|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #45
Posted: June 22, 2007
The final environmental
remediation and duct cleaning at the Dental School
is moving into the final stages. The crews have
worked long hours in difficult conditions to
complete the work in a timely manner. They have been
able to stay well ahead of the contractors doing the
ceiling tile and grid replacement. Details of their
progress and the related testing are detailed below.
The project to replace the
ceiling grid and tile in the Clinic and
Administration Buildings has ramped up and the crews
have worked out the details of how to complete the
work efficiently. This contract requires significant
coordination between the crews installing the grid
and the tiles, and the subcontractors who are
installing and moving light fixtures, relocating
sprinklers, and installing the new flex ducts and
diffusers in the new ceiling grids. Good progress
has been made and we expect the pace to pick up some
as the coordination details are worked out.
Behind the scenes, we have
been making plans to make significant changes and
improvements in certain areas that will positively
impact on the security of the LSUHSC campuses.
Improved exterior lighting and an aggressive
expansion of the use of the institution’s
campus-wide access control system are at the heart
of these initiatives. An extensive and detailed
update on this work is provided below. We firmly
believe that the safety and security of our
students, faculty, staff and campus visitors is
crucial.
We are also seeking to
make improvements to the facilities used by the
students and faculty in a continuing effort to
enhance the teaching and learning experience.
Significantly, we have issued a contract to replace
the old morgue coolers with modern, state of the art
coolers and related equipment. We’re also upgrading
the audio/visual equipment in the Multi-Disciplinary
Labs to take advantage of the latest technology and
network connectivity.
We’ve recently received
the final versions of Section 406 Hazard Mitigation
proposals that will provide better protection to all
of the elevators around campus should we ever
experience another flooding event. The proposals
will provide a control system that will allow
Facility Services staff to automatically elevate
elevator cabs to preset levels and keep the cabs and
cables above flood water levels from a single
central location. The proposal will also install
float switches that will automatically lift the cab
should water be detected in the elevator pits. The
cost/benefit is substantially favorable, so we
anticipate that the proposals will move through the
various FEMA review queues with little questioning.
As soon as we get the official approvals, we’ll
develop the bid specifications and seek to get a
contract awarded.
Here are highlights of
work that has been accomplished since our last
update was posted two weeks ago.
Project to Make Temporary
Repairs to the Dental School:
- The final environmental remediation and duct
cleaning contract is progressing smoothly. The
focus of the work has shifted to the
Administration Building.
- When the contractor completes their duct
cleaning or their remediation cleaning of an
area, an independent environmental
consultant must inspect the spaces and test
a variety of samples to verify that the
cleaning has been thorough and that the
spaces are suitable for occupancy. The
requirement for some re-cleaning is common.
- Remediation Status:
- Clinic 1st Floor:
- Duct work has been cleaned.
- Test results are pending.
- The interior insulation has been
coated/encapsulated.
- Interior spaces have been cleaned.
- Clearances have been received.
- The containment has been
removed.
- Clinic 2nd Floor:
- Duct work has been cleaned.
- Test results have been received
and passed.
- The interior insulation has been
coated/encapsulated.
- Both AHUs are operational.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 3rd Floor:
- Duct work has been cleaned.
- Test results have been received.
One unit passed and one unit
required recleaning.
- The interior insulation has been
coated/encapsulated.
- One AHU is operational.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 4th Floor:
- Duct work has been cleaned.
- Test results have been received
and passed.
- The interior insulation has been
coated/encapsulated.
- Both AHUs are operational.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 5th Floor:
- Duct work has been cleaned.
- Test results have been received.
One unit passed and one unit
required recleaning.
- The interior insulation has been
coated/encapsulated.
- One AHU is operational.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 6th Floor:
- Duct work has been cleaned.
- Test results are pending.
- The interior insulation has been
coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 7th Floor:
- Duct work has been cleaned.
- Test results are pending.
- The interior insulation has been
coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are clear.
- The containment has been
removed.
- Clinic 8th Floor:
- Duct work cleaning is in progress.
- Interior spaces have been cleaned.
- Test samples are to be taken.
- Admin 2nd Floor:
- Duct work has been cleaned.
- One unit passed and one unit
required recleaning.
- The interior insulation has been
coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are pending.
- Admin 3rd Floor.
- Duct work has been cleaned.
- One unit passed and one unit
required recleaning.
- The interior insulation has been
coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are pending.
- Admin 4th Floor:
- Duct work has been cleaned.
- Test results are pending.
- The interior insulation has been
coated/encapsulated.
- Interior spaces have been cleaned.
- Test results are pending.
- The project to upgrade the network
infrastructure continues to progress.
- Boe-Tel is pulled network cable from the
1st floor up to the 2nd floor into the
Clinic cubicles.
- Boe-Tel is removing the old network
cables before Landis closes up the ceiling.
- Work is currently under way on the
construction of the new network/telecom
closets on floors 2 through 8 in the Clinic
Building.
- The build out of each closet
includes the installation of plywood
back planes, gypsum board and rack
installation.
- The demolition of the old IT closets is
underway in the Clinic building.
- Cores have been drilled on floors 2
through 8 and sleeves have been installed on
floors 2 through 6.
- The contract to replace the ceiling tiles
and grid in the Clinic and Administration
Building is well underway.
- Landis has all of the new ceiling tile
installed on the 2nd floor of the
Clinic Building except at the sprinkler
heads.
- Ceiling grid and tile installation is
nearly complete on the 2nd, 3rd,
and 4th floors and continues on
the 5th, 6th and 7th
floors of the Clinic Building.
- The installation of the new HVAC flex
duct is nearly complete on the 2nd,
3rd and 4th floors and
continues on the 5th floor.
- Frischhertz has nearly completed
reinstalling the lights on the 2nd,
3rd, and 4th floors
and continues working on the 5th
and 6th floors.
- Additional damaged junction boxes and
lights were discovered on the 6th
and 7th floors and a change order
is being written to address the needed
repairs.
- Firetrol continues to reposition and add
sprinkler heads as necessary on the 2nd,
3rd, and 4th floors
and continues on the 5th floor.
- Schindler Elevator has been working on
completing repairs to the three passenger
elevators in the Administration Building.
- The contract to restore the Central
Sterilization function in a 3rd floor
space has been awarded and the initial phase of
work has begun.
- The structural demolition has been
completed.
- The electrical and mechanical demolition
is also finished.
- Frischhertz has removed old conduit from
the 3rd floor area where the new Central
Sterilization unit is being constructed.
- The new ducts are being installed, and
the walls are laid out.
- The emergency generator was successfully
tested and training on the equipment was
conducted for 5 LSUHSC Facility Services
employees.
- The repairs to the exterior site lighting
and the electrical work necessary to power the
parking lot controls are continuing.
- Old subsurface wires have been pulled
and the damaged light standards have been
dismantled.
- The replacement doors and frames needed for
the 1st floors of the two buildings
have been delivered and the installation work
has started.
- A change order proposal to replace a number
of HVAC inline dampers in the buildings has been
received and approved. The contractor is
ordering the needed parts and materials.
Installation is anticipated to begin by the end
of next week.
- A change order proposal to make repairs to
the compressed air line running through the
utility tunnel from the Power Plant to the
Clinic Building has been received and approved.
Repairs should begin shortly.
- A proposal to replace the 1st
floor ceilings in the Clinic and Administration
Buildings has been prepared and submitted.
- The architects have submitted a proposal for
additional testing of the roofs on the two
buildings. This testing will assist in
accurately determining the extent and nature of
the storm related damage.
- Once the scope of the damage is aligned
with FEMA, plans will be developed and bid
to complete the permanent repairs.
Project to Make Temporary
Repairs to 1542 Tulane Ave.:
- Arc Mechanical continued the installation of
the domestic hot water pumps.
- They are also installing the heat
exchangers for domestic hot water.
- Ordes Electrical is installing
disconnect panels for the domestic hot water
circulating pump.
- Arc Mechanical is installing one of the new
air compressors in the rear of the basement.
- Ordes Electrical is installing
disconnects for the new air compressors and
air driers.
- Ordes is also running conduit to the
disconnect panels for the air compressors
and the air driers.
- Arc Mechanical started the installation of
new pipe to the condensate pumps.
- They are welding in new pipe and valves
for the condensate return pumps.
- Ordes Electrical is installing the wire
to the condensate return pump and is
installing the disconnect panels for the
pump.
- Stratos Elevator is making the final repairs
and running on Elevator #3 in preparation for a
follow up visit by the State Elevator Inspector.
The wrong governor cable had been sent and
installed. It is being replaced.
- The safety chain is being installed on
Elevator #3.
- Stratos is installing the new floor call
buttons.
- The replacement controllers for
Elevators #7 and #8 have been received on
site.
- Stratos has begun the repairs to
Elevator #2 by removing the damaged cab.
- Ordes continues running conduit between the
new 480V panels and the switchgear.
Downtown Campus
Landscaping Project:
- All 23 irrigation valves around the
Lions/LSU Clinic Building and the CSRB are now
wired into the controller.
- All of the irrigation zones have the
underground pipe installed and terminated.
- All of the irrigation zones around the CSRB
are complete, fully operational and are on auto
via the controller.
- 26 Savannah holly trees were planted around
the CSRB and the Lions/LSU Clinic Building.
- All of the crepe myrtles were planted around
both the Lions/LSUHSC Clinic Building and the
CSRB.
- 62 juniper plants were planted around the
flag pole area of Lions/LSU Clinic Building and
the planting is complete.
- The final grading was completed around
CSRB.
- Edging is being installed and additional
planting is being done around the CSRB and the
Lions/LSU Clinic Building.
MEB Cafeteria Project:
- All of the HVAC duct work has been
fabricated and installed.
- The circular terrazzo floor section has been
poured in the center of the space, and the 2nd
portion of the terrazzo floor has also been
poured.
- The majority of the new stud walls and the
fur downs in the ceiling have been constructed.
- The drywall has been installed on a majority
of the new stud walls and the ceiling fur downs.
- The new air handling unit has been delivered
and installed.
Student Parking Lot
Re-Surfacing:
- Work has begun on a contract to pave Student
Lot #2 and #3 with asphalt.
CSRB Temporary Vivarium
Repairs:
- The contractor has begun work on the
project. The initial phase of demolition is
underway.
Campus Security
Enhancement Project:
LSUHSC has undertaken a
series of significant projects to improve the
overall security environment of the campus. Specific
work includes the enhancement of exterior lighting
around the buildings and in the parking lots, and
significant expansion of the campus-wide access
control and security system. This state of the art
system allows for flexible and sophisticated control
over the access to buildings, selected interior
rooms and areas, provides integration with digital
security cameras, emergency intercoms, scream
alerts, etc. All of this will provide significantly
better security for patients, students, faculty,
staff and visitors. Accomplishments and plans for
the future are highlighted below:
- Plans for enhanced exterior lighting on the
downtown campus have been finalized and the
implementation is already underway. Plans for
enhancements to the Dental School campus
lighting are being developed and finalized.
- New lighting has already been installed
in Student Lots #2 and #3.
- All of the door locks on the rooms, suites,
and apartments in Stanislaus Hall and the
Residence Hall have been replaced.
- The new locks utilize the resident’s
LSUHSC ID card plus a private PIN for entry.
- Sister Stanislaus Hall
- The fully integrated Access Security
System became operational on June 4th,
2007.
- Enhancements to further limit access
to selected areas are continuing. An
example would be limiting access to dorm
floors to residents and authorized
staff.
- Features that have been installed
include surveillance cameras and
recorders, proximity card readers that read
the LSUHSC ID, door sensors, scream alerts
and emergency intercoms.
- Proximity card readers will be installed in
the elevators to allow access to individual
floors to be limited to residents
- Centralized monitoring of the system by
the LSUHSC University Police has begun.
- Residence Hall
- Conduit and cable is being installed to
connect the surveillance cameras and
recorders, proximity card readers, door
sensors, scream alerts and the emergency
intercoms.
- Proximity card readers will be installed
at the elevator doors on both the 1st
floor and 2nd floor of the
Residence Hall.
- Proximity card readers will also be
placed at exterior entrances to the
building, including the side gates to the
second level to control general access to
the building.
- Walk To Wellness
- Proximity card readers will be installed
on the connections from the elevated walkway
to the Medical Education Building, the
Lions/LSU Clinic Building, the
Nursing/Allied Health Building and the
Resource Center.
- Installation of access control devices
is also planned for the stairwell from
Gravier Street to the Walk-To-Wellness at
the University Hospital Medical Office
Building and for the elevator/stairwell
leading from the Walk-to-Wellness to Gravier
Street closest to Claiborne Ave.
- The old stand alone access control system
used in the CSRB will be replaced with the
campus wide system. This will allow all of the
campus buildings to be controlled, secured and
monitored in a consistent fashion with the
campus-wide unified system.
- Proximity card readers will be installed at
the 1st floor entrances to the
stairwells in the Roman Street Garage to limit
access to the upper floors to LSUHSC employees
only.
- The existing old surveillance cameras on the
Walk-To-Wellness and Roman Street garage will be
replaced with a digital video management system
(DVMS) that will be integrated with the
campus-wide security system.
- All of the loading docks serving the
downtown campus buildings have been surveyed and
plans are being made to secure those areas with
access control devices and surveillance cameras.
- A site survey of the remaining CCTV
surveillance system at the Dental School has
been completed. Further evaluation and
recommendations for implementing access control
and CCTV capabilities has been requested from
the access control contractor.
Morgue Cooler:
We have initiated a
project to replace the cooler in the morgue located
in the MEB.
- Bids for a new cooler were solicited and the
contract was awarded.
- The cooler is currently being manufactured.
- The installation of the new cooler is being
planned to begin in mid-August.
Multi-Disciplinary Labs AV
Equipment:
Significant enhancements
to and modernization of the audio/visual equipment
are being made in the Multi-Disciplinary Labs (MDLs)
located on the 4th floor of the MEB.
- All of the new LCD monitors, high resolution
projectors, and motorized screens have been
installed in Labs #2, #3, #4, #5, and #6.
- The main switch and the centralized control
center are being wired; connecting all of the
devices together.
We encourage you to follow the details of our progress
through the daily updates which are posted on the web site.
|