From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #44
Posted: June 8, 2007
The past two weeks have had
contractors focusing on the many projects that have
been underway for some time now. The contractor
completing the final environmental remediation and
duct cleaning has made good progress in the Dental
School Clinic Building and some of his crews have
shifted over to the Administration Building. At the
same time, the crews working on the upgrade of the
network infrastructure in the two Dental School
buildings have been coordinating closely with the
remediation crews to insure that their work doesn’t
stop. As a result, they have been making steady
progress as well.
The new contracts for
installing the new ceiling tile and grid in the
Clinic and Administration Building and for restoring
the Central Sterilization unit have both gotten
underway. The crews installing ceiling tiles and
grids are also coordinating closely with the
remediation teams. The ceiling tile crew has
completed the grid installation on the 2nd
floor of the Clinic Building and the sub-contractors
are following behind installing the light fixtures
and sprinkler heads. The initial demolition needed
for the Central Sterilization project has begun.
The temporary repair work has
also been steadily progressing at 1542 Tulane Ave.
We are hopeful that we will have a certified
passenger elevator operating in the next week. The
power for the large building pumps is being
connected and additional transformers have arrived
and have been installed. Cable is being pulled to
the transformers at this time.
We are still waiting to hear
back from FEMA on our various 406 Hazard Mitigation
proposals. We remain optimistic that the final
proposal for the Lions/LSU Clinic will be approved.
The conceptual design of the 406 Mitigation proposal
that addresses both the CSRB and the MEB is also
under consideration and we believe that it will be
well received. We hope to get approval for a
proposal to provide additional protection for the
many building elevators throughout the downtown and
Dental School campuses.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Project to Make Temporary
Repairs to the Dental School:
- The final environmental
remediation and duct cleaning contract is
progressing smoothly. The focus of the work has
been within the Clinic Building and as that is
completed, the crews are moving to the
Administration Building.
- When the contractor
completes their duct cleaning or their
remediation cleaning of an area, an
independent environmental consultant must
inspect the spaces and test a variety of
samples to verify that the cleaning has been
thorough and that the spaces are suitable
for occupancy. The requirement for some
re-cleaning is common.
- Remediation Status:
- Clinic 1st Floor:
- Duct work has been
cleaned.
- Test results are pending.
- The interior insulation has been coated/encapsulated.
- Interior spaces have been cleaned.
- Clearances have been received.
- The containment has been removed.
- Clinic 2nd Floor:
- Duct work has been cleaned.
- Test results are pending.
- The interior insulation has been coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been removed.
- Clinic 3rd Floor:
- Duct work has been cleaned.
- Test results are pending.
- The interior insulation has been coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been removed.
- Clinic 4th Floor:
- Duct work has been cleaned.
- Test results are pending.
- The interior insulation has been coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been removed.
- Clinic 5th Floor:
- Duct work has been cleaned.
- Test results are pending.
- The interior insulation has been coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been removed.
- Clinic 6th Floor:
- Duct work has been cleaned.
- Test results are pending.
- The interior insulation has been coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been removed.
- Clinic 7th Floor:
- Duct work has been cleaned.
- Test results are pending.
- The interior insulation has been coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been removed.
- Clinic 8th Floor:
- Duct work cleaning has not begun.
- Interior spaces have not been cleaned.
- Admin 2nd Floor:
- Duct work cleaning is underway.
- Interior spaces are being cleaned.
- Admin 3rd Floor.
- The A/C registers and flex duct is being removed from the 3rd floor of the Administration Building.
- The project to upgrade the network infrastructure has progressed.
- Boe-Tel continued with the installation of the new network cables
on the 6th and 7th floors.
- They are making all the terminations on the 6th floor.
- They have been testing
the new connections made on the 5th
floor and every connection tested has passed.
- NV-I x-rayed the new network closet
locations in the Clinic Building in preparation for core drilling.
- Boe-Tel is working in the ceiling of the
porch area pulling cable outside the Clinic Building.
- Boe-Tel resumed work on the 3rd
floor pulling network wire to each teaching
bay in the Clinic Building through the
Sealtite conduit previously installed.
- Boe-Tel continues pulling network wiring
on the 2nd, 3rd, and 4th
floors in the Clinic Building.
- The contract to replace
the ceiling tiles and grid in the Clinic and
Administration Building has been awarded and
work has gotten underway.
- Frischhertz (the electrical
sub-contractor) is working the 3rd floor
removing lights in the halls and raising
lights in other areas.
- MCC (the mechanical sub-contractor)
surveyed the building for all the A/C drops
to follow behind the ceiling installers.
- Firetrol is working throughout the whole
Clinic Building installing new sprinkler
heads and re-positioning old ones as part of
the project to replace ceiling tiles.
- Landis started the lay out of the new
ceiling tile grid on the 2nd floor of the
Clinic Building.
- Frischhertz followed behind Landis
installing the existing light fixtures
into the newly installed grid.
- MCC followed behind Frischhertz
installing the replacement flex duct for
the A/C vents.
- Landis has
completed the 2nd floor
Clinic area ceiling grid installation.
- Light fixtures and
ceiling tiles are now being installed on
the larger side of the 2nd
floor.
- Landis has moved a
crew to the 8th floor to raise lights in
preparation for the ceiling grid
installation.
- Schindler Elevator has
been working on completing repairs in the
Administration Building.
- They have been
repairing or replacing damaged elements in
the elevator pits.
- They are replacing the roller guides in
the basement.
- They are working on
the governor cables in the elevator pits.
- BellSouth/AT&T installed a
telephone line for the fire alarm service;
running the line from the Room 5312 to Room 2315
where the fire alarm panel is located in the
Clinic Building.
- They have been working
on making the connections to the new phone
blocks.
- AT&T spliced in the cable in the
sub-basement that connects the telephone
cables from the 5th floor to the
wires to the manhole outside the building.
- A & A has completed core drilling 4" holes
for the new network closets in Rooms 5312,
4329b, 3312g.
- A & A has moved over
to the Administration Building and are
finished with the 3rd floor core
drilling.
- The contract to restore the Central
Sterilization function in a 3rd floor
space has been awarded and the preconstruction
meeting held.
- Frischhertz has begun demolition in
preparation for the installation of the
Central Sterilization unit.
- Landis had the water
to the Clinic Building shut down for work
required in the new Central Sterilization
area.
- York delivered the replacement motor for
the 2nd chiller and completed the
installation.
- The unit is powered up but it needs
additional work to repair a flow switch.
Project to Make Temporary
Repairs to 1542 Tulane Ave.:
- Stratos Elevator is
working to complete the repairs to Elevator #3
in order to request the final inspection and
certification by the State Elevator Inspector.
- The communications
cable for the elevator has been installed.
- The safety cable has
been installed.
- The safety limit
switches have been installed.
- The safety brakes have
been installed.
- The controller on
Elevator #3 that stops the car for each
floor has been installed.
- Final repairs and
adjustments are being made.
- The inspection will be
scheduled for early next week.
- Ordes Electrical installed
new breaker panels in the engine room for Floors
1 through 7.
- They have completed
the installation of the breaker panel that
services the building pumps that require
480v.
- They are installing disconnect panels for
the condensation pumps and air driers in old
engine room.
- They have completed
the installation of the additional
transformers in the vault.
- Ordes Electrical is
now pulling additional cable to the new
transformers.
- Arc Mechanical has
continued with the installation of a new heat
exchanger in the basement.
- Arc Mechanical is running pipe to the
condensation pumps in the old engine room.
- Arc Mechanical began
installing the heating hot water pumps.
Downtown Campus Landscaping
Project:
- The irrigation valve wiring for the Lions/LSU
Clinic and the CSRB has been completed and all
of the valves installed.
- The irrigation system serving the CSRB has
been completed.
- The installation of the
irrigation system that serves the front of the
Lions/LSU Clinic Building is substantially
complete.
- Two of the 'Natchez'
(white) crepe myrtles were planted in the
designated location behind CSRB.
MEB Cafeteria Project:
- The flooring contractor
has completed the removal of the terrazzo floor.
- Significant portions of
the new HVAC duct work has been fabricated and
installed.
CSRB Temporary Vivarium Repairs:
- The contract to make
temporary repairs to the Vivarium space on the 1st
floor of the CSRB has been awarded and the
Notice To Proceed has been issued.
- The preconstruction
conference is scheduled for June 14th
and work will begin shortly thereafter.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|