|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #61
Posted: February 1, 2008
Our first major project for permanent repairs and mitigation is about to get underway. The contract for the Lions/LSU Clinic Building has been executed by Construction Masters, Inc. The Notice to Proceed has been issued with an effective date of February 11, 2008 and the pre-construction conference is scheduled for 2:00 PM on February 7, 2006. The scope of the contract includes re-building the Isadore Cohn Learning Center on the 6th Floor, relocating an existing research lab from the 6th Floor to the 7th Floor, moving the critical mechanical, electrical and plumbing equipment to the 2nd Floor, and constructing an exterior stairwell on the front of the building to provide adequate egress from the new Learning Center. The 6th Floor lab will remain in operation until the replacement lab on the 7th Floor is ready for use. The contract will also restore the public areas of the 1st Floor and will use surfaces that will resist damage from flood waters. The building elevator pits will be protected. Repairs will also be made to the damage on the roof done by Katrina.
We are pleased with the
progress being made in replacing the roof of the MEB
and the roofs of the Dental School Clinic Building,
Administration Building and the Power Plant. The
majority of the demolition is complete on the MEB
roof and the initial, temporary layers of roofing
have been laid. The contractor has begun the
installation of the light weight concrete in some
areas. In spite of several days of rain, we have not
seen any leaks resulting from the replacement work.
At the Dental School, the
Clinic Building roof has been stripped and the first
new layer of roofing has been installed. The workers
are working on flashing the parapet walls and
sealing all the roof penetrations. A second and
final layer of roofing is to follow. Crews have
already begun working on the roof of the
Administration Building.
The execution of all nine
contracts for the building demolitions on the back
campus of the Dental School is nearing completion.
Since the contracts were awarded to three separate
contractors, extra effort is being made to
orchestrate the work to limit the inconvenience to
patients, faculty, students and staff as much as
possible. We are expecting this work to start about
mid-February and be complete (weather permitting)
not later than early March.
FEMA continues their
review and the preparations of the final
recommendations on the two proposals to make
permanent repairs and complete hazard mitigation
work at the Resource Center and the Residence Hall.
A few additional questions were raised recently and
the architects were able to respond quickly. The
FEMA Health & Research team is reviewing the latest
data and we are hopeful that they can complete their
recommended PW versions and Hazard Mitigation
Proposals (HMPs) for these two buildings and move
them into next level of FEMA review queues for
approval and obligation. The downtown architects are
working to complete the Construction Document
submissions on these buildings so that when the PW’s
and HMP’s are approved, the bid documents will be
ready to be issued.
The design team working at
the Dental School is planning to have their design
concept for the permanent repairs and HMP submitted
to us by late next week. While this work is being
completed, we are working with the GOHSEP Hazard
Mitigation specialist on a package of information to
accompany the design concept when it goes to FEMA.
We’re attempting to proactively answer the types of
questions that we anticipate will be generated by
this large and complex proposal in hopes that we
might speed up the review process.
The schematic design
package for the permanent repairs and hazard
mitigation at 1542 Tulance Ave. has just been
submitted by the architects. This submission is an
expansion of the initial design concept and provides
additional details to FEMA and GOHSEP. While the
review of these documents is being completed, the
architects will be working on the Design/Development
submissions that will be used for the final review
and approval of the project by FEMA.
The work at 1542 Tulane
Ave. to prepare the front portion of the building to
be re-occupied continues. Ducts have been cleaned
and are now being sealed with an encapsulant that
will help to minimize future mold growth and the
spread of particulate matter. All of the building
debris has been removed from the front and center
sections of the building. The crews are now working
in the rear (old) section of the building which will
not be put back into use immediately. All of the
damaged carpet has been removed and much of the
floor tile is gone as well. The task of removing the
vast amounts of peeling paint from ceilings and
walls has been daunting. Every surface that has
paint removed must also be floated, primed and
re-painted to seal the walls and prevent any further
peeling. However, the contractor is making good
progress.
The use of 1542 Tulane
Ave. has changed over the years and when we return
people to the building it will function primarily as
an office building. Old laboratory equipment,
benches and case work have been removed. A modest
number of new walls will be constructed in selected
locations to enhance the functionality of the space
so that faculty, residents and staff will enjoy the
greatest possible benefits from this space.
Here are highlights of
work that has been accomplished since our last
update was posted two weeks ago.
Repair Work at 1542 Tulane
Ave.:
- Fire Alarm System:
- Siemens completed trouble-shooting the
fire alarm system wiring on the 1st Floor
and all the devises have been stabilized.
- The contractor finished pulling the new
fire alarm wires on the 6th and 7th Floors.
- They currently trouble-shooting the
wiring on both floors.
- The contractor is now pulling new wires
to the fire alarm devices on the 5th Floor.
- New fire alarm devices have been
installed in the elevator penthouse.
- Siemens continues to test and
stabilize the fire alarm wiring in the
elevator penthouse.
- They have stabilized the alarm devices
for the dry-pipe sprinkler system on the 8th
floor.
- Elevator Repairs:
- Elevator #1:
- The rear door for Elevator #1 at the
basement level has been installed.
- Work is underway to install the new
elevator cab.
- Elevator #8:
- Stratos Elevator is installing the
safeties on Elevator #8.
- The rope gripper has been installed.
- Final Remediation and Duct Cleaning:
- Duct Cleaning Status:
- The HVAC ducts that were cleaned on
the 5th, 6th, 7th and 8th Floors have
now been sealed.
- Crews are now working on sealing the
4th Floor ducts.
- Debris Removal:
- Zimmer continued to remove debris on
Floors 2 - 5 in the rear of the building
(old section).
- Final Remediation/Cleaning/Painting:
- Zimmer finished cleaning in the
corridors and rooms along Tulane Ave.
and in the "A section (over parking
garage)" on the 3rd Floor.
- The contractor also finished
cleaning in the main corridor on the
3rd floor.
- Following the completion of the
final cleaning and wipe down, the
3rd Floor passed the visual
inspection and air samples were
taken.
- Zimmer finished cleaning on the 2nd
Floor in the offices along the Tulane
Ave. side of the building.
- This area passed the visual
inspection and was tested for lead.
- The air samples for mold were
taken.
- Zimmer finished cleaning on the 2nd
Floor in the offices along the central
corridor.
- This area also passed the visual
inspection.
- Air samples have been taken.
- The painting contractor finished
floating the walls on the 1st Floor in
Suite 122.
- The contractor finished priming
the walls on the 1st Floor in Suites
123 and 122.
- The finish costs of paint have
been applied in Suite 123.
- The contractor is applying the
finish coats of paint on the 8th
Floor.
- The painting contractor has
floated the walls on the 6th and 7th
Floors.
- The walls on the 5th Floor
are currently being floated.
- Floor Tile Removal:
- Zimmer finished removing floor tile
from the 5th Floor.
- Tile was removed from the
corridors and rooms along Tulane
Avenue.
- Tile was also removed from the
center corridor.
- Encapsulant was applied over the
same areas.
- The 5th Floor passed the visual
inspection and samples have been
taken.
- Zimmer finished removing the floor
tile from the 4th Floor in the center
corridor.
- The center corridor passed the
visual inspection and samples were
taken.
- Network Closets:
- Trison installed the plywood and the
required electrical utilities for the 1st
Floor network closet (126).
- The contractor floated, sanded,
primed and painted the walls for the
network closets on the 1st and 4th
Floors.
- The walls of the 3rd Floor
closet have been painted.
- The electrical service and
connections have been made to all the
network closets.
- The floor of the 1st, 3rd and 4th
Floor closets have been prepped for the
installation of new tile.
- The new tile has been installed
in all three closets.
- The contractor is applying the
primer and finish for the walls of the
network closet on the 3rd Floor.
- Boe-tel has finished pulling all new
network cables throughout the 7th Floor.
- Work has begun on the terminations
of the new cable and is nearing
completion.
- The contractor is removing the old
data drops on the 5th and 6th Floors.
- ATT/Bell has workers on site relocating the
telephone demark for the building to the 2nd
Floor in Room 243, where it will be protected
from future flooding.
Repair Work at the Dental
School:
- Roof Replacement:
- The roofing contractor has finished
removing all of the old roofing material
from the top of the Clinic Building.
- Well over 120 squares (one square =
100 square feet) of roofing material was
removed.
- All of the debris has been removed
from the roof into the dumpster on the
ground level.
- They applied the adhesive and new
insulation, decking material, and the 1st
ply of the new roofing material over each
area as the old roof was removed.
- The installation of the new flashing and
sealing around the various roof penetrations
is substantially complete.
- The crews have started removing the old
roofing material from the Administration
Building.
- The first ply of the new roof is
being installed over the sections where
the old roof has been removed.
- Temporary Bookstore:
- All of the new walls have been framed up
and dry walled.
- The walls have been taped and
floated.
- The walls have been primed.
- The interior walls are being
painted.
- The duct board and flex duct for the
supply air and return air has been
installed.
- This ducting serves the temporary
bookstore and the existing adjacent
rooms.
- The rough in electrical for the new
lights, outlets and switches has been
completed.
- The ceiling tile, the carpet, and wall
base has been installed in the hall on the
exterior of the temporary bookstore.
- Elevator Repairs:
- Elevator #3:
- Schindler worked on the cab finishes
and ran the electrical wires for the
lights in the elevator car.
- The car top has been painted.
- The lanterns (Up and Down Arrows)
are being repaired.
- The new wall panels, ceilings and
lights have been installed in the
elevator cab.
- Elevator #4:
- Schindler worked on the cab finishes
and ran the electrical wires for the
lights in the elevator car.
- The car top has been painted.
- The lanterns (Up and Down Arrows)
are being repaired.
- The new wall panels, ceilings and
lights have been installed in the
elevator cab.
- Elevator #8:
- The front and rear of the cab has
been installed.
- The new door tracks are being
installed.
- Work on the rear doors is in
process.
- Work is also proceeding on the
equipment mounted on the car top.
- Security:
- Securitas ran coax cables for the
intercom system to the front desk located in
the Clinic Building, 1st Floor lobby.
- Securitas installed new security cameras
on the Administration Building facing the
Power Plant and the parking lots in the rear
of the property.
- They are working on the installation
of the cameras for the Clinic Building.
- The conduit and wiring have been run
and the posts where the cameras will be
mounted are set.
- Misc.
- Trison Constructors completed the
demolition of the existing oven duct work
that had run on the 1st Floor and through
the basement.
- They have completed the majority of
the installation of the new ducts in the
basement and on the 1st Floor.
- They are waiting for the new fire
dampers and the fan to arrive to
complete the work.
- Pflueger Electric supplied power to the
parking gate on the east side of the Dog
Kennel.
Exterior Lighting Project:
- Ordes finished installing the new exterior
lights on the Allied Health/Nursing Building.
- The plaster repairs around the twelve new
can lights that were installed at the MEB have
been started and are nearing completion.
- Multiple layers are required.
- Rain has interrupted and delayed the
completion of repairs.
- Additional light poles are being installed
in locations around the 440 Perdido Lot, Student
Lot 1, and Residence Hall Lot.
- The existing pavement has been cut out
and removed from the light pole locations.
- Holes are being dug with a large augur
for the concrete footings that will support
each pole.
MEB Roof Replacement:
- The contractor continued to demo the
lightweight ballast on the South Roman side of
the MEB.
- The contractor is working on the last
section of the roof on this side of the
building.
- All of the existing debris from the
demolition has been moved to the dumpster on the
ground level.
- The contractor has started pouring the
lightweight concrete on the penthouses and on
the Bolivar street side of the MEB.
Landscaping Project:
- Crews trenched, installed
pipe and sprinklers and backfilled a complete
irrigation station on the Perdido St. side of
the MEB at the corner of S. Roman St.
- Crews moved the backflow preventer (for the
water supply for irrigation in the Parking Lot 2
pocket park) inside the parking lot fence.
- They started trenching for the irrigation
pipe in the small park area in the corner of the
lot.
Downtown Campus – 1st
Floors:
- The State Fire Marshal has required that we
take measures on the unoccupied 1st Floors and
basements of the buildings on the downtown
campus. This work will insure that the existing
sprinkler systems will function properly while
we wait for the permanent repairs to be
designed, bid, contracted and completed.
- In the majority of the buildings, the most
cost effective method of accomplishing this goal
is to re-install ceiling tiles into the existing
ceiling grid on the 1st Floor.
- A contract has been issued for the work.
- All of the temporary ceiling tiles are
on site and have been moved to the
designated buildings.
- Trison has finished installing ceiling
tiles inside the 1st Floor lobby of the MEB.
- Crews have moved on to begin the work at
the CSRB and the Residence Hall.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|