptacle
power) and a 250 foot run for the Lake side Air Conditioning and
Exhaust units.
- Work to replace the damage
feeders commenced Tuesday, May 9, 2006 with the removal of existing
500 MCM (about a ¾ inch copper cable) electrical cables for the Air
Conditioning and Exhaust Feeder. This feeder is made of three sets of
4 cables (3 hot and one neutral) run through three 4 inch conduit.
During attempts to remove the first (and damaged) set of cables that
make up this feeder, the cable became stuck.
- During an emergency outage on
Wednesday, May 10, 2006, the contractor and LSUHSC Facilities staff
removed the stuck cable and revealed a 4 foot threaded rod in the
duct, probably left from construction of the CSRB. This threaded rod,
which may have damaged the cable during original installation, and the
introduction of water to the conduit by Katrina flooding, are one of
the suspected sources of our electrical problems. Damage to the other
feeders is yet to be determined. Since removal of this damaged cable
from the electrical system, there has been no loss of power to the
CSRB.
- An independent engineering
analysis concluded that all cables of the affected feeders, not just
damaged cables, should be replaced, and a contract was awarded on
Friday, May 12, 2006, to accomplish the work.
- Work began on Saturday, May
13th to replace all the building electrical feeders.
- Work will result in
testing, isolation and removal of damaged cables of the CSRB riser
feeders (750 MCM cable is about 1 inch diameter copper or about 5
pounds per foot meaning each set weighs about 20 pound per foot).
Removal of damaged cables from each feeder will also establish the
baseline for the amount of time needed to pull and replace the
remainder of the cables.
- By the end of the day on
5/13, the contractor finished pulling the A riser feeder; one
conduit of 4 cables. Pulling and preparation took about 5 hours.
The conduit carrying the feeder cables was not damaged and no
surprises were found. This was the faulty set of cables for this
feeder, so we are in an improved position even though much work is
left to do. Time did not allow the contractor to address the B
feeder.
- Additional outages will be
necessary to complete the removal and reinstallation of remaining
affected feeder cables. All work will be done evenings and weekends.
No more than half of the building will be without power and air
conditioning during these outages.
- The replacement of 20 year old
carpeting in the Resource Center is proceeding smoothly. The
installation of new carpeting is substantially complete on all of the
Library floors and the re-shelving of the Ische collection is nearing
completion.
- A contract has been issued for
repairs to the medical air compressors, vacuum pumps and water purifiers
at the CSRB, Lion’s Eye Center and the MEB. An updated status follows:
- The damaged medical air and
vacuum pumps and the damaged water purifiers have been removed from
the CSRB and the Lion’s/LSU Clinic Building.
- The medical air and vacuum
pumps have been installed at the CSRB.
- In the MEB, the contractor
has removed the medical air and vacuum pumps. The contactor is still
working to remove the housekeeping pad in the MEB. The vacuum pumps
have been delivered and installation will begin early next week.
- The preparations for the
installation of the new or repaired pumps at the Lion’s/LSU Clinic are
complete.
- Upgrades to the Seminar Rooms
on the 3rd floor of the MEB have been underway for some
time. New carpeting has been laid, new and improved lighting has been
installed, the old chalk boards have been replaced with new marker
boards, and wireless network connectivity is being installed. These new
teaching facilities should be available for use by the students who
begin their next semester on the New Orleans campus.
- The Roman Street Parking Garage
emergency power panel, which controls the electricity to the 1st
floor lighting and emergency lights in the stairwells, has been repaired
and is re-energized.
- The replacement of carpet and
tile in both Medical Center Stores and Campus Office Stores has been
completed. Both stores are in the process of moving their operations
back into these spaces on the 2nd floor of the MEB.
-
The exhaust fans powering the fume hoods in the MEB are now working.
The Safety Department has begun to certify the hoods in the building.
-
LSUHSC Facility Services is now located in their permanent offices on
the 2nd floor of MEB, Suite 2110. The work order system is up and
running and can be accessed through the LSUHSC website. Only the
Downtown Campus work order section is attended. The phone number is the
same, 568-7716.
Please continue to follow our
progress through our Daily Updates that are also available on the web
site.
|