|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #62
Posted: February 15, 2008
Our first major project for
permanent repairs and mitigation is about to get
underway. Construction Masters, Inc. and
representatives from all their sub-contractors
attended the pre-construction conference on 2/7/08
along with representatives of LSUHSC, the Office of
Facility Planning and Control, the LSU Systems
Office and the architects. The contractors are working on their
schedule for sequencing the work and we are
coordinating with the academic departments that
currently use space where the initial demolition
will occur.
All nine contracts for the
building demolitions on the back campus of the Dental School have been executed
and the coordination and staging of the work (with
three separate contractors) is underway. Work is expected to begin as early as the
beginning of next week. The Dental School leadership has been
kept abreast of the specific plans and timelines.
Two weeks ago, we were able to
report good progress on both of the permanent roof
replacement projects; one at the MEB and one
addressing the Dental School Clinic and
Administration Buildings and the Power
Plant.
While progress has continued, we experienced two
major rain events during the past week and each
caused significant leaks and damage. The Dental School
leak (2/12/08) damaged the freight elevator and it
was taken out of service. The contractor estimates a 6-8 week repair. Late this evening (2/15/08), rain at the
downtown campus leaked through some roof
penetrations at the MEB and damaged a critical bus
duct and feeders supplying emergency power to
portions of the upper floors of the building. Emergency repairs are already underway.
FEMA continues their review and
the preparations of the final recommendations on the
two proposals to make permanent repairs and complete
hazard mitigation work at the Resource Center,
the Residence Hall and the Allied Health/Nursing
Building. A few additional questions were raised
recently and the architects were able to respond
quickly.
The FEMA Health & Research team is reviewing the
latest data and we are hopeful that they can
complete their recommended PW versions and Hazard
Mitigation Proposals (HMPs) for these three
buildings and move them into next level of FEMA
review queues for approval and obligation. The downtown architects are working to
complete the Construction Document submissions on
these buildings so that when the PW’s and HMP’s are
approved, the bid documents will be ready to be
issued.
The FEMA Health and Research
team has completed their revisions to the draft
Section 406 Hazard Mitigation proposal for the
CSRB/MEB. Their revised draft is now under review
within the FEMA hierarchy. The project would build a full height
addition to the back of the CSRB which would provide
space for elevating the vivarium functions from the
MEB and CSRB. The addition will also allow space for
critical mechanical, electrical and plumbing (MEP)
equipment to be elevated from the 1st
Floor of the CSRB, and provide for a bank of
emergency generators that would be able to provide
temporary power to the surrounding campus buildings
to maintain basic environmental controls, critical
data network components, and research refrigerators
and freezers. The concept also elevates some critical MEP
within the MEB, and makes basic repairs to the 1st
Floors of both buildings, using wet flood proofing
techniques to limit damage in another flood event.
The design team working at the Dental School
finished their design concept for the permanent
repairs and HMP and submitted it to us on 2/15/08. LSUHSC and GOHSEP are reviewing the draft and
will send comments back to the joint venture to be
incorporated into the submission.
We have
finished our work with the GOHSEP Hazard Mitigation
specialist on a package of information to accompany
the design concept when it goes to FEMA. With this document, we are attempting to
proactively answer the types of questions that we
anticipate will be generated by this large and
complex proposal.
The schematic design package
for the permanent repairs and hazard mitigation at
1542 Tulance Ave. was
submitted by the architects approximately two weeks
ago.
This submission is an expansion of the initial
design concept and provides additional details to
FEMA and GOHSEP. The GOHSEP 406 Hazard Mitigation specialist
has reviewed the documents and has formally
submitted them to FEMA. Key to this proposal is the construction of
an elevated addition that will house all the
critical mechanical, electrical and plumbing
equipment that was previously located in the
basement. While the FEMA review of these documents is
being completed, the architects will be working on
the Design/Development submissions that will be used
for the final review and approval of the project by
FEMA.
The work at
1542 Tulane Ave. to
prepare the front portion of the building to be
re-occupied continues. Ducts have been cleaned and are now being
sealed with an encapsulant that will help to
minimize future mold growth and the spread of
particulate matter. Holes cut in the ducts to provide access for
the cleaning are being sealed. All of the building debris has been removed
from the front and center sections of the building. The crews are now working in the rear (old)
section of the building which will not be put back
into use immediately. All of the damaged carpet has been removed
and much of the floor tile is gone as well. The task of removing the vast amounts of
peeling paint from ceilings and walls has been
daunting. Every surface that has paint removed must
also be floated, primed and re-painted to seal the
walls and prevent any further peeling. However, the contractor is making good
progress. Furniture to replace the items that were
damaged by mold and removed is being coordinated
with the School of Medicine
and many items have already been ordered.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Lions/LSU Clinic Permanent
Repairs:
- Our first major project
for permanent repairs and mitigation is about to
get underway. The contract for the permanent repairs
and Section 406 Hazard Mitigation to the
building has been executed by Construction
Masters, Inc.
- The pre-construction
conference was held on February 7th with
representatives of the contractor, the
sub-contractors, the Office of Facility
Planning & Control, the LSU Systems Office
and LSUHSC.
- The contractor is
preparing his plans for sequencing the work
and we are coordinating with the academic
departments who have faculty and staff in
the spaces scheduled for some of the initial
demolition work.
- Work on some of the
demolition may begin as early as next week.
- The scope of the contract
includes:
- Re-building the
Isadore Cohn Learning Center on the 6th Floor.
- Relocating an existing
research lab from the 6th Floor to the 7th
Floor.
- The 6th Floor lab
will remain in operation until the
replacement lab on the 7th Floor is
ready for use.
- Moving the critical
mechanical, electrical and plumbing
equipment to the 2nd Floor.
- Constructing an
exterior stairwell on the front of the
building to provide adequate egress from the
new Learning Center.
- The restoration of the
public areas of the 1st Floor that will use
surfaces that will resist damage from flood
waters.
- The dry-flood proofing
of the building elevator pits.
- Roof repairs.
Repair Work at
1542 Tulane Ave.:
- Fire Alarm System:
- Siemens has completed
the trouble-shooting of the fire alarm
wiring on the 6th Floor.
- They have programmed
the fire alarm devices on the 6th Floor and
cleared all the trouble codes.
- All the trouble codes
have been cleared on the 7th and 8th Floors,
and in the penthouse.
- Siemens is trouble
shooting new ground faults for the fire
alarm wiring in the basement on the fire
pump and dry-pipe sprinkler system that
serves the parking garage.
-
They are resetting trouble codes on the 1st
Floor.
- Elevator Repairs:
- Elevator #1:
- Stratos Elevator has installed the safeties.
- They are installing the hoist cables, whisper cables and rigging equipment.
- Elevator #7:
- Stratos has begun installing the Position Indicators in the elevator lobbies.
- Elevator #8:
- They are wiring the controller on Elevator #8.
- Stratos has begun installing the Position Indicators in the elevator lobbies.
- Final Remediation and Duct Cleaning:
- Duct Cleaning Status:
- Zimmer finished sealing the ducts on the 4th Floor.
- Zimmer has coated the ducts on the 3rd Floor and has sealed the holes that were cut into the ducts.
- Zimmer has coated the ducts on the 2nd Floor with an anti-microbial solution and has sealed the access holes that were cut into the 2nd Floor ducts.
- Zimmer finished removing the transite exhaust ducts on the 6th, 7th and 8th Floors.
- They have begun removing the transite ducts on the 5th Floor.
- Debris Removal
- Zimmer continued to remove debris in the rear of the building (old section).
-
Final Remediation/Cleaning:
- Zimmer finished
removing the peeling paint and cleaning on
the 7th Floor in the rear of the building
(old section) on the I-10 side.
-
The 7th floor (old section - Charity
side), passed the visual inspection and
air samples were taken.
- Zimmer finished
cleaning and paint removal on the 6th Floor
in the rear of the building (old section) on
the Charity side.
- The area passed
the visual inspection and is being
scheduled for mold sampling.
- The contractor
began cleaning the I-10 side of the 6th
Floor (old section).
- The contractor
finished installing the new sheetrock on the
8th Floor to replace the drywall that was
removed during the mold remediation.
- The contractor
finished installing the new sheetrock on the
6th Floor to replace the drywall that was
removed during the mold remediation.
- The new sheetrock
installed on Floors 6 & 8 have been taped
and floated.
- The contractor
continues to install new sheetrock on the
7th Floor.
- Painting:
- The contractor primed
the walls on the 7th Floor.
- They have cut in
with the finish paint throughout the
floor.
- They have spayed
on the finish coat in the corridors.
- They are spraying
on the finish coat in the offices and
conference rooms.
- The contractor floated
and primed the walls on the 6th Floor.
- They have cut in
with the finish paint.
- They have sprayed
on the finish coat in the corridors.
- They are applying
the finish coat in the offices and
conference rooms.
- The contractor has
floated and primed the walls on the 5th
Floor.
- The contractor has
cut in with the finish paint.
- They are applying
the finish coat in the corridors.
- The painters finished
floating and prepping the walls on the 4th
Floor.
- Floor Tile Removal:
- Zimmer has removed the
damaged floor tile and mastic from the 3rd
Floor in the corridors and offices along
Tulane Avenue and
in the "A section" (over the garage).
- The area passed the visual inspection
and samples have been taken.
- Zimmer finished
removing the floor tiles in the center
corridor on the 3rd Floor.
- The contractor is
prepping the area for a visual
inspection.
- Ceiling Tile Replacement:
- The contractor
completed the installation of new ceiling
grid "tees" on the 6th, 7th, and 8th Floors
to convert the existing 2' x 4' ceilings to
2' x 2' ceilings.
- The contractor is
also removing and replacing any damaged
ceiling grid.
- Network Closets:
- Trison finished
sealing the wall and ceiling penetrations in
the new network closets.
- Network closet
construction is complete with the
exception of the installation of new
HVAC grilles.
- Boe-tel finished
terminating the new network cables on the
7th Floor.
- They finished removing
old network wire mold on the 6th Floor.
- They have removed the
old network wire mold on the 5th Floor.
- Boe-tel removed the
old network wire mold on the 4th Floor.
- They are pulling
new cable on the 4th Floor.
- Boe-Tel is removing the old wire mold from the 3rd Floor.
- Boe-Tel is pulling new network wires from office stations to the new network closet on the 1st Floor.
- They finished installing the final components of the network rack on the 1st Floor.
- Boe-Tel began installing network drops in the offices on the 1st Floor.
Repair Work at the Dental School:
- Roof Replacement:
- Needham Roofing
removed approximately 230 squares (100
square feet per square) of the old roofing
from the Administration Building.
- They installed the
first ply of the new roof over the same
area.
- Needham Roofing
substantially completed the tear off and the
installation of the first ply of the new
roof on the balcony of the Clinic Building.
- Needham Roofing began
installing the flashing around the perimeter
of the Administration Building roof.
- Needham Roofing is
installing the pitch pans on the Clinic Building
roof around the various penetrations through
the roof.
- They also assessed the
roof leaks that were revealed by the heavy
rains earlier in the week and began to
prepare for the forecasted weather this
weekend.
- Needham Roofing
re-flashed sections at the perimeters of
the Clinic and Administration Building roofs.
- They tore off and
applied the 1st ply completing the tie
in where the scaffolding rested on the
roof over the breezeway.
- They also split
and patched wrinkles in the roof
material on both buildings to thwart
possible leaks.
- Temporary Bookstore:
- Sherlocks Construction
finished the carpet and ceiling tile
installation in the hall between the
temporary bookstore and the Library.
- They also removed the
temporary dust partition inside the Library
and erected a temporary wall in the new
corridor to block access from the Library to
the work site.
- Sherlocks continued
installing sheet rock on the walls for the
temporary bookstore.
- As the sheet rock
is installed, they are taping and
floating the walls.
- The carpet has been cut in around the new walls and the wall base has been installed.
- The contractor worked
on closing up the ceiling in the temporary
bookstore; installing the remaining ceiling
grid and tiles.
- They continued balancing the air supply for the new space.
- Sherlocks pulled data/telephone wires and wired outlets for the temporary bookstore.
- Elevator Repairs:
- Elevator #3:
- The repairs and
upgrades to Elevator #3 have been
completed.
- The elevator
is now in service.
- Schindler is
installing the hall lanterns for
this elevator in the floor lobbies.
- Elevator #4:
- The repairs and
upgrades to Elevator #4 have been
completed.
- The elevator
is now in service.
- Schindler is
installing the hall lanterns for
this elevator in the floor lobbies.
- Elevator #8:
- Schindler
continued to work on the door operator.
- NOTE: Elevator #1
in the Clinic Building will be
taken out of service to allow the
interior and control upgrades to be
completed once the repairs and upgrades
to Elevator #8 have been completed and
the elevator is back in service.
- Freight Elevator:
- During the heavy
rains on 2/12/08, water leaked through
areas of the roof that are being
replaced and damaged the freight
elevator. It has been taken out of service
and the damage assessed by Schindler.
- Schindler has
provided LSUHSC with a quotation to
repair the damage.
- The State Elevator
Inspector has been contacted and asked
to inspect the damage and verify the
quote.
- The Schindler
damage assessment and quotation has
been picked up by the Inspector.
- Once the scope
of work has been validated, LSUHSC
will immediately issue a Purchase
Order for the repair work.
- The current
estimate from Schindler to complete
these repairs is six weeks from the
receipt of the Purchase Order.
- At this time, these
elevators are in service:
- Elevator #1
(Clinic)
- Elevator #2
(Clinic)
- Elevator #3
(Clinic)
- Elevator #4
(Clinic)
- Elevator #6
(Admin)
- Elevator #7
(Admin)
- Security:
- Securitas ran wires to
install security cameras located next to the
intercom speakers at the entrances to the
Clinic Building.
MEB Roof Replacement:
- The contractor has
completed installing the last temporary roof
portion on the S. Roman St.
side of the building.
- All of the lightweight
concrete has been poured on the roof of the
building, including the penthouses.
- The contractor has started
installing the next ply of roofing materials
over the lightweight concrete on the Allied
Health side of the building.
- During the night time
hours of 2/15, heavy rains hit the downtown
campus.
Water leaked through portions of the roof and
damaged one of the emergency power bus duct;
causing a dead short that burned the feeders.
- The roofing contractor
is already on site early on 2/16/08 and is
making repairs to prevent a similar
occurrence.
- An electrical
contractor is under contract to make
emergency repairs to restore emergency power
to those parts of the building that were
impacted.
- Permanent repairs will
be addressed later.
- The Builders Risk
insurance carried by the roofing contractor
is expected to reimburse the costs that will
be incurred.
Landscaping Project:
- Crews installed irrigation
pipe and sprinklers between the sidewalk and
street curb on the Perdido Street
side of the Residence Hall.
- They trenched for the
irrigation pipe on the building side of the
sidewalk and prepared to connect to the backflow
preventer.
Downtown Campus – 1st Floors:
- The State Fire Marshal has
required that we take measures on the unoccupied
1st Floors and basements of the buildings on the
downtown campus. This work will insure that the existing
sprinkler systems will function properly while
we wait for the permanent repairs to be
designed, bid, contracted and completed.
- In the majority of the
buildings, the most cost effective method of
accomplishing this goal is to re-install
ceiling tiles into the existing ceiling grid
on the 1st Floor.
- A contract has been issued
for this work.
- Trison completed
installing the temporary ceiling tiles in
the MEB, the Residence Hall, the CSRB, the
Resource Center and the
Allied Health/Nursing Building.
- The crews have moved
on to Lions/LSU Clinic Building.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|