|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #67
Posted: April 25, 2008
With much of the temporary
repair work completed or nearing completion around
campus, our focus has shifted to the more complex
and time consuming process of designing the
permanent repairs and related Section 406 Hazard
Mitigation for our major buildings. There are two fundamental parts to the
process as we seek FEMA approval.
We begin by working with our
architects and engineering teams to develop
relatively high level design concepts for each
building. The conceptual documents set forth all of the
significant elements of the proposed 406 mitigation
work, provide some basic drawings and include the
initial cost estimates for the specific concept. These are reviewed by LSUHSC and the Office
of Facility Planning and Control. They are then forwarded to the 406 Mitigation
Team within the Governors Office of Homeland
Security and Emergency Preparedness (GOHSEP). GOHSEP reviews each proposal and completes a
preliminary Benefit Cost Analysis (BCA) to insure
that the proposal appears to be cost beneficial. GOHSEP then forwards the design concepts to
the FEMA Health & Research Team for their
consideration and preliminary approval. FEMA will consider the proposal for
eligibility of the work as proposed, the technical
feasibility of the mitigation concept, and the cost
effectiveness (based on the BCA).
The following are brief
summaries of the design concepts that have been
submitted to FEMA and are pending their preliminary
approval:
- Dental School Clinic, Administration & Power Plant:
- This proposal
combines the permanent repairs of all three major
buildings; the Clinic Building,
the Administration Building and the Power
Plant. The mitigation concept focuses on elevating all of
the critical functions and mechanical, electrical
and plumbing equipment into a new Clinic Building
Annex, and elevating other critical equipment within
the Power Plant. Additional emergency generation capacity and
extended fuel supplies for the generator(s) will be
provided, and a small Emergency Operations Center will be provided.
- 1542 Tulane Ave.:
- All of the building
system components that were originally located in
the basement will be elevated into an addition built
over the Lakeside Parking Lot. Additional fuel capacity for the emergency
generator(s) will be provided.
- Central Utility Plant:
- The critical pumps
and related electrical systems that supply the
majority of the downtown buildings with chilled
water for air conditioning and steam for heat will
be elevated to the platform that currently carries
two cooling towers. The cooling towers will be removed to make
the necessary space available and a single smaller
cooling tower will be installed to provide a limited
supply of chilled water, should the Entergy Thermal
system fail or go down.
- Roman St. Garage:
- In addition to
completing the eligible permanent repairs, the
equipment that runs the two passenger elevators will
be elevated from the ground floor and located on the
3rd Floor.
- District Entergy Garage:
- The majority of the
work will be making the permanent repairs to the
structure. Where practical, new materials will be used
that resist water damage and that can be easily
cleaned should they be flooded in the future.
- Walk To Wellness:
- The key mitigation
proposal is to elevate the pumps that supply water
to the overhead fire sprinklers and their related
systems above the flood level.
When FEMA gives their
preliminary approval of a design concept, the
architects and engineers will produce the
Design/Development submittal (D/D). This is a much more complete set of drawings
and specifications, but not as complete as the
Construction Documents that will be sed to bid and
build the project. Similar to the design concepts, the DD
submittal is reviewed by LSUHSC, FP&C, and GOHSEP. They are then forwarded to FEMA for their
formal review and approval. This submission will result in the
preparation of a formal Hazard Mitigation Proposal
and version(s) to the related Project Worksheets. When approved, the State will have funds set
aside by FEMA to cover the estimated cost for the
project.
The following are the
Design/Development submittals that have been
forwarded to FEMA and are under review, but not yet
approved:
- CSRB/MEB:
- This proposal
addresses the permanent repairs in both buildings. The key mitigation measure is the
construction of an addition that will begin on the 3rd
Floor and extent to the existing roof level on the
back of the CSRB. This addition will allow for the vivariums
previously located on the 1st Floors of both
buildings to be elevated above the flood of record. The addition will also house and elevate
critical mechanical, electrical and plumbing
equipment that was damaged on the 1st Floor of the
CSRB. Critical MEP at the Medical Education Building
will be elevated within that structure. The final important element of the proposal
is to provide two large (non-life/safety) emergency
generators located in the addition that will be able
to provide for basic power needs for all of the
buildings in the downtown campus area (except for
1542 Tulane and Stanislaus Hall). The emergency power would be sufficient to
maintain the critical animal care areas, keep
critical research freezers and refrigerators
functioning, the morgue cooled, provide power to
sustain the critical statewide network components
located on the 7th Floor of the Resource Center and
to provide for basic interior air conditioning that
would protect building contents from high heat and
humidity and the buildings themselves from mold. A modest Emergency Operations
Center will be included as well.
- Allied Health/Nursing Building:
- The mitigation
measures proposed will elevate all of the critical
MEP to the 2nd Floor or above the flood of record in
1st Floor spaces. The restoration of the 1st Floor spaces will
take advantage of some wet flood proofing
techniques.
- The Construction
Documents will include some non-FEMA work that will
assist the School of Nursing in expanding class sizes.
- Student Residence Hall:
- In this case, space
for elevating the critical MEP within the existing
structure is very limited, so the proposal includes
the construction of a modest elevated single floor
addition to house this equipment. It will be located behind the building and
will be at the level of the existing basketball
court.
- Resource Center:
- The mitigation
measures proposed will elevate all of the critical
MEP to the 2nd Floor or above the flood of record in
1st Floor spaces. The restoration of the 1st Floor spaces will
take advantage of some wet flood proofing
techniques. The life/safety emergency generator will be
mounted on the roof to protect it from flood waters.
Whenever a D/D submittal is
approved, the design team moves forward with the
development of the Construction Documents. These documents are used as part of the bid
package and represent the actual construction work
that will be included in the resulting contract. To date, only the Lions/LSU Clinic Building
has proceeded to the CD phase and is under
construction. LSUHSC, the Office of Facility Planning and
Control, and GOHSEP continue to work closely with
FEMA to move all of the outstanding design concepts
and Design/Development submittals forward.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Lions/LSU Clinic Permanent
Repairs and Mitigation:
- The crews continue framing
up the new interior walls for the 7th Floor
laboratory.
- The rough in
electrical and plumbing for the space is
proceeding well.
- The layout for the new
walls on the 6th Floor is finished and the
framing of the new interior walls is well
underway.
- Crews have been removing
the metal trim and frames from around the
exterior windows on the 1st Floor as part of the
cleaning and restoration process.
- The metal frames and
window casings are cleaned and the corrosion
is removed.
- The metal surfaces are
then painted with a protective,
anti-corrosion coating.
- The window units are
cleaned and the entire window assembly is
reinstalled.
- The work around the
building is nearing completion.
- The work on the dry flood
proofing of the 1st elevator pit continues and
appears to be on schedule.
Repair Work at
1542 Tulane Ave.:
- Elevator Repairs:
- Stratos tested the fire control relays for Elevators
#1, #2, and #3 in preparation for final inspection
by the State Elevator Inspector.
- The State Fire Marshal
tested Elevators #1, #2, and #3 and the
elevators tested successfully in conjunction
with the fire alarm/elevator relays.
- Stratos resumed work
on Elevator #7.
- They have changed
out the door hardware.
- Stratos is
changing out the components in the
elevator pit.
- Final Remediation and Cleaning:
- Zimmer-Eschette finished re-cleaning miscellaneous
areas throughout the old section of the building.
- Zimmer has prepared the 1st Floor side entrance and
corridor in the old section of the building for
remediation/cleaning.
- Crews have started cleaning the offices along the
corridor.
- Painting:
- The painting contractor finished applying the
touch-up paint in the mezzanine offices and other
miscellaneous areas around the building.
- The painting
contractor has started preparing the walls
in the old portion of the building for
paint.
- They started on
the 8th Floor and are working down
through the building.
- The painting
contractor prepped and painted the
stairwells along the Tulane Ave. side of the building.
- Stairwell D was
prepared and painted.
- The contractor is
currently preparing Stairwell C to be
painted.
- Ceiling Tile Replacement:
- The contractor finished trimming and installing the
edge and corner ceiling tiles on the 1st, 2nd, 3rd
and 4th Floors.
-
Carpet Installation:
- The installers
finished the installation of carpet tiles,
transition strips and cove base on the 4th
and 7th Floors.
- The contractor
finished installing the VCT on the 3rd and
4th Floors.
- The contractor is
installing carpet tiles, transition strips
and cove base on the 2nd and 3rd Floors.
-
Network Upgrades:
- Boe-Tel pulled the new
network fiber cable from the 1st Floor
network closet to the 6th Floor closet.
- Trison Construction
taped and floated the new walls of the 4th
Floor network closet.
- Trison primed and
painted the new walls for the 4th Floor
network closet.
- Trison installed new electrical rough-in for the 4th Floor network closet.
- The new electrical outlets have been installed.
- Trison installed the flooring for the 4th Floor network closet.
- New Furniture:
- The Herman Miller Group delivered the last of the office
chairs for the 1st through the 8th Floors.
- The Herman Miller Group is assembling and installing
furniture in the offices on the 5th Floor.
- Ceiling Light Fixtures:
- The new ceiling lights have been installed on the 4th Floor.
- Hogue continues to
install the new ceiling lights on the 5th
and 6th Floors.
Repair Work at the Dental School:
- Permanent Roof Repairs:
- Needham Roofing has
completed work on the replacement of the
Power Plant roof.
- They removed all
of the old roofing material and replaced
it with the new two ply roof.
- The flashing and
trim work has also been completed.
-
Needham
has loaded additional materials onto the Clinic Building
roof and has resumed work on the penthouse
roof.
- They removed a
total of 58 squares of roofing material
that was damaged from water intrusion
and installed new insulation, decking
and the granulated cap sheet.
- They have
installed the perimeter flashing.
- Temporary Bookstore:
- Sherlocks Construction
ran new conduit from the feeder location to
the electrical panel room in preparation for
the installation of a new transformer and
circuit panel.
MEB Roof Replacement:
- The contractor completed
the remainder of the base smooth modified torch
grade material on the parapet wall located on
the
S. Roman St. side of
the building.
- This is the first of
two layers before the installation of the
metal cap.
- Crawford continues to
install the mineral surface modified cap sheet
(final layer) on the main roof of the building.
Downtown Landscaping Project:
- Crews removed the
existing vegetation from around the new oak tree
on the Perdido St.
side of the MEB.
- The final grading on the Perdido St.
side of the Residence Hall has been finished in
preparation for planting.
- The crews completed the
planting and mulching in all ten landscape areas
on the Perdido St. side of the Residence
Hall.
Exterior Lighting Project:
- Frischhertz finished
installing the new electrical wire and light
fixtures under Interstate 10 at the Residence
Hall parking lot.
- Frischhertz is painting
the bases of the new light poles that have been
installed at the Residence Hall parking lot.
Parking Lot Improvements:
- Boh Bros removed the
existing limestone rock from Interstate-10
Parking Lot #3.
- They have installed
concrete forms and poured a new concrete parking
surface.
- Boh Bros installed a new
culvert in the lot and connected it to the
underground draining system to improve the
drainage in the lot.
- Crews formed and poured
the concrete curb and driving lane for the lot.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|