|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #43
Posted: May 25, 2007
The final, detailed proposal
for the permanent repairs and hazard mitigation for
the Lions/LSU Clinic Building has been forwarded to
FEMA for their review and approval. The plan
includes rebuilding the Cohn Learning Center on the
6th floor, building an additional
external stairwell on the front of the building, and
elevating the critical mechanical, electrical and
plumbing components from the 1st floor to
the 2nd floor to protect it from any
future flooding. The refined cost estimates
prepared by the architects demonstrate that the
project is cost effective, so we are optimistic that
FEMA will approve the proposal. When the final
approvals are received, the construction documents
can be prepared and the bids for the construction
will be issued.
The contract to make temporary
repairs to the vivarium on the 1st floor
of the CSRB has recently been awarded and work
should be underway shortly. The completion of these
temporary repairs will provide additional vivarium
space to support the research community.
Concurrently, the first proposal for permanent
repairs and hazard mitigation for the CSRB and MEB
has been crafted and shared with FEMA. The concept
addresses issues in both buildings; moving Animal
Care facilities out of 1st floor
locations in the MEB and CSRB and elevating them
into a multistory addition that would be constructed
on the rear of the CSRB. Critical mechanical,
electrical, and plumbing equipment would be elevated
in both buildings, and a bank of emergency
generators to run non-life safety critical functions
in the nearby buildings would be installed in the
addition. An emergency operations center is also
contemplated. If FEMA determines that the concept
is feasible and reasonable, the architects will move
forward with the design work and preparation of the
final proposal.
The downtown campus architects
have recently discussed their initial concepts for
permanent repairs and mitigation for the
Nursing/Allied Health Building, the Resource Center,
and the Student Residence Hall with LSUHSC and
Facility Planning. All of the concepts appear
reasonable and are less complex that the proposals
noted above. As each concept is developed, it will
be forwarded to FEMA for their initial review and
comment.
The work to prepare the Dental
School campus for the return of the School in late
summer continued. The contract to establish the
Central Sterilization function on the 3rd
floor of the Clinic Building has been awarded. The
contract for the replacement of the ceiling tiles
and grid on the upper floors of both buildings has
also been awarded. Work on the final environmental
remediation and duct cleaning has progressed rapidly
and remains on schedule. The upgrade of the network
infrastructure continued as all of the cable trays
have been installed and a significant portion of the
new cable has been pulled in the Clinic Building.
The Dental School architects continue to refine
their concept for the permanent repair and
mitigation of the Clinic and Administration
Buildings, and the Power Plant. The current concept
envisions constructing an annex to the Clinic
Building that would house critical clinical
functions previously located on the 1st
floor of the Clinic, along with other critical
functions and the mechanical, electrical and
plumbing components that had been in the basement.
The contractors working at 1542
Tulane Ave. have made good progress during the past
few weeks. The elevator contractor is striving to
have one elevator repaired and certified for normal
use within the next week or so. The electrical and
mechanical contractors have been completing repairs
to the steam system and the hot water heat
exchangers, running power to new pumps, and
preparing for the installation of additional
equipment that has been on order and should be
received soon.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Project to Make Temporary
Repairs to the Dental School:
- The final environmental
remediation and duct cleaning contract is
progressing smoothly. The focus of the work has
been within the Clinic Building. Zimmer has
been working 24 hour days. When the contractor
completes their duct cleaning or their
remediation cleaning of an area, an independent
environmental consultant must inspect the spaces
and test a variety of samples to verify that the
cleaning has been thorough and that the spaces
are suitable for occupancy. The requirement for
some re-cleaning is common.
- Duct cleaning is
underway. As the cleaning is completed test
samples are taken and the interior
insulation within the ducts is
coated/encapsulated.
- The remediation work
in the interior spaces is also well
underway.
- As stairwells are
cleaned, the required testing is
conducted. Following the receipt of
clearances, the walls are painted with
an antimicrobial paint.
- As interior spaces
(halls, offices, etc.) are remediated,
air sampling is conducted. The cleaned
spaces will remain sealed until the
clearances are received.
- Remediation Status:
- All four stairwells
have been cleaned.
- Test results are
pending on two stairwells.
- The other two
stairwells have been painted with the
antimicrobial paint.
- Clinic 1st Floor:
- Duct work has been
cleaned.
- Test results
are pending.
- Interior spaces
have been cleaned.
- Clearances
have been received.
- The
containment has been removed.
- Clinic 2nd Floor:
- Duct work has been
cleaned.
- Test results
are pending.
- Interior spaces
have been cleaned.
- Test results
are pending.
- The
containment remains in place.
- Clinic 3rd Floor:
- Duct work has been
cleaned.
- Test results
are pending.
- Interior spaces
have been cleaned.
- Test results
are pending.
- The
containment remains in place.
- Clinic 4th Floor:
- Duct work has been
cleaned.
- The interior
insulation has been
coated/encapsulated.
- Interior spaces
are being cleaned.
- Clinic 5th Floor:
- Duct work is being
cleaned.
- Interior spaces
are being cleaned.
- The project to upgrade the
network infrastructure has moved forward.
- The installation of
the new cable trays in the spaces above the
suspended ceiling has been completed.
- New conduit has been
installed on the 3rd and 4th floors of the
Clinic Building.
- Wire mold and new
jacks are being installed on the 2nd and 3rd
floors of the Administration Building.
- Wire mold and new
jacks are being installed on the 5th floor
of the Clinic Building.
- Network cable is being
pulled on the 3rd, 4th, 5th, 6th and 7th
floors of the Clinic and the network drops
are being connected.
- The contract to replace
the ceiling tiles and grid in the Clinic and
Administration Building has been awarded to the
low responsive bidder. We are cautiously
optimistic that this work will begin within a
short time.
- Demolition work continues
in Auditoriums A and B located in the
Administration Building in preparation for the
planned renovations.
- Zimmer is working in
Auditorium B jack hammering the floor to
remove the concrete that forms the slope in
the floor.
- The emergency telephone
lines have been connected to Elevators #1 and #2
in the Clinic Building, while the elevator
repairs have continued in the Administration
Building.
- Frischhertz has pulled
new wire into the Automatic Transfer Switch
and over to each disconnect for the three
elevator controllers. This will allow the
elevators to be powered by the emergency
generator should a loss of building power
occur.
- Schindler Elevator now
has power to all three controllers in the
Administration Building penthouse.
- Schindler worked on
the electronics in the elevator control
panels in the Administration Building.
- Repairs are underway
to Elevator #2 in the Administration
Building penthouse.
- They are also working
in the penthouse on the controller for
Elevator #3.
- Pflueger installed small
switchgear on the 2nd level of the Power Plant
to service the cooling tower.
- They installed
additional indicator lights on the motor
control center and serviced several fuses
that were blown.
- Pflueger started
running a 4 inch conduit on the second level
of the Power Plant.
- They continue working
on the installation of the motor control
center switches.
- BellSouth/AT&T installed a
telephone line for the fire alarm service;
running the line from the Room 5312 to Room 2315
where the fire alarm panel is located in the
Clinic Building.
- We have started the
process of removing all of the chemicals that
were stored in the basement of the Clinic
Building.
Project to Make Temporary
Repairs to 1542 Tulane Ave.:
- Stratos Elevator is
working to complete the repairs to Elevator #3
in order to request the final inspection and
certification by the State Elevator Inspector.
- The communications
cable for the elevator has been installed.
- Final repairs and
adjustments are being made.
- The inspection will be
scheduled for next week.
- Ordes Electrical installed
new breaker panels in the engine room for Floors
1 through 7.
- Wire has been pulled
to the new panels.
- Work is underway on
the breaker panel that supplies power to the
exterior lighting for Floors 1-7.
- A new breaker panel
for the building pumps is being installed.
- The breakers for the
480 volt pumps are being installed.
- Arc Mechanical has begun
the installation of a new heat exchanger in the
basement.
- Arc Mechanical is removing the damaged air
compressors and pumps from the basement.
- Arc Mechanical is testing
all the valves in the basement.
- The new steam condensate
pumps are being installed.
Downtown Campus Landscaping
Project:
- The contractor has started
installing empty conduit under the sidewalks and
driveways to allow completion of the irrigation
systems.
- A large plant order was
received recently. The planting will begin
shortly.
MEB Cafeteria Project:
- Completing the demolition
and building the construction walls were the
main focus of the contractor initially.
- The ceiling demolition
and the removal of the old ceiling lights is
complete.
- The wall dividing the
old dining room from the 3rd
floor hallway has been demolished.
- The Air Handling Unit
has been removed, as has the portion of the
duct work that will not being reused in the
new design.
- The construction wall
separating the 3rd floor hallway
from the construction area has been
completed.
- The flooring contractor
starting cutting the pattern in the floor and
began to demolish the rest of the terrazzo
floor.
CSRB Temporary Vivarium
Repairs:
- The contract to make
temporary repairs to the Vivarium space on the 1st
floor of the CSRB has been awarded and the
Notice To Proceed has been issued. Work will
begin shortly.
We encourage you to follow the details of our progress
through the daily updates which are posted on the web site..
|