From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #77
Posted: September 26, 2008
The last days of August and the
1st week of September were consumed by
concerns and preparations for Hurricane Gustav and
Hurricane Ike. The campus was spared the worst of the
effects of both storms, but the preparations
required that the various contractors working on the
many projects around campus shut down their
operations and evacuate their personnel. In addition, LSUHSC Facility Services
personnel were fully engaged in preparing the
campus.
Consequently, little work was done on the projects
during that period of time. To simplify our summarized reporting, this
update will reflect the progress made over the past
three weeks.
There has been a great deal of
activity on the project to make permanent repairs to
the Lions/LSU Clinic Building. The steel frame of the exterior stairwell is
rising rapidly to its final height. A tremendous amount of mechanical, electrical
and plumbing work is underway on the new
Cohn Learning Center
on the 6th Floor. The work on the construction of the new lab
on the 7th Floor is nearing completion.
Both of the new initiatives at
the Dental School
are progressing well. Rough in mechanical, electrical and plumbing
work has been completed in the lab space in Room
8405 and 8401. Additional demolition has been completed on
the 6th Floor. In the Auditoriums, the exterior walls are
being moisture proofed. Ceiling framing has been completed in
Auditorium B and is nearing completion in Auditorium
A.
Chilled water valves have been installed and the
base for the new AHU is being constructed. The preliminary rough in electrical work for
the ceiling lights in both auditoriums is underway.
The renovations at the Clinical Education Building (1542 Tulane Ave.)
continue on a number of fronts. One of the largest efforts is the repair and
replacement of a large number of the old fan coil
units that provide heat and cooling to significant
parts of the building. The painting contractor continues to paint a
number of interior spaces to make them ready for
use.
Electricians are making the electrical connections
to the system furniture that has been installed in
various places in the building. The construction of the new lounge areas has
been a priority. New walls are being constructed and insulated
and rough in plumbing for the kitchenettes is being
completed. Additional access control devices and closed
circuit televisions are being installed at key entry
points to the building. The interior spaces of Floors 3 and 4 in the
Annex have been demolished.
Work continues on the Library
Commons project. Additional walls have been framed up and dry
walled.
Smoke dampers have been installed in the new duct
work, the vent pipe has been connected, and the
rough in plumbing for the coffee kiosk is complete. The electrical rough in for the lights is
finished and the new ceiling lights for the café and
walkway have been laid out.
The project to replace the
ceiling of the 4th Floor of the MEB is
approaching completion. The majority of the ceiling tiles (including
the edge tiles) have been installed. The contractor framed up the ceiling at the
end of the corridors around the return air grilles. The lay in emergency lights, the supply
ducts, the sprinkler caps, ceiling mounted smoke
detectors, and the exit signed have been installed. In the MEB 2nd Floor lobby, the
new walls and ceiling have been primed and painted. Electrical wiring is being completed in the
Campus Office Stores and Medical Center Stores
spaces.
The network wiring contractor pulled network cable
to the engineering office. The contractor completed building out the
area above the elevator and widened the door opening
for the room between the lecture halls.
The new steel for the expanded
roof of the 2nd Floor Residence Hall
Lobby has been installed and the treated wood
blocking is in place. The 1st and 2nd layers
of self-leveling concrete have been installed on the
floor and the cantilever tops of the walkway are
being removed. Casework and countertops are being installed
in the MDL #5 and the plumbers and electricians are
working behind the cabinet installers to connect
sinks, drains, and electrical outlets. The VCT and ceiling tiles have been installed
throughout.
Here are highlights of work
that has been accomplished during the past three
weeks.
Lions/LSU Clinic Permanent
Repairs and Mitigation:
- The mechanical
subcontractor has run and testing the lines for the
medical gas service to the 6th Floor
simulation rooms.
- Supply duct has been
installed and insulated on the Gravier St. side of the 6th
Floor.
- The heating hot water
lines on the Bolivar St./CSRB side of the 6th
Floor were insulated.
- Waste lines have been
run from the 5th Floor to the new 6th
Floor scrub sinks.
- The sump pumps in the
elevator pit for Elevators #3 and #4 have been piped
in.
- The existing waste
lines that were below the new ceiling height
on the 6th Floor have been
raised.
- The waste lines and
the vents for the water closet carriers and
urinals in the bathrooms on the
Bolivar St.
side of the 6th Floor have been
roughed in.
- The subcontractor is
laying out and installing hangers for new
waste lines on the Gravier St./S. Prieur St.
side of the 6th Floor.
- Their crews are
installing and testing the water lines to
the water closets and the urinals in the
bathroom on the 6th Floor Bolivar
St./CSRB side of the building.
- They are re-routing
heating hot water lines on the 7th
Floor that are in the way of the new supply
duct.
- New supply grills are
being installed on the 7th Floor.
- A crew is piping in
the VAVs on the
Gravier St./S. Prieur St.
side of the 6th Floor.
- Another crew is piping
in the AHU in the 1st Floor
mechanical room on the Gravier St./Bolivar St.
side of the building.
- The supply grills are
being installed on the 7th Floor.
- They are moving acid
waste vents on the 7th Floor.
- Pipe for the new
domestic hot and cold water lines on the
Gravier St. side
of the 6th Floor are being fabricated.
- The sprinkler
subcontractor is relocating sprinkler pipes on
the 7th Floor.
- Glass subcontractor
installed new metal trim pieces that surround the
lower windows on the 1st Floor.
- The electrical
subcontractor tied in conduit for the new transfer
switches on the 2nd Floor in the new
electrical room on the CSRB side of the building.
- They relocated
electrical pipe and electrical boxes to make space
for the new air conditioning system on the 6th
Floor.
- Wire was pulled to
new electrical panel boxes in the new electrical
room on the on the 2nd Floor on the CSRB
side.
- New wire was pulled
to the electrical panels on the S. Preiur St. side of the building.
- Electrical outlets
have been installed in the new lab area on the 7th
Floor.
- They have re-routing
conduit that was in the way of the duct
installation on the Gravier St.
side of the 6th Floor.
- Light fixtures have
been installed on the 7th Floor.
- The electrical
subcontractor is running conduit for the
switches for the Med Gas lines that were run
to the 6th Floor simulation
rooms.
- They are installing
electrical receptacles on the CSRB side of
the 6th Floor.
- A crew is trimming out
the electrical work for the 7th
Floor.
- The emergency lights
are being installed on the 7th Floor.
- The electrical
subcontractor installed a new breaker in
Panel EH2 for the new emergency lights in
the 7th Floor lab.
- The iron subcontractor set anchors for the new stairwell.
- The steel beams for
the first 2 floors of the new stairwell have been
laid out and erected.
- New stairwell beams
were welded to the outside of the building
on the 2nd and 6th
Floors.
- The stair structure was welded to the 2nd Floor.
- The iron subcontractor
welded the new stairs from the 2nd
to the 3rd Floor to the
structure.
- The iron subcontractor
is erecting the steel frame on the
Bolivar St. side
of the stairwell from Floors 4-6.
- The iron workers have
decked the 2nd Floor landing and
they are working on the 3rd Floor
landing.
- Crews are also installing the hand rails.
- The iron subcontractor
is erecting the upper portions of the steel
frame for the exterior stairwell.
- Contractor painted
the new drywall on the 6th Floor on the
CSRB and Gravier sides of the building.
- Crews have taped and
floated the new drywall on the 7th
Floor.
- Crews have taped and
floated the new drywall on 2nd Floor new
switchgear room.
- The floor penetrations on
the 7th Floor have been sealed and
approved by the State Fire Marshall.
- The penetrations on
the 6th Floor are being sealed.
- The contractor hung door
frames on the CSRB side of the 6th
Floor.
- The contractor framed the
bathroom on the 6th Floor located on
the Bolivar St./CSRB side of the building.
- A crew laid out the CMU
walls for the 1st Floor S. Prieur St.
side of the building.
- Crews are removing old
data and telephone wire from the 1st
Floor network closet on the CSRB side of the
building,
- The contractor is placing
concrete on the floor of the new equipment area
on 2nd Floor.
- Ceiling grid is being
installed on the 7th Floor.
- They are prepping the
floors for the new tile on the 7th
Floor.
- Door frames are being hung
on the
S. Prieur St.
side of the 1st Floor.
- The fire sprinkler
subcontractor is moving sprinkler heads on the 7th
Floor.
- The glass subcontractor is
installing glass in the side panels of the door
frames on the 7th Floor.
Dental School Laboratory Renovations:
- The vent lines for the fume hoods in Room 8405 were roughed in.
- The new wall locations and coring locations were laid out in Room 8405.
- Coring has been finished in Room 8405.
- The contractor roughed in
the drain lines for the new lab sinks in Room
8405.
- The mechanical sub
installed pipe hangers and prepared pipe
fittings for the installation of vacuum piping
in Room 8405.
- The mechanical
subcontractor is installing domestic cold water
lines for Room 8401.
- The mechanical
subcontractor is installing pipe sleeves and
connecting vent and drain lines for Room 8401.
- The demolition crew began
removing lab benches and wall panels in Room
6331.
- The old plumbing and
exhaust connections for the fume hood in Room
6331 have been removed.
- The electrical contractor
is installing wiring for the laboratory
casework.
Dental School Auditoriums A & B:
- The support beams for the accordion walls have been removed.
- The duct work and piping in Auditorium B was insulated.
- The framing for the new ceiling in Auditorium B has been completed.
- The framing for the new ceiling in Auditorium A is nearing completion.
- The mechanical subcontractor set up for the chilled water pipe valve installations required for the new AHU.
- The general contractor began removing the elevated flooring in Room 4203.
- The mechanical subcontractor installed the chilled water pipe valves.
- The electrical subcontractor is making preliminary rough-ins for the new lighting in the auditoriums.
- The general contractor finished installing the 1st coat of mastic moisture protection on the exterior walls in Auditorium B.
- They have started installing moisture protection on the exterior walls in Auditorium A.
- The electrical contractor is installing junction boxes and electrical wiring "BX cabling" for the new lighting in the Auditoriums.
- The mechanical contractor is laying out foundation pads for the new air-handling units.
Repair Work at 1542 Tulane Ave.:
- Elevator Repairs:
- Elevator contractor continues work on elevator #4.
- Lighting:
- The lighting contractor installed new light fixtures in the 1st Floor Family Medicine offices.
- The contractor started installing new light fixtures in Conference Room 729.
- Lounge Areas:
- The general contractor completed the demolition in the 1st Floor lounge area.
- Duct work and piping has been insulated.
- The rough in plumbing
for the new kitchenettes in the 6th
and 7th Floor lounges is
complete.
- The general contractor
poured new concrete decks in the lounges on
the 4th, 5th, 6th
and 7th Floors.
- Plumbers completed the
mechanical rough-in for the kitchenettes in
the lounges on the 5th, 6th,
and 7th Floors.
- The general contractor
is constructing the walls in the lounges on
the 4th and 7th
Floors.
- Sprinkler piping has
been installed in the 5th Floor
lounge.
- Drywall is being hung in the lounge on the 7th Floor.
- Demolition of Annex Interior:
- The demolition of the
interiors of the 3rd and 4th
Floor annex spaces has been completed.
- Furniture:
- The furniture vendor
delivered new furniture for the University
Police office on the 1st Floor.
- The furniture vendor
surveyed all the offices on the 5th
through the 8th Floors and
identified remaining rooms requiring final
furniture arrangement.
- LSUHSC Facility
Services electricians installed power feed
cables for the new systems furniture that
has been installed on the 6th and
7th Floors.
- Facility Services
electricians installed power feed cables
for the systems furniture in Rooms 536,
613, 658 and 723.
- Security:
- The security system
contractor installed the card reader for the
front door access control.
- A number of new
cameras have been installed at several
locations.
- The security
contractor completed installation of access
control for the front doors and the side
doors closest to the District Energy garage.
- Misc.:
- The contractor built
formwork for the concrete lids on the area ways.
- New Orleans Sewerage
and Water Board contractor repaired sidewalk in the
area of the new irrigation meter.
- The contractor
installed support bracing for ceiling lights
in the rear elevator lobbies on 5th,
6th and 7th floors.
- The contractor
repaired holes in plaster ceilings of
several offices on the 5th, 6th
and 7th Floors.
- The painting
contractor continues painting stairwell and
hallway ceilings, and restrooms throughout
the building.
- They painted the
University Police office on the 1st
Floor.
- ORM insurance
adjusters toured the building to document
Hurricane Gustav damage.
- Electronics
technicians wired the parking gate
controller for the parking garage.
- The building supplies
have been removed from the 1st
Floor auditorium where they had been staged.
- LSUHSC Facility
Services personnel continued installing new
fan coil units throughout the building.
- Repairs to the ceiling
in Room 718 have begun.
- The flooring
contractor is installing and repairing
carpet in rooms on the 8th Floor.
- They are installing floor tile in the stairwell.
Repair Work at the Dental School:
- Permanent Roof Repairs:
- Needham Roofing
repaired the roof at the wing walls of the
Clinic Building and waterproofed the
perimeter of the
Clinic Building roof.
- They repaired the roof
decking on the elevator penthouse of the Administration
Building.
- A 10ft x 10ft
section of roof decking, insulation,
mineral board, and roof cap sheets were
removed.
- The Contractor
installed sheet metal and concrete to
repair the deck and re-installed the
insulation, mineral board and cap
sheets.
- The contractor
installed walk pads on the
Clinic Building roof.
- Needham Roofing began
installing walk pads on the roof of the Administration
Building.
Library Commons Project:
- Smoke dampers have been installed in the new duct work.
- The plywood backer board has been installed in the media room.
- The rough in plumbing for the coffee kiosk has been completed.
- The drywall ceiling above the coffee kiosk has been framed in.
- LSUHSC Facilities Services completed the rough in electrical work for the new lights.
- The contractor framed the knee wall nearest to stairwell.
- The vent piping is complete.
- A crew framed up the wall nearest to the freight elevator.
- The contractor installed cementitious board on the frieze wall.
- The contractor finished the sheetrock edge of the window wall.
- Light fixtures have been laid out in the cafe and hallway.
MEB 2nd Floor Lobby Renovation:
- The new drywall has been primed and painted.
- The ceiling has been painted.
- The electrical subcontractor ran wire for electrical outlets in the new walls for Medical Center Stores and Campus Office Stores.
- The network wiring contractor pulled network cable to the engineering office.
- The contractor completed building out the area above the elevator and widened the door opening for the room between the lecture halls.
Residence Hall 2nd Floor Expansion:
- The steel supports for the new roof have been installed.
- The contractor removed the
temporary ramps between Tower A and Tower B
elevators and removed the bricks at all door
entrances to make a clean transition for the new floor.
- The flooring sub finished
the first layer of self-leveling concrete in the
area from the S. Roman St.
side of the building toward the Tower B
elevator.
- The flooring subcontractor
placed a second layer of mortar concrete from
the S. Roman St. side of the building
toward the Tower B elevator.
- They are removing both cantilever tops attached to the elevated walkway.
- The contractor completed
installation of the treated wood blocking on the
roof of the new enclosure and completed removing
the canopy structure on walkway.
MEB 4th Floor - MDL #5 Renovations:
- The contactor
completed installing VCT tiles in the main MDL room
and in Rooms 4106A, 4109, 4122A, and 4123A.
- Ceiling tiles were
installed in the main MDL room and Rooms 4106A,
4109, 4122A, and 4123A.
- The new casework and
countertops are being installed and the plumbers
and electricians are following behind and
installing the rough in plumbing and electrical
connections.
- New LCD panel displays have been installed.
- The medical air, gas, and vacuum lines have been reinstalled.
- The contractor completed
installing new partition panels, including the
new door and frame in Room 4123A.
- The contractor is
installing wall mounted chase for the electrical
and AV service for each quadrant.
- The casework contractor
began installing the new sink cabinets in the
main MDL room.
- The casework contractor is installing pedestal frames in the main MDL room.
- The casework subcontractor is installing frames and shelves in Room 4109.
- The network wiring
contractor began routing and terminating data
cable in the main MDL lab.
Downtown Perimeter Fence Project:
- The contractor removed the barbed wire from the 440 Perdido Street lot and Student Lot #1.
MEB 4th Floor Ceiling Replacement:
- The contractor replaced lay-in emergency lights and installed sprinkler head caps.
- The supply grills have been installed in the ceiling.
- The installation of the edge tiles is substantially complete.
- The ceiling mounted fire speakers have been installed.
- The exit signs have been installed.
- The contractor framed up the ceiling at the end of the corridors around the return air grilles.
- The contractor is repairing damage ceramic tiles near the ceiling grid.
Downtown Landscaping Project:
- Landscaping
contractor replanted storm damaged trees and
reinstalled support cables.
- Support cables were
tighten and/or replaced on other trees throughout
the campus.
- The layout and
preparations for the irrigation piping and
landscaping along the front of 1542 Tulane Avenue
were completed.
- The irrigation piping is being installed.
Residence Hall Walkway Resurfacing:
- The contractor applied the
first and second of the three underlayment
layers of concrete planned for the walkway.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|