|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #66
Posted: April 11, 2008
As part of our continuing
efforts to improve the security and safety of the
downtown and Dental School campuses, we will
activate Access Control on Monday, April 14. All faculty, staff, students and MCLNO
employees (for the downtown campus) will be able to
access facilities with their ID cards at any time.
The one
exception will be ground floor access to the Allied
Health/Nursing Building. This entry will only be available during
“normal hours” until cameras can be installed and
tested on the exterior of the doors and inside in
the elevator lobby.
Normal working hours have been
defined as Monday through Friday, 7:00 AM to 6:00
PM, excluding holidays. Access Control will be off during these
hours, the regular entrances to buildings will be
unlocked and everyone will be able to enter and exit
campus buildings as they presently do. Outside of normal working hours (on weekends
and holidays), the faculty member, staff person, or
student must use their ID card for access. Readers are positioned at entry doors and
elevators where Access Control is installed. By holding a current ID card to the reader,
it will unlock the door and allow entry.
Entry via loading dock doors
will be restricted to specifically authorized
individuals and will not be for general access. There will be additional rooms or areas, such
as specific core labs, animal care, data center,
etc. where access will be restricted to specific
authorized personnel.
Another aspect of the project
to improve campus security is continuing. New exterior lights are being installed at
and around the Student Residence Hall. The pole mounted lights surrounding the
basketball courts have been installed and are in
operation. New conduit, electrical cable and light
fixtures are being installed underneath Interstate
10 to enhance the parking lot lighting behind the
Residence Hall.
The work on the permanent
repairs and hazard mitigation at the Lions/LSU
Clinic Building is progressing well. The demolition on the 6th and 7th Floors is
substantially completed. The framing of the walls for the new
laboratory space is well underway and the rough in
electrical work has begun. The layout of the walls on the 6th Floor is
well underway and the framing has started. Work also continues on the dry flood proofing
of the first elevator pit. The cleaning and repair of the flood damaged
windows and window frames on the ground floor is
well underway and should be completed in the near
future.
A great deal of effort is being
expended to allow the reoccupation of portions of
1542 Tulane Ave. The final remediation work is nearing
completion. A substantial portion of the fire alarm
system has been replaced and tested. The damaged floor tile has been removed and
new carpet tiles, transition strips and base molding
are being installed in spaces as the painters
complete their work. The painting crews are moving rapidly to
complete the significant amount of repainting that
was needed to address the large volume of peeling
paint throughout the building. The replacement of the ceiling tiles is
progressing well. Trimming and fitting the edge and corner
tiles has been time consuming, but three floors have
already been completed. Repairs to three additional elevators are
nearing completion and the contractor is engaged in
the final testing and working the punch list to
prepare for the final inspection.
The old Medical School Building
is also having new light fixtures installed in the
ceilings. Several truck loads of new fixtures have been
received and staged in warehouses in town and large
deliveries are periodically being made to the
building. The ceiling fixture installers are currently
at work on four of the upper floors. Truck loads of new furniture have also been
delivered to the site and staged throughout the
building. As spaces are prepared, (ceiling tile
installed, painting complete, carpet installed,
etc.) the furniture is being uncrated, assembled as
necessary and installed. The project to upgrade the network
infrastructure is also progressing on schedule.
The temporary bookstore at the Dental School
is nearing completion. The construction is substantially complete,
except for a recent change order to add additional
electrical capacity to address future needs. Auxiliary Enterprises has the new slat wall
and book store casework scheduled to be installed
starting next week. Campus Federal Credit Union has installed its
new ATM machine in the new location outside the
Bookstore and removed the temporary equipment.
The repairs to Elevator # 8 at
the Dental School
have been substantially completed. The elevator was inspected by the State
Elevator Inspector and certified for normal use. The contractor has some punch list items to
complete, but they do not prevent use of the
elevator. The repairs to the freight elevator required
by the roof leaks in February are progressing well. We believe that the repairs may be completed
within the next two weeks.
The last few
small buildings located on the back campus of the Dental School
that were scheduled for demolition have been
removed.
Some debris remains to be removed and the final
grading and seeding will be completed shortly.
The two permanent roof
replacement projects are underway again. Crews on the Medical Education
Building have completed
the installation of the final layer of roof material
on the penthouse roofs. They have also installed the first two layers
on a substantial portion of the parapet wall. At the Dental School,
a significant portion of the old roof on the Power
Plant has been removed and the new insulation, deck
board and granulated layer have been installed.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Lions/LSU Clinic Permanent
Repairs and Mitigation:
- On Monday, March 24th, the
contractor responsible for the Lions/LSU Clinics
Building permanent repairs and mitigation
project shut down Elevators #3 and #4 in order
to begin dry flood-proofing the elevator pits. These modifications are being done to
reduce damages and downtime in case of any
future flood event.
- The work on the pit
for Elevators #3 and #4 will take
approximately 8 weeks, during which time
only Elevators #1 and #2 will be available
for service.
- Once the pit work is
complete for Elevators #3 and #4, the
elevators will be returned to service.
- The contractor will
then begin work on the pit for Elevators #1
and #2. The freight elevator pit will be the
last one worked on.
- CMI completed the
demolition of the bathroom floors on the 6th
Floor.
- All of the demolition
on this floor has been completed.
- The crews are framing up
the walls for the 7th Floor lab.
- The electrical rough
in has begun in this space.
- The layout for the new
walls on the 6th Floor is finished and the
framing for the new walls has started.
- Crews have been removing
the metal trim and frames from around the
exterior windows on the 1st Floor to start the
cleaning and restoration process.
- The metal frames and
casing are being cleaned and the corrosion
is being removed.
- The metal is then
painted with a protective coating.
- The window units are
cleaned and the entire window assembly is
reinstalled.
- New shut off valves were
installed in the 1st Floor bathrooms, the 6th
Floor bathrooms and in the water lines on the
7th Floor so that old pipe can be removed and
new pipe installed without requiring a shutdown
of the entire building.
Repair Work at
1542 Tulane Ave.:
- Fire Alarm System:
- The contractor
finished installing new fire alarm devices
on the 2nd Floor in the old section of the
building on the I-10 side and behind the
elevators on the 3rd Floor.
- Siemens finished
installing the fire alarm devices on the 2nd
Floor in the old section of the building on
the Charity side.
- The contractor
installed and tested the new fire alarm
devices in the P-3 Lab on the 4th Floor
roof.
- The contractor
connected and tested the monitoring points
between the fire alarm panel and the
automation panel.
-
Siemens installed smoke detectors in the
elevator shaft of Elevator #8.
- Elevator Repairs:
- Elevator #1:
- They re-painted the elevator lobby doors on the 2nd Floor.
- The contractor finished painting the floor in the elevator penthouse.
- Stratos continued to work on punch-list items; cleaning the elevator doors, guides, and thresholds.
- The elevator is being tested in preparation for the final inspection by the State Elevator Inspector.
- Elevator #2:
- They re-finished the elevator lobby doors on the 2nd Floor.
- The contractor finished painting the floor in the elevator penthouse.
- Stratos continued to work on punch-list items; cleaning the elevator doors, guides, and thresholds.
- The elevator is being tested in preparation for the final inspection by the State Elevator Inspector.
- Elevator #3:
- They re-finished the elevator lobby doors on the 2nd Floor.
- The contractor finished painting the floor in the elevator penthouse.
- Stratos continued to work on punch-list items; cleaning the elevator doors, guides, and thresholds.
- The elevator is being tested in preparation for the final inspection by the State Elevator Inspector.
- Stratos technicians fire caulked the penetrations in the elevator shaft and penthouse.
- Final Remediation and Duct Cleaning:
- Remediation:
- Zimmer-Eschette
finished cleaning on the 1st Floor in
the old section of the building on the
I-10 side.
-
Zimmer-Eschette began cleaning the
corridor and elevator lobby on the 1st
floor in the old section of the
building.
- Zimmer-Eschette is
re-cleaning miscellaneous areas
throughout the building on various
floors in the old section of the
building.
- Cleaning in
the corridor and elevator lobby on
the 1st Floor in the old section of
the building will resume as the
re-cleaning is completed.
- Painting:
- 3rd Floor:
- The painters have
finished applying paint in the offices
along the center corridor.
- The contractor
continues to apply finish paint in the
offices along Tulane Ave.
- 2nd Floor:
- The contractor
finished priming the corridor walls and
offices along Tulane Ave.
- The priming in the
offices along the center corridor is
complete.
- The painting
contractor finished applying paint in
the offices along the center corridor.
- Painters are
applying the finish paint in the offices
along Tulane Ave.
-
They are applying finish paint in the
offices along the center corridor.
- 1st Floor:
- They finished
priming the walls in the offices along
the center corridor.
- The painters
finished painting the offices along the
center corridor.
- They are applying
touch-up paint in the mezzanine offices.
- Floor Tile Removal:
- The contractor
finished removing floor tile from the 1st
Floor in the old section of the building on
both the Charity and the I-10 side of the
building.
- Ceiling Tile Replacement:
- The crews have
finished trimming and installing the edge
and corner tiles on the 7th Floor.
- The contractor
finished trimming and installing the edge
and corner ceiling tiles on the 6th Floor.
- The contractor
finished trimming and installing the edge
and corner ceiling tiles on the 5th Floor.
- The contractor began
trimming and installing the edge and corner
ceiling tiles on the 4th Floor.
-
Carpet Installation:
- Royerre Commercial
Carpet has finished installing carpet tiles,
transitions, and cove base on the 8th Floor.
- Royerre is installing
new carpet tiles, transition strips, and
cove base on the 7th Floor.
- They have finished
installing carpet tiles, transitions, and
cove base on the 6th Floor.
- They have finished
installing carpet tiles, transitions, and
cove base on the 5th Floor.
- The Royerre installers
finished installing the carpet tiles on the
4th Floor.
- They are
installing cove base and transition
strips on the 4th Floor.
-
Network Upgrades:
-
Boe-Tel finished constructing the new
network rack for the 3rd Floor network
closet.
- Boe-Tel finished
terminating the station cables in the
offices on the 3rd Floor along the
Tulane Ave.
side of the building.
- Trison Constructors
began work on the change order to expand the
4th Floor network closet.
- Their crews framed
the closet and installed new sheetrock
on the walls.
- They installed the
new sprinkler heads and plywood
backboard.
- Boe-Tel completed the
installation and termination of new station
cables on the 6th Floor.
- Boe-Tel completed the
installation and termination of new station
cables on the 8th Floor.
-
The contractor terminated and tested the
wiring and connections for the 1st Floor
network closet.
- New Furniture:
- Herman Miller Group
delivered several loads of new furniture and
staged it throughout Floors 5 through 8.
- New furniture is being
installed in the offices along the center
corridor on the 6th, 7th and 8th
Floors.
- Ceiling Light Fixtures:
- Approximately 12
pallets of new light fixtures were delivered
to the site.
- The contractor has
crews working on the installation of the new
ceiling light fixtures on the 5th, 6th, and
7th Floors.
Repair Work at the Dental School:
- Permanent Roof Repairs:
- Needham Roofing
received additional roofing materials for
the Administration Building Penthouse and
the Power Plant.
- The installation of
the granulized 2nd ply has been completed on
the Administration
Building
penthouse roof.
- Crews have removed 23
squares (one square equals 100 square feet)
of the old roofing material from the Power
Plant.
- They have
installed the new insulation, decking
and the granulated 2nd ply material over
the prepared areas.
- Temporary Bookstore:
- Sherlocks Construction
tested the fire alarm system in the
temporary bookstore and verified the
connection with the building fire alarm
system in preparation for the State Fire
Marshal inspection.
- The slat-wall and
bookstore furniture installation is
underway.
- Campus Federal Credit
Union installed the permanent ATM in the
vestibule of the temporary bookstore.
- The temporary
machine that has been located in the
breezeway will be removed tomorrow.
- Elevator Repairs:
- Elevator #8:
- Schindler
installed hand rails and electrical
covers for Elevator #8 in the Administration
Building.
- The repairs to
Elevator #8 have been completed.
- The State
Elevator Inspector has certified the
elevator for normal use.
- The contractor is
completing the punch list.
- Freight Elevator:
- Schindler
continued to wire the new switches for
the freight elevator.
- They also worked
on wiring the controller.
- Schindler installed
new handrails in Elevator #4 and prepped
Elevator #3 for the installation of new
handrails.
- Schindler continues
working on the punch list for Elevators # 6,
#7, and #8.
- Demolition:
- HDC Building
119 (Barracks)
- The building has
been demolished and the debris has been
removed.
- The site has been
backfilled and sand has been spread.
- The work has been
completed and the punch list provided to
the contractor.
- HDC Administration
Building 138
(Barracks)
- The building has
been demolished and the debris has been
removed.
- The concrete
sidewalk has been demolished.
- The site has been
backfilled and sand has been spread.
- The work has been
completed and the punch list provided to
the contractor.
- HDC Building
124 (Day Care)
- The site has been
backfilled and sand has been spread.
- The work has been
completed and the punch list provided to
the contractor.
- HDC Building
180 (Library)
- The site has been
backfilled and sand has been spread.
- The work has been
completed and the punch list provided to
the contractor.
-
HDC
Building 100 (Storage Building)
- The work has been
completed and the punch list provided to
the contractor.
- Storage Barn
- The work has been
completed and the punch list provided to
the contractor.
- Disposal Facility
- The work has been
completed and the punch list provided to
the contractor.
- Auto Shop
- The work has been
completed and the punch list provided to
the contractor.
- Green House
- Grading and
seeding has been completed.
- The work has been
completed and the punch list provided to
the contractor.
- Misc.:
- Sherlocks Construction
began running conduit for the transformer
and circuit panels that will expand the
electrical capacity for future power
requirements in the Bookstore and Library.
MEB Roof Replacement:
- Crawford has completed the
installation of the mineral surface modified cap
sheet (final layer) on all the penthouse roofs.
- Crawford completed
installing most of the base smooth modified
torch grade layer (the first of two layers
before the installation of the metal cap) on the
perimeter of the parapet wall.
- Crawford started
installing the Mineral Surface Modified Cap
sheet on the main roof above the loading dock.
Downtown Landscaping Project:
- Crews removed broken
concrete in front of the
1542 Tulane Ave.
front steps in preparation to install sleeves
for the irrigation pipe and valve control wires.
- The crews installed
nozzles on all of the sprinklers around the
Residence Hall and fully activated the system to
run according to the programming on the
controller.
- They started the final
grading on the
Perdido St. side of
the Residence Hall.
- The crews removed all the
existing vegetation on the
Perdido St. side of
the Residence Hall in preparation for installing
new plants.
- They started removing the
existing vegetation on the
Perdido St.
side of the MEB.
Exterior Lighting Project:
- Frischhertz is installed
conduit and lights around the base of the
basketball court at the Residence Hall.
- The light poles are
up, the electrical service has been
installed and the lights are operating.
- Frischhertz is installing
conduit and wire for lights that will be
installed under I-10 in the Residence Hall
parking lot.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|