From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #82
Posted: December 5, 2008
The initial re-occupation
of the Clinical Education Building, 1542 Tulane Ave.
began, as scheduled. Three clinical departments of
the School of Medicine; Surgery, Neurology, and
Pathology are moving into the upper floors of the
building. The faculty and staff have unpacked and
are operating out of their new offices. The second
phase of the move in is planned for mid-December. We
have additional moves scheduled on December 9th and
15th that will include OB/GYN, Urology, Orthopedics,
Dermatology and Anesthesiology.
Four passenger elevators
and the freight elevator were in operation when the
move began. Access control was activated on all the
exterior entrances to the building. Repairs and the
work on the new lounge areas continued on the lower
floors. New lighting is being installed in
conference rooms, hallways, and lounges. Additional
exterior security lighting has been added to the
rear of the building. Carpet and floor tile is being
laid in lounges. Additional furniture and cabinetry
has been installed in conference rooms and lounge
areas. A variety of other repair work continues
throughout the building.
We are pleased with the
progress being made in renovating Auditoriums A and
B at the Dental School. The walls in Auditorium A
have been primed and the electricians installed
wiring for the riser seating and wall sconce
lighting. The concrete was poured and finished for
the stairs in Auditorium B. The new walls and
ceiling have been taped, floated and primed. The
wall scones have been installed on three walls in
Auditorium B. The connections to the new air
handling units that will serve both rooms are being
completed. The electricians have been working on the
6th and 8th Floors of the Clinic Building as work
continues on the lab renovations. Conduit is being
run and wiring has been pulled to junction boxes.
A major milestone in the
project to complete permanent repairs and mitigation
at the Lions/LSU Clinic is about to be reached.
Preparations have been completed to allow the new
switch gear located on the 2nd Floor to be put into
operation. This step insures that a future flood
event would not damage the switch gear which
distributes power to the entire building. The
mechanical contractor has also been working to
prepare critical mechanical equipment that has been
elevated to the 2nd Floor to be put into service.
Building power is scheduled to be switched over to
the new switch gear over the coming weekend.
A great deal of work
continues on the 1st and 6th Floors of the Lions/LSU
Clinic Building. Significant portions of the
demolition of the lab on the 6th Floor have been
completed by both the mechanical and electrical
sub-contractors, now that the lab functions have
been moved to the 7th Floor. Chilled water, heating
hot water and supply lines have been insulated on
the 1st Floor. Crews have been applying plaster to
CMU walls on the 1st Floor and wall tile is being
installed. Conduit has been installed and wire
pulled for the roll up fire protection doors on the
6th Floor. Dimmer switches have been installed and
wire for the new fire alarms has been pulled. The
fire proofing sub has been priming and painting key
areas of the exterior stairwell. Sprinkler stand
pipes are being installed.
The contractor working on
the Library Commons project has laid floor tile and
grouted it in the cafe area, by the coffee kiosk and
in front of the passenger elevators. The renovations
to the lab located in MEB 6109 & 6148 are rapidly
nearing completion. New floor tile has been laid and
the plumbing connections to the sinks have been
made. The walls are being touched up to address
minor damage.
The demolition in MDL 6
located on the 4th Floor of the MEB is well
underway. The ceiling tiles, ceiling grid and the
ceiling mounted light fixtures have been removed
from the main room and from one of the adjacent
spaces. Plumbing and electrical wiring has been
disconnected and made safe to allow the demolition
and removal of case work and equipment. Equipment
has been removed from the lab. Approximately half of
the old flooring has been taken up. On the 2nd Floor
of the MEB, the sprinkler sub-contractor has
installed new sprinkler piping in the lobby.
The project to expand the
lobby of the Residence hall is continuing to more
ahead. The rough in electrical work between Towers A
and B continued over the past two weeks. The old
duct work has been capped and access holes have been
cut in the duct work for the slit diffusers. The
frame work for the new store front is under
construction. Framing for the new sliding door is
nearing completion.
Here are highlights of
work that has been accomplished during the past two
weeks.
Repair Work at 1542 Tulane
Ave.:
- The initial re-occupation of the building
has begun.
- Materials from the Departments of
Surgery, Neurology and Pathology have been
moved into the upper floors of the building.
- Faculty and staff have been unpacking
and organizing their offices.
- Four passenger elevators and the freight
are in service.
- Business managers were given move in
check lists to assist in capturing and
reporting any problems that they may
discover. A staff person from the Office of
the Dean will accumulate the check lists and
deliver them to LSUHSC Facilities.
- Lighting:
- The electrical contractor continued
installing new light fixtures in the
conference rooms on the 2nd and 3rd Floors.
- They removed old light fixtures from
Conference Room 639.
- Lounge Areas:
- The flooring contractor installed floor
tile in the kitchenettes in the 7th Floor
lounge.
- Crews installed VCT and carpet in
the 5th Floor lounge and cove base in
the 6th Floor lounge.
- The furniture vendor completed
installing cabinets and setting up chairs
and tables in the lounge on the 7th Floor.
- They installed cabinets in the 6th
Floor lounge.
- LSUHSC Facility Services installed the
sink, refrigerator and ice maker in the 7th
Floor lounge.
- The electrical contractor continued
installing new light fixtures in the lounges
on the 2nd and 3rd Floors.
- The furniture vendor set lounge
furniture on the 6th Floor.
- Furniture:
- The furniture vendor set conference room
furniture on the 6th Floor.
- Misc.:
- The network wiring contractor completed
installing and testing the new data drops on
the 6th Floor.
- They completed wiring new drops on
the 5th Floor.
- The access control was activated for all
doors.
- The electrical contractor roughed-in
electrical conduit and boxes for Room 545.
- The general contractor installed ceiling
tiles in the 6th Floor lounge.
- The general contractor installed drywall
in Room 545.
- They are taping and floating the new
drywall.
- The painting contractor is painting the
front stairwell on the Charity end of the
hall.
- Facility Services installed four new
exterior lights at the back of the building
along the sidewalk leading to the Walk to
Wellness.
- Electricians ran new conduit for
additional exterior lighting that will
be installed at the rear of the
building.
- Facility Services sealed old exhaust
duct wall penetrations on the exterior walls
facing the Lakeside Lot and continued making
minor repairs on various floors.
Dental School Auditoriums
A & B:
- Auditorium A.
- The general contractor finished priming
the walls in Auditorium A.
- The electrical contractor installed
wiring for the riser seating and wall
sconces in Auditorium A.
- The mechanical contractor completed the
drain lines to both AHUs and installed
registers in Auditorium A.
- The heating water return line for the
AHU serving Auditorium A was installed.
- Auditorium B.
- The contractor framed the stairs for
Auditorium B.
- They poured and finished the
concrete for the stairs.
- The general contractor floated and
sanded the sheetrock ceiling and walls.
- The electrical contractor installed wall
sconces on the east, south and west walls of
the Auditorium.
- The mechanical contractor installed the
drain line to the AHU for Auditorium B.
- The heating water return line for the
AHU serving Auditorium B was installed.
- The contractor primed the new walls in
the Auditorium.
- The mechanical contractor connected chilled
water supply and return lines to the new AHUs.
- They installed piping for the heating
hot water supply and return lines connected
to the new AHUs.
- The contractor installed the CMU wall for
the electrical room.
Dental School 6th
and 8th Floor Lab Renovations:
- The electrical contractor installed conduit
for the data outlets in Room 6335.
- They connected wiring for the junction
boxes above the ceiling in Suite 8405.
- The general contractor applied mastic to the
exterior wall in Room 6335.
Library Commons Project:
- The flooring contractor installed and
grouted the tile in the cafe area.
- The flooring contractor installed floor tile
in the area of the coffee kiosk.
- The contractor installed and grouted the
floor tile in half of the elevator.
Lions/LSU Clinic Permanent
Repairs and Mitigation:
- A building-wide power outage at the
Lions/LSU Clinics Building has been scheduled
for Sunday, December 7th, 2008 from 7:00 AM to
7:00 PM. During this outage there will only be
emergency power to maintain emergency lights and
service to some specific equipment in the
building – these items are plugged into the red
receptacles. The regular receptacles, elevators,
lights, air conditioning and heating, exhaust,
and all pumps will be off in all sections of the
building as the electrical power from Entergy is
shut down to allow installation of power for the
new equipment in the building.
- The mechanical subcontractor insulated chill
water lines, heating hot water lines, and supply
lines on the east side of the 1st Floor.
- They installed roof drains on the
exterior stairwell tower.
- Crews notched the fire door duct on the
north side of the 5th Floor.
- They installed exhaust fans and curbs on
the roof of the stairwell tower.
- Angle stops for the plumbing fixtures in
the rest rooms and the scrub sinks on the
6th Floor were installed.
- They installed additional pipe for the
medical air system on the 2nd Floor.
- The medical air and vacuum lines running
to the lab on the east side of the 6th Floor
were capped.
- Plumbers shut off the domestic hot and
cold water lines supplying the same lab.
- They set and trimmed out plumbing
fixtures in the rest rooms on the east side
of the 6th Floor.
- They insulated fire dampers on the 6th
Floor.
- Crews demolished duct work and water
pipes in the 6th Floor lab.
- The mechanical subcontractor installed
thermostats on the 6th Floor.
- The controls for the AHU on the east
side of the 6th Floor were disconnected.
- The waste lines in the ceiling of the
north side of the 5th Floor were capped.
- They demolished glass pipe on the 2nd
Floor that is in the way of the new
electrical work.
- The mechanical subcontractor installed
new acid waste lines in the 6th Floor
ceiling for the 7th Floor lab.
- A crew demolished ductwork and old storm
drains in the 6th Floor lab.
- The electrical subcontractor grounded
service entrance cable on the west side of the
1st Floor.
- Electricians crimped and terminated 32
feeders to allow for termination to the new
switchgear on the 2nd Floor.
- The electrical subcontractor mounted
current and potential transformers for
Entergy monitoring in the switchgear on the
2nd Floor.
- They ran conduit to Panel 2AC and the
switchgear on the 2nd Floor and grounded the
new switchgear.
- Conduit for the riser to the switchgear
on the 2nd Floor was run.
- They ran conduit to ATS 1 and 2 from the
2nd Floor to the new switchgear and
installed conduit for the lights and exhaust
fans in the stairwell.
- They cleaned the buss duct for the 2nd
Floor switchgear and tested the line side of
the new switchgear in preparation for the
Entergy feed.
- They installed wire for the fire alarm
devices on the south side of the 6th Floor.
- Wire to provide power to the roll up
fire doors on the 5th and 6th Floor was
pulled.
- They installed dimmer switches on the
south side of the 6th Floor.
- Electricians disconnected the electrical
lines outside of the lab on the 6th Floor.
- They demolished Panels HA6A and LA6A on
the 6th Floor.
- They also installed conduit for switches
and receptacles on the CSRB side of the 2nd
Floor.
- The fireproofing subcontractor primed the
saddles on the 1st – 6th Floors of the exterior
stairwell tower.
- Crews primed all welds (treads and
handrails) on the exterior stairwell tower.
- They painted the main structure beams on
the 6th Floor of the new stairwell.
- The contractor taped and floated the fur
downs and monitor recesses on the 6th Floor,
north side.
- Crews framed windows on the northwest
side of the 6th Floor.
- Carpenters constructed new walls on the
2nd Floor and installed CMU on the 1st
Floor, west side.
- The contractor taped and floated the
walls in the 6th Floor simulation rooms.
- Crews installed doors by the simulation
rooms on the 6th Floor.
- They installed fire walls on the 2nd
Floor by the stair tower, north side.
- Crews installed metal studs and
sheetrock for the fur down on the S.
Prieur/Gravier St. side of the 6th Floor.
- They also installed metal studs and
sheetrock on the 2nd Floor and metal lathe
on the 1st Floor.
- The CMU wall on the 1st Floor is being
plastered.
- Wall tile is being installed in the
restrooms on the 1st Floor.
- They pressure washed the new stairwell.
- The steel subcontractor fastened landing
supports on Floors 1 through 5 of the exterior
stairwell.
- The sprinkler subcontractor installed stand
pipe in the stairwell sprinklers.
MEB MDL 6 RENOVATIONS:
- The project to renovate Multidisciplinary
Lab 6 has gotten underway. The renovations to
this lab will follow the model established in
the renovation of MDL #5.
- The contractor removed existing ceiling
tiles, equipment, and disconnected electrical
and plumbing for demolition.
- Ceiling grid, existing casework, and
lighting fixtures have been removed from the
main MDL room.
- Approximately half of the old floor has been
removed.
- The old blackboards have been removed from
the main MDL room.
- The contractor removed ceiling grids and
ceiling tiles in Room 4121A.
MEB 2nd Floor Lobby
Renovation:
- The sprinkler subcontractor installed
sprinkler pipe on the east and west side of the
lobby.
Residence Hall 2nd Floor
Expansion:
- The contractor capped existing supply HVAC
duct between Tower A & B and near the corner of
Perdido & Bolivar Sts.
- They created new supply holes on existing
duct for slot diffusers between Tower A and B.
- The vertical storefront frame for the
expansion lobby was erected.
- The existing glass was removed from the old
storefront system.
- The contractor installed the horizontal
frame at the double sliding door for the
external enclosure.
- They installed four vertical mullions and
the horizontal mullion for the single sliding
door (Bolivar & Perdido corner).
- The contractor continued the electrical
rough in (running conduits and junction boxes
for light fixtures) between Tower A and B.
MEB 6109 & 6148 LAB
RENOVATIONS: This is a new project that will
renovate a research lab at the MEB. Included in the
scope of work are new ceilings, flooring, and lab
countertops.
- The contractor installed new VCT tiles
flooring.
- The contractor patched and touched up walls
in both rooms.
- The contractor capped all plumbing and
reconnected all plumbing for sinks in both
rooms.
- The project is nearing completion.
We encourage you to follow the
details of our progress through the daily updates
which are posted on the web site.
|