|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #55
Posted: November 9, 2007
Early in the morning of
November 9, 2007 we received word that FEMA had
approved our first major building repair and hazard
mitigation project. Approximately $9.2 million has been obligated
to fund the proposed work at the Lions/LSU Clinic
Building. The project features rebuilding the Isadore Cohn Learning Center on the 6th
Floor to prevent any risk of flood damage in the
future.
A lab will be moved to the 7th floor to
clear the site for the construction of the Learning Center. All of the critical mechanical, electrical
and plumbing equipment that supports the building
operations will be elevated above flood levels; most
will be placed on the 2nd Floor. Portions of the 1st Floor will be
repaired using materials that can withstand flooding
and will be easily cleaned. The elevator shafts will be sealed to prevent
flood water from entering the elevator pits and
damaging the equipment located below the elevator
cabs. 1st
Floor windows and exterior doors will be repaired or
replaced as needed. The damage done to the building roof by
Hurricane Katrina will be repaired.
The architects are completing
their construction and bid documents at this time. The Office of Facility Planning and Control
will begin to be advertised the bid next week so
that bids can be received prior to the Christmas
holidays. We are hopeful that this schedule will allow
bids to be evaluated and a contract to be awarded
that will allow work to begin on the building early
in calendar year 2008. We will provide updates on the bid process
and the contract award as they are available.
We wish to acknowledge all of
the assistance and support that has allowed us to
reach this significant milestone in the recovery. The Office of Facility Planning and Control,
the Governors Office of Homeland Security and
Emergency Preparedness, the FEMA Health and Research
Team and the Section 406 specialists, and our team
of architects and engineers have all played critical
roles in this success. We look forward to reporting on similar
successes as the recovery process moves forward.
The preconstruction conference
for the contract to replace the roof of the MEB was
held on November 9th and the contractor
has been issued the Notice To Proceed. Work is scheduled to begin on November 19th. The bids for the replacement of the Dental
School
roofs had to be cancelled and re-issued to correct a
technical deficiency in the bid. An expedited bid process was approved by the
Office of Facility Planning and Control and the new
bids will be opened on November 20th.
Work on the temporary repairs
to 1542 Tulane is progressing well. Faculty and staff members have been busy
cleaning out offices and removing personal items in
for the start of the final remediation
contract. Ordes Electric is completing the last of the
repairs that were covered by their contract. The installation of the new fire alarm system
is progressing.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Permanent Building Repairs and Section 406 Hazard
Mitigation:
- FEMA has just approved a
$9.2 million Project Worksheet for the permanent
repairs and Section 406 Hazard Mitigation at the
Lions/LSU Clinic Building. The project includes rebuilding the Isadore Cohn Learning Center on the 6th
Floor to insure that it would not be damaged by
any future flood events. A lab will be moved to the 7th
floor to clear the site for the construction of
the Learning Center. We will also elevate all of the building
critical mechanical, electrical and plumbing
components to protect them from flooding. Most of this equipment will be placed on
the 2nd Floor. Repairs will be made to the roof, and
portions of the 1st Floor will be
repaired using finishes that will withstand
water and can be easily cleaned.
- The consolidated
comments on the Construction Documents for
the Lions/LSU Clinic Building permanent
repairs and 406 Hazard Mitigation have been
delivered to the architects to be
incorporated into the final bid documents.
- Some additional
documentation has been requested by FEMA
to assist in preparing an additional
version to the PW to address the
projected construction costs.
- We anticipate that the
bid documents will be prepared shortly and
that the bids will be advertised next week. We are hopeful that a contract can be
awarded promptly and that work can begin
early in calendar year 2008.
- A meeting was recently
held with FEMA, GOHSEP and LSUHSC to review
comments prepared by FEMA on the
Design/Development documents submitted for the
Allied Health/Nursing Building, the Residence
Hall, and the Resource Center.
- Only a few issues
remain to be addressed by the architects.
- FEMA will begin the
of the versions to the
appropriate PWs and the corresponding
Section 406 Hazard Mitigation proposals and
will incorporate the comments from the
architects as they are received.
- We believe that these
three projects will be recommended by the
FEMA Health and Research team.
Project to Make Temporary
Repairs to 1542 Tulane Ave.:
- Fire Alarm System:
- Siemens has finished
installing the new fire alarm speakers,
strobes and wiring for the 1st
Floor, the 7th Floor and the 8th
Floor.
- Siemens is currently
installing the new fire alarm system wiring,
speakers, and strobes on the 6th Floor.
- Elevator Repairs:
- Stratos Elevator
installed the cab walls and roof of Elevator
#8.
- They have
installed the interior door hardware for
the cab of Elevator #8
- The elevator cab
has been leveled.
- The contractor is
installing the wiring for the Elevator
#8 controller.
- Stratos is removing
the counter-weights and elevator cab frame
for Elevator #1.
- The contractor is
working in the penthouse wiring the
controller for Elevator #7.
- The elevator
safeties have been installed.
- The tape selectors
which aid in the automatic cab leveling
are being installed.
- The contractor
installed plywood in Elevator #2 to protect
the interior so that it can be used.
- The contractor is
installing the temporary control wiring for
the Elevator # 8 controllers. This will allow them to call the
elevator up or down and begin rebuilding the
cab.
- Final Remediation and Duct
Cleaning:
- Bids were opened on
October 31st. The bid has been awarded to
Zimmer-Eschette and work us scheduled to
start on November 19th.
- Faculty and staff
members are cleaning out their offices and
removing personal items on upper floors to
prepare for the final remediation and duct
cleaning.
- Work has been
completed on Floors 5, 6, 7 and 8.
- Work is currently
underway on Floors 1 and 2.
- Painting: The extended exposure to heat and
humidity caused significant amounts of paint to
peel off the walls and ceilings in a variety of
locations throughout the building. A painting contract has begun work to
remove the peeling paint and to patch and
prepare the surfaces within the building
stairwells for repainting.
(The
balance of the paint removal and repainting will
be done as part of the remediation and duct
cleaning contract.)
- The contractor has
finished priming and repainting Stairwell C.
- The contractor
mobilized crews to begin working in
Stairwell D.
- They have removing
the peeling paint on Floors 1 through 9
and in the basement.
- The contractor has
patched and floated the walls on Floors
1 through 9.
- The walls on
Floors 1 through 9 have been sanded.
- The walled have
been primed in this Stairwell.
- The contractor
primed the ceilings and began priming
the hand rails on Floors 4 – 8 in
Stairwell D.
- The contractor has
mobilized crews to begin work in Stairwell
B.
- The peeling paint
has been removed on Floors 1 through 8.
- The contractor is
floating the walls on Floors 4, 5, 6, 7
and 8.
- Misc.
- Arc Mechanical
repaired a leaking steam line.
- They also worked
on the soft water system; draining the
tank and removing hoses.
- Ordes installed the
contacts/relays for the Parking Garage
exhaust fan starters.
- Ordes removed the
Entergy Thermal control box (PLC) which
monitors and controls the Energy Transfer
Station.
- They are labeling
wires in for the
installation of the new Entergy Thermal
control box (PLC) which monitors and
controls the Energy Transfer Station.
- The installation
of the new PLC is in progress.
- Ordes finished
installing the starters for the Parking
Garage exhaust fans.
- The building steam
lines were re-energized and they are being
checked for leaks and proper operation.
- Ordes Electric
disconnected the power from the fire pump
motor and removed the motor.
- It has been sent
off to be rebuilt.
Project to Make Temporary
Repairs to the Dental School:
- 1st Floor Clinic Building
Projects:
- The installation of
the Barrel ceiling has been completed.
- The Curviture ceiling
installation is complete with the exception
of a few panels.
- The contractor is
waiting on a few additional chandeliers
to arrive and to be installed before the
last panels can be put in place.
- Landis has installed
most of the small chandeliers in the 1st
floor lobby of the Clinic Building.
- All of the carpeting
has been installed in the 1st
Floor lobby space.
- The lobby reception
furniture arrived and the installation is
complete.
- The contractor
installed the sprinkler heads in the Barrel
ceiling.
- The veneer wraps for
the columns behind the curved wall are on
order and should be delivered shortly.
- The contractor has
completed the fur-outs that cover the supply
air ducts and diffusers above the curved
wall in the main lobby and they have been
painted.
- Most of the other
ceiling mounted fixtures have been installed
throughout the 1st Floor lobby of
the
Clinic Building.
- 2nd Floor Conference Room Administration Building:
- The painting of the 2nd
Floor conference room in the
Administration Building is
complete.
- The 6 new exterior
windows have been installed.
- The installation of
the new duct work in the room is complete.
- Landis finished the
installation of the electrical outlets and
switches.
- All of the ceiling
tile has been installed.
- Permanent Roof Replacement:
- The bids for the
replacement of the roofs of the main Dental School
campus buildings were opened on 10/23/07. During the evaluation process,
several of the low bids were found to
contain technical deficiencies that required
that they be rejected. It was determined that it would be in
the best interests of the State to reject
all bids and re-bid the project with
adjustments to the specifications.
- The State has
agreed to use an expedited bid process
that will allow the new bids to be
opened on November 20th.
-
Elevator Status:
- Schindler programmed
the emergency telephone lines for Elevators
#6 and #7.
- They began the ceiling
installation in Elevator #5.
- Schindler finished
running wires to the machine room for
Elevators #3 and #4.
- They installed the
interior lights in the freight elevator.
- Miscellaneous:
- Siemens has completed
the installation and connection of the
controls for the new inline dampers in the
Clinic Building.
- Landis has
finished reinstalling the ceilings at
the damper locations on Floors 6, 7, and
8 with the exception of one area on 7,
where the damper for location (7BD) is
on order.
- They are now
working on the 5th floor of
the Clinic Building.
MEB Roof Replacement:
- The roof of the
Medical Education
Building
was severely damaged by Hurricane Katrina. The contract to replace the roof has been
issued and work is scheduled to begin on
November 19, 2007. Equipment and supplies will be staged in
the parking lot across Roman St. from
the building. A lift will be mounted on the side of the
building to move men and materials to the roof. The contract allows 120 days for the
contractor to complete the work. We are hopeful that the contractor may be
able to finish their work in advance of this
deadline.
- Prior to beginning the
removal of the old roof, the contractor will
be surveying all of the rooms and spaces on
the top floor of the building to identify
any damage that existed prior to the
initiation of the roof replacement. This will assist in identifying any
additional damage that might occur during
the replacement process, which will be the
responsibility of the contractor. You may expect to see the contractor
representatives on the 7th floor
seeking access to all of the rooms. This should be a relatively quick
process and any inconvenience to the room
occupants should be minimal.
- Depending on the phase
of construction, wind direction, etc.,
building occupants may also expect to notice
odors related to the installation of the new
roof.
Asphalt-based products will be used and they
will naturally create some odors that may
enter the building from various air intakes
located at lower levels on the building. We hope that this will be minimal,
and building occupants may be assured that
there is no health or safety risk associated
with any odors that they may perceive.
Downtown Campus Landscaping
Project:
- Irrigation Stations #23 &
#24 on the
Bolivar St.
side of the MEB have been activated.
- Flowering annuals have
been planted at the Lions/LSU Clinic Building
flagpoles and at the memorial bench.
- 1,400 variegated Algerian
ivy plants were planted under the overhang and
elevated walkway on the Bolivar St.
side of the Allied Health/Nursing Building.
- The crews sprayed
herbicide on old vegetation on the S. Roman St. side of the Allied
Health/Nursing Building in for
re-landscaping.
- They sprayed herbicide in
various parking lots and performed routine
landscape maintenance.
- The installation of plants
and mulch on the
Bolivar St.
side of the MEB has been completed.
- Channel drains have been
installed on the
Gravier St.
side of the Allied Health/Nursing Building.
- The installation of
irrigation stations 7 and 8 on the S. Roman St. side of the Allied
Health/Nursing Building has been completed.
- Crews removed all of the
old vegetation and started added topsoil to the
sections that will become planting beds in the
same area.
Cafeteria Project:
- Advanced Millwork has been
installing the maple veneer walls and the booths
on elevated deck of the cafeteria.
- Zimmer continues to work
on addressing the outstanding punch list items.
- The doors have been
installed.
- Zimmer also started
preparing the four columns in the cafeteria for
the ceramic tile installation.
MEB Morgue:
- The contractor has
finished insulating the pipes for the condensing
units.
- The stainless steel strips
for the cooler panels have been installed.
- The hose with reel for
washing the coolers is now installed.
- The contractor is now
beginning work on punch list items as the
contract nears completion.
Exterior Lighting Project:
- The demolition of the old
lights from underneath the patio areas on both
sides of the MEB and the cutting for new access
panels is complete.
- The new lights are now
working on the top part of both MEB patios.
- The demolition of the
old lights is in progress.
Allied
Health/School of Nursing Flooring:
- All the new floor tile has
been installed in the 8th Floor
elevator lobby and in Corridors A and B.
- The tile installation in
Corridors C and D has also been finished.
We encourage you to follow
the details of our progress through the daily
updates which are posted on the web site.
|