|
From: Ronnie Smith,
Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #21
Posted: July 25, 2006
There has been an
intensive focus on restoring some of the key areas in the Medical
Education Building to support the return of classes to the downtown
campus. In particular, work has focused on the two large Lecture
Rooms, the Morgue, the Gross Anatomy and Swing Labs, the MDL, and the
Seminar Rooms on the 3rd floor. The Seminar Rooms have been
re-carpeted, re-painted, new ceilings installed, new white boards
installed, and wireless network connectivity is now available in each
room. We trust that this will enhance the learning experience for our
students who use those rooms. Long lead times on some items and problems
with the availability of certain materials have made some of the other
work particularly challenging. Some accommodations may be required during
the 1st few weeks of classes, but we should be completing the
remaining work soon. You will find a detailed listing of the progress made
in the MEB restoration below.
The two contractors
responsible for making the temporary repairs to the School of Dentistry’s
Clinic and Administration Buildings continue to press towards completion
of their respective contracts. Both contracts are estimated by the
architects overseeing this work to be more than 95% complete. Details on
this work can be found in the highlights section below.
The efforts to complete
temporary repairs that will allow us to reoccupy the last of our major
buildings on the downtown campus also continue. The environmental
remediation work at 1542 Tulane Ave. is largely completed. The contractor
who has been selected to make temporary repairs to the building’s
electrical system and other key mechanical systems is scheduled to begin
work shortly. Parts have been ordered and should begin arriving soon.
LSUHSC Facilities and Property has been working on
plans to provide temporary protective measures for critical building
components for the 2006 hurricane season. FEMA is generally willing to
reimburse the costs of reasonable, effective measures taken to protect the
temporary repairs that have been made, so they will be an integral part of
this process and plans are finalized and bids are solicited. A specific
proposal from one contractor is anticipated to be received at the end of
this week.
Both of the design teams (architects & engineers) are
continuing to work closely with our FEMA team to reconcile their
assessments of the damage to the various buildings with the FEMA team’s
assessments. This task is critical, as it will insure that as
specifications are developed for the permanent repairs, the scope of work
in the bids will be fully eligible for FEMA reimbursement.
The eventual permanent repairs will also involve the
elevation of critical building components and functions to prevent
repetitive damage should a similar event ever occur. The planning for
this work by both the downtown campus and Dental School design teams is
underway. Concepts continue to be refined and shared with FEMA as they
are developed. Recently, at the request of LSUHSC, the design team for
the downtown campus has been focusing on developing plans to rebuild the
Cohn Learning Center on an upper floor of the Lion’s/LSU Clinic Building
as part of the permanent repairs planned for this building.
Here are highlights of work that has been
accomplished since our last update was posted two weeks ago.
- The temporary repairs to the School of Dentistry
Clinic and Administration buildings continue.
- The hot water
heaters are in place and being connected to the building plumbing.
- The air dryer for
medical air has been installed.
- Some of the old
black iron pipe is being replaced with copper to meet current codes.
- Sump pumps are in
place and connected and the pump covers have been installed.
- The temporary
chillers are now connected to building power.
- The Dry Vac has
been delivered and installed.
- The Wet Vac system
has been delivered and set in place (vacuum producer, tank, & pumps).
The connections to the building systems will be made shortly.
- Boiler/Hot Water
System:
- Steam traps have
been installed.
- The expansion
tank has been set in place, but needs to be piped-in.
- Hot water heaters
are connected to the building’s water supply, and they need to be
piped to steam lines, hot water return lines, the expansion tank, &
the mixing valve.
- The chilled water
is connected to Chiller #1, while the connections being completed to
Chiller #2.
- The air compressors
have been piped in and the electrical connections are completed. The
controls need to be programmed and the air dryers need to be tied into
the system.
- The deionized water
system has been piped in to the building and the electrical
connections are complete.
- The ice water
system is scheduled to be installed next week.
- The contractor has begun fire sealing all of the
floor/ceiling penetrations caused by the new temporary switchgear
conduit.
- The elevator contractor is removing damaged
parts and completing their evaluation of the damage to the elevators.
- The fire alarm
system has been installed and inspected. A telephone line is still
required to all the system to call out when activated.
-
- The contractor for the permanent repairs to the
MEB Lecture Rooms, the Gross Anatomy Lab, the Morgue, and the
Multidisciplinary Labs has crews on site and is progressing on the
work.
- The repairs to MDL
#6 in the MEB are complete and the room is ready for the final
inspection.
- The new epoxy
flooring was installed over the weekend of 7/15 in the Gross Anatomy
Lab, the Swing Lab and the Morgue. An additional epoxy coating will
be applied to the Morgue floor on Tuesday, 7/25. This 2nd
coating provides additional protection from higher concentrations of
certain chemicals.
- The new casework
for the Gross Anatomy Lab, the Swing Lab and the Morgue should be
delivered to the site beginning on 7/24 and the installation in the
Gross and Swing Labs at that time.
- The casework
installation in the Morgue will begin on Wednesday, 7/26 following
the application of the 2nd epoxy layer.
- The new
countertops will be installed in all three rooms beginning on
Thursday, 7/27.
- The contractor
will also install the emergency shower in the Morgue at the same
time that the casework is installed.
- The installation of
the new carpet is complete in Lecture Room A & B.
- The pedestals to
support the seating and table tops have been delivered.
- The installation
of the pedestals is complete in Lecture Room B.
- The installation
is underway in Lecture Room A and should be finished shortly.
- The 1st
shipment of table tops has arrived and they are being installed in
Lecture Room B. The new electrical and network wiring is being pulled
to the table tops as they are being installed.
- The installation of
the vinyl wallpaper is completed in Lecture Rooms A & B.
- The installation of
the acoustic wallpaper (on the side walls) in Lecture Rooms A & B has
been almost finished, however an additional roll of the wallpaper is
required to replace a roll that contained flaws and could not be
installed.
- The installation
of the trim still remains to be done as well.
- The network cable
has been pulled and bundled beneath the floor in “B”.
- The electrical
wiring has been pulled in both “A” and “B” and it is ready to be run
to the table tops when they have been installed.
- The installation of
the new presentation equipment is underway. The projectors have been
installed in Lecture Room B.
- The replacement air
conditioning unit that serves the 2nd floor of the MEB was connected
over this past weekend. This required a chilled water outage in the
building.
- Spare compressors for the Morgue coolers are on
order.
- Work on the 3rd environmental
remediation contract addressing the balance of the buildings and
facilities on the downtown campus is approaching completion. While the
remediation work is underway, access to the entire building remains
restricted. When air sampling results are received indicating that the
remediation has been successful, we will again allow access to the
building. Specific updates on progress are as follows:
- 8th Floor: Cleaning is complete.
- 7th Floor: Cleaning is complete.
- 6th Floor: Cleaning is complete.
- 5th Floor: Cleaning is complete.
- 4th Floor: Cleaning is complete.
- 3rd Floor: Cleaning is complete.
- 2nd Floor: Cleaning is complete.
- 1st Floor: Cleaning is completed.
- Mechanical Rooms: All of the mechanical rooms
have been cleaned.
- Duct Work: All of the duct work has been
cleaned.
- Basement: All of the walls scheduled to be
demolished have been taken down and the debris removed. The final
cleaning is underway and is expected to be completed shortly.
- Post-cleaning testing and monitoring results are
starting to come in and generally look good. A few rooms have been
identified as needing re-cleaning and that work has been performed as
it has been identified. Retesting will verify that the cleaning was
sufficient.
- The cleaning has progressed far enough that the
contractor who is making temporary repairs to the building electrical
and mechanical systems can freely access the basement.
- Bids have been received, evaluated and a contract
has been awarded for additional repairs to the chilled water pump and
related mechanical/electrical components in the Central Utility Plant,
attached to the Roman St. Garage. These additional repairs will insure
that we have sufficient chilled water capacity for the hottest summer
months and also have a redundant pumping system should one fail or
require repairs.
- The contract to make temporary repairs to the
building’s critical electrical & mechanical systems at 1542 Tulane Ave.
has been awarded. The contractor has ordered the parts and materials
necessary for the contract and work will begin shortly. The contract
includes an aggressive schedule for completion.
- The permanent repairs to building elevators
continue. Elevators that have been repaired, inspected and certified for
passenger use include:
- All of the Stanislaus Hall elevators.
- All five of the elevators in the Lion’s/LSU
Clinic Building.
- Repairs to the damaged elevator floors have
been completed.
- The MEB elevators.
- Repairs to the damaged elevator floors are now
complete.
- The elevators in the Residence Hall.
- Repairs to the damaged elevator floors in the
“B” and “C” towers are now complete.
- The passenger elevators in the Nursing/Allied
Health Building.
- Repairs to the damaged elevator floors are now
complete.
- Two passenger elevators in the Resource Center.
- The inspections of a 3rd passenger
elevator and the freight elevator are being scheduled with the State
Elevator Inspector.
- Roman St. Parking Garage – The contractor has
begun making repairs to the two passenger elevators.
- Dental School Clinic and Administration
Buildings: The elevator pits have been pumped out and the contractor
is now able to access the pits and make the final determinations
regarding damage and needed repairs.
- Parts required for the repairs have been
ordered.
Please
continue to follow our progress through our Daily Updates that are also
available on the web site.
|