|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #76
Posted: August 29, 2008
Hurricane Gustav is threatening
significant portions of the Gulf
Coast and hurricane preparations are underway. LSUHSC Facilities personnel have been at work
positioning sand bags, locating the elevator door
dams, and clearing the campus of objects that could
become wind blown projectiles, etc. The contractors on site are also making their
preparations; protecting their construction areas,
and preparing to shut down their activities if an
evacuation is necessary.
In spite of this, a great deal
of work has been underway for the past two weeks. At 1542 Tulane Ave., we
continue to prepare the front and center sections of
the building to be re-occupied. Fan coil units are being repaired and/or
replaced as necessary. Repairs to Elevators #4 and #7 are
progressing. The demolition of the lounge areas on Floors
2 and 3 has been completed and the contractor has
begun framing up new walls for the lounges on Floors
3 through 7. A new sidewalk has been poured in front of
the building and irrigation piping is being
installed. The terrazzo honing efforts are progressing
well.
The contractor working in MDL
#5 has installed the HVAC and supply air grilles in
the ceiling grid. The sprinkler heads have been relocated. The sub-floor has been prepared for laying
new tile and the tile layout is underway. The new sub-floor has been poured in the 2nd
Floor Lobby of the MEB, the drywall is being floated
and sanded, and the new walls are being primed. The replacement of the ceiling on the 4th
Floor of the MEB shows significant progress. A majority of the ceiling lights have been
installed. New flex duct and supply grills are being
installed. The sprinkler heads have been repositioned
and the installation of new ceiling tiles has
started.
The permanent repairs and
hazard mitigation work at the Lions/LSU Clinic
Building are ongoing. New walls on the 6th and 7th
Floors are being dry walled and insulated. Power cable has been run from the Entergy
vault to the 2nd Floor location of the
new elevated switchgear. The medical gas and vacuum lines are being
run to the new simulation rooms located on the 6th
Floor.
New exterior glass has been installed on the 1st
Floor and the trim pieces that frame each window
pane are being installed. A variety of plumbing work is underway and
the connections to one of the new VAVs on the 6th
Floor are being made.
The two new initiatives at the Dental School
are moving forward. Old wiring has been removed from the lab
spaces being renovated in the Clinic Building. The rough in of new electrical service has
begun in the same areas. The drain lines have been removed from
beneath Room 8405 and new duct work is being
installed. The remaining demolition has been finished in
Auditoriums A & B. New HVAC duct work, piping and drain lines
are being installed. The layout for the new walls has started.
The rough in electrical work in
the Library Commons is proceeding as conduit and
wiring is being run for additional light fixtures,
switches and outlets. The monitor fur outs in both the small and
large media rooms are finished. The coffee kiosk is being constructed,
network cable is being run and old data and
telephone cable is being removed. The security doors and intercom on the Walk
To Wellness at the Derbigny St. parking lot have been tested
and are operational.
The new steel for the roof at
the Residence Hall 2nd Floor lobby
expansion has been delivered and the installation is
nearing completion. LSUHSC has approved the sample of the
decorative pre-cast concrete that will be used in
the downtown perimeter fencing project and the items
have been put into production. The fencing contractor is installing fence at
Student Lot 2.
Here are highlights of work
that has been accomplished since our last update was
posted two weeks ago.
Lions/LSU Clinic Permanent
Repairs and Mitigation:
- The contractor continues
to install new sheetrock and frame walls on the S. Prieur St. side of the 6th
Floor.
- Sheetrock and
insulation is still being installed on the
new walls on the 7th Floor.
- The chase wall in the
bathrooms on the S.
Prieur side is being framed.
- A crew is installing a
CMU wall by the Electrical Room on the 1st
Floor on the S. Prieur St.
side of the building.
- The contractor is
installing the steel platform for the new
switchgear on the 2nd Floor.
- They are installing a
trap primer on the floor drains under the
platform on the 2nd Floor.
- Thimbles are being
installed to prepare the new deck for
concrete placement on the 2nd
Floor.
- The contractor is
constructing the new circular ceiling
outside of the passenger elevator lobby on
the 6th Floor.
- The contractor is
installing steel sleeves in the elevator
pits and fire caulking.
- The mechanical contractor
is piping in supply and return mains to VAVs on
the 6th Floor on the
Bolivar St./Gravier St.
side of the building.
- Crews are installing
ductwork in the mechanical room on the S. Prieur/Gravier St. side of the 6th
Floor.
- The electrical
sub-contractor is running cable from the main
Entergy vault to the new switchgear location on
the 2nd Floor.
- The electrical
sub-contractor is wiring the new tap box
from the high voltage line in the Entergy
vault on the 1st Floor to the new
switchgear location on the 2nd
Floor.
- They are installing
new electrical panels on the 2nd
Floor in the new electrical room on the CSRB
side of the building.
- Plumbers are routing
medical gas lines to the new simulation rooms.
- Crews are re-routing
the domestic water and waste lines for the
break room area on the 6th Floor.
- Plumbers are also
working on the waste line for the bathrooms
on the S. Prieur St. side that runs between
the 5th and the 6th
Floor.
- The hot water lines on
the 6th Floor are being
insulated.
- The condensate line on
the 6th Floor is being re-routed.
- The new water closets
and urinal carriers are being set in the
bathrooms on the Bolivar St. side of the 6th
Floor.
- The contractor has started
installing new glass on exterior of the 1st
Floor.
- Glass has been
installed along the CSRB side of the
building.
- Glass has been
installed along the
Bolivar St.
side of the building.
- Glass has been
installed along the S. Prieur St.
side of the building.
- New trim pieces are
being installed.
Dental
School
Laboratory Renovations:
- The old wiring has been
removed.
- The contractor continues
installing new electrical rough-ins and has
begun installing the new ductwork.
- The contractor finished
removing the drain lines beneath Room 8405 and
reinstalled the ceiling tiles.
Dental
School
Auditoriums A & B:
- Pipe insulation and old
ductwork was removed.
- The contractor finished
removing the old HVAC heating water lines.
- The block walls
surrounding the AHUs have been removed and crews
are removing the AHUs.
- The electrical
sub-contractor continues to remove the old
electrical and telecommunications wiring.
- The contractor is removing
the support beams for the accordion walls and
the old fresh air ductwork.
- The contractor is laying
out the new walls and the concrete flooring for
the auditoriums.
- The contractor is
installing new HVAC piping and drain lines.
- The lay out of the new
ceiling has started.
- The contractor began
installing new duct work.
- The renovation of
Auditorium A and B includes replacing the air
conditioning units that serve these rooms. In order to facilitate the installation
of these units, the contractor will need to shut
down the chilled water system that provides the
cooling water to both the Administration and
Clinic
Buildings. This will take place on Friday, September
5th from 6:00 PM until approximately
11:30 PM.
During the outage there will be no air
conditioning in any part of either the
Administration
Building or the Clinic Building.
Repair Work at
1542 Tulane Ave.:
- Elevator Repairs:
- Stratos Elevator
finished installing whisper-flex cable and
buffer springs in the pit and they are
currently mounting the hall call stations,
as well as installing the tape leveling
switches and readers for Elevator #4.
- They finished mounting
equipment and tape selector on top of the
cab for Elevator #7.
- The elevator
contractor is pulling wire and hanging
travel cable for Elevator #4.
- They are wiring the
controller for Elevator #7.
- They began work on the
8th Floor doors for Elevator #4.
- Lounge Areas:
- The demolition of the
2nd and 3rd Floor
areas where lounges will be constructed is
complete.
- Zimmer finished
removing the ceiling in the area of the
1st Floor lounge.
- New walls are being
framed for the lounges on the 3rd,
4th, 5th, 6th
and 7th Floors.
- The electrical
sub-contractor installed new electrical
wiring in the lounges on 6th and 7th floors.
- Demolition of Annex
Interior:
- The crews demolishing
the interiors of the 3rd and 4th
Floors of the annex.
- Terrazzo Floors:
- The terrazzo honing of
the 1st Floor is complete.
- The terrazzo honing in
Stairwell D is finished.
- Furniture:
- The furniture vendor
completed setting up and arranging furniture
on the 8th Floor.
- The rooms have
been inspected and locked.
- The Herman Miller
Group finished setting up and arranging
furniture in several rooms on the 7th
Floor.
- Those rooms have
been inspected and locked.
- Misc.:
- The new sidewalk in
front of the building is complete.
- Plumbers capped
disconnected plumbing on the 3rd
and 4th Floor center hallways.
- The work on the
restrooms is complete except for floor
mounted urinals (1st Floor) and
new flush valves (2nd - 4th
Floors).
- Zimmer-Eschette
completed patching walls and painting on the
5th Floor.
- Crews have finishing
installing fan coil units on Floors 4
through 7.
- The insulation
sub-contractor completed work on the fan
coil unit pipes and has begun insulating
the piping in the hallways.
- Plumbers capped most
of the water lines on the 3rd and
4th Floors. Approximately a dozen lines remain to
be capped.
- Zimmer patched the
concrete sub-floors in the lounges on the 4th
through the 7th Floors.
- The painting
contractor started repairing walls and
painting in five rooms on the 6th
and 7th Floors.
- Landscape irrigation
piping is being installed in the front of
the building.
- The lighting
contractor completed installing light
fixtures in Stairwell D and started
installing fixtures in Stairwell C.
Repair Work at the Dental School:
- Permanent Roof Repairs:
- Needham Roofing
continues work on punch-list items and is
applying sealant to the newly installed
umbrellas around the bases of the exhaust
fan supports.
- They are repairing and
patching the roof in areas damaged by the
torches.
- Needham Roofing
repaired the roof on the
Administration
Building penthouse
around the base of new exhaust units.
- Crews completed
replacing roofing sheets near exhaust stacks
# F20 and # F22.
- The contractor
replaced roof material next to the wing
walls.
- They finished
installing roofing around the perimeter of
the penthouse on the Clinic Building.
Walk To Wellness Security:
-
The
Derbigny St. parking lot
security doors and intercom have been tested and are
operational.
Library Commons Project:
- LSUHSC Facility Services
electricians continue work on the electrical
rough-in.
- LSUHSC electricians
ran additional conduit and boxes, began to
layout the exit signs, and continued running
wire for the light switches (switch legs).
- LSUHSC Facility
Services started running conduit and wiring
for light fixtures in the study areas along
the exterior windows.
- Auxiliary Enterprises
continues rerouting network cables to the rear
offices.
- The contractor completed
framing the monitor fur-outs in both the large
and small media rooms.
- They continue framing
the wall behind the interior stairs.
- Crews continue
constructing the new Coffee Kiosk.
- The contractor is removing
old data and telephone cables that have been
replaced by new re-routed cables.
MEB 2nd Floor Lobby Renovation:
- The new sub-floor was
poured.
- A crew is sanding the
joints in the sheetrock walls.
- The painting contractor is
priming the new sheetrock walls.
Residence Hall 2nd
Floor Expansion:
- The newly fabricated steel
has been delivered.
- The installation of the
new steel is well underway.
- The contractor
continues installing the steel supports for
the new roof section.
- The contractor installed
the remaining 4 bar joists and the steel tube
truss above the pedestrian gate.
MEB 4th Floor - MDL
#5 Renovations:
- The HVAC grilles and
return grilles have been installed in the new
ceiling grid.
- The sub-floor has been
built up in preparation for the installation of
VCT tiles.
- The contractor finished
relocating the sprinkler heads in the ceiling.
- The contractor began
laying out the new floor tile pattern.
Downtown Perimeter Fence
Project:
- The sample of the pre-cast
concrete for the decorative fence posts was
approved by LSUHSC and is now in production.
- The contractor is
installing fence at Student Lot 2, on the corner
of Poydras St. and Perdido St.
MEB 4th Floor Ceiling
Replacement:
- The new corridor ceiling
lights were delivered.
- The fur-down ceiling
partitions received a 2nd coat of
paint.
- The new ceiling tile has
been delivered.
- The contractor completed
relocating the sprinkler heads.
- The contractor began
installing perimeter ceiling tiles in the
corridors and installing supply diffusers.
- The contractor continues
installing flex duct and supply grilles in the
corridors.
- The contractor has
installed approximately eighty-five percent of
the light fixtures and the fixtures are being
tested.
- Approximately sixty-five
percent of the ceiling tiles have been
installed.
Building Trash Compactors: All of the existing building trash compactors
were seriously damaged by the post-Katrina flood
waters.
- The new trash compactor
has been installed at the
Dental
School campus.
Hurricane Preparations:
- Crews staged and set
sandbags around switchgear rooms for the CSRB
and the Lions/LSU Clinic Building.
- They inspected and removed
possible missile hazards from the all rooftops.
- Elevator door dams have
been staged near their respective storm
locations.
- A temporary diesel fuel
tank was positioned between the CSRB and the
Lions/LSU Clinic Building and filled with fuel.
- This tank will provide
additional fuel reserves for the emergency
generators.
- All of the sandbags were
set in final locations.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|