|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #90
Posted: April 10, 2009
Two weeks ago we reported on the
results of a March 17, 2009 meeting with Mr. Charlie
Axton (appointed by Secretary Napolitano to head up
an independent "decision team") and representatives
of GOHSEP regarding our hazard mitigation proposals
that were deemed ineligible by FEMA late in 2008.
The Unified Public Assistance Project Decision Team
decided the issues that we raised in the meeting in
our favor.
Since that time, we have had
discussions with representatives of both GOHSEP and
the FEMA Health and Research team about the path
forward. The FEMA Health and Research team has
already begun to work on re-packaging our more
straight forward proposals and preparing them to be
submitted to FEMA for review under the new
guidelines and principles set forth in the decision
document. We would anticipate that the proposals for
the Resource Center and the Residence Hall will be
prepared in a short period of time. The bid
documents for both projects are nearly complete so
that when FEMA approves and obligates funds, the
projects can be bid immediately.
Current plans for the Allied
Health/Nursing Building now include additional work
that will provide critical lecture room space on the
2nd Floor and use 1st Floor space to provide for the
office space that will be displaced from the 2nd
Floor. This additional work will require some
additional review by both FEMA and GOHSEP. The bid
documents for this project are also nearing
completion.
The combined project to address the
permanent repairs and mitigation for the MEB and the
CSRB includes a sizable addition to the rear of the
CSRB that will elevate critical animal care spaces
from both buildings and provide emergency generator
power that will help to protect the surrounding
downtown campus buildings. Significant permanent
repairs are also incorporated into the proposal. The
resulting complexity of this project is expected to
prompt addition requests for information from FEMA
as the proposal is prepared for re-submission. The
architects anticipate having the Construction
Documents prepared by the end of May for this
project.
The Dental School campus is
similarly complex. The proposal addresses permanent
repairs to the Clinic Building, the Administration
Building and the Power Plant. It also proposes an
annex to the Clinic Building that will house
critical functions and building equipment that had
been housed in the shared basement spaces of both
buildings and the 1st Floor of the Clinic Building.
Similar to the downtown campus concept for the CSRB,
the annex will also house additional emergency
generation capacity that will provide for non-life
safety needs; protecting research animals, research
samples, etc. The Design/Development documents are
being worked on by the joint venture at this time.
When they are prepared, they will form the basis of
the formal proposal to FEMA.
We also expect to have the
Design/Development documents for the Central Utility
Plant and the Roman St. Garage available by early in
May. Once these documents have been reviewed and
approved by LSUHSC and the Office of Facility
Planning and Control, they will be formally
transmitted to FEMA and GOHSEP for approval. These
reviews typically consume about 30 days.
We remain cautiously optimistic that
the new leadership at the FEMA Temporary Recovery
Office and the decisions of Mr. Axton’s team will
allow our proposals to move through the FEMA review
queues without any undue resistance. However, we
will remain in touch with senior FEMA and GOHSEP
leadership and seek their assistance should any
unexpected problems arise.
Work is continuing at 1542 Tulane
Ave. with the intention of moving additional faculty
and staff onto the 3rd and 4th Floors within the
next month. Painting and miscellaneous electrical
repairs are being finished and some additional
carpeting has been laid. New fan coil units are
being wired and three new offices are being
constructed along the Tulane Ave. side of the
building. Other crews are being shifted to the 1st
and 2nd Floors where work on the lounges is
progressing. The 2nd Floor lounge has been dry
walled and painted. The ceiling grid is in place and
ceiling tiles are being installed. The plumbers are
roughing in the plumbing in the 1st Floor lounge.
The duct work has been installed and insulated. The
attached parking garage has been cleaned and
striped. A new high speed roll up door has been
installed and should be fully operational soon.
The formal proposal to make
permanent repairs to the Clinical Education Building
and to elevate critical building components into an
addition to the building has been reviewed and
approved by the State and FEMA historical groups.
They have approved the plan, but required that the
exterior of the addition be clad in concrete panels
that will better match the exterior of the existing
structure. The historic review was the final review
required by FEMA locally and we anticipate that
proposal will move to the Million Dollar queue in
Washington, DC for the final approval.
The Library Commons project is
nearing completion. Work on the display cases is
substantially complete. The electrical receptacles
and network connections are complete, shelving has
been installed, and the metal base trim material is
in place around the cabinet bases. The wall
coverings have been hung in the small and large
multimedia rooms and along the window wall.
Additional light fixtures are in place and the wood
trim has been applied to the wood covered columns.
The contractor at the Lions/LSU
Clinic Building continues his push to complete work
on the 6th Floor so that we can have constructive
occupancy of the Learning Center within the next few
weeks. Stryker and the electrical contractor are
nearing completion of the installation of the
Stryker equipment in the simulation labs and of the
related audio/visual equipment. Flooring materials
and ceiling tiles continue to be installed
throughout the floor. Finish work is being completed
in the conference rooms. Most of the granite facing
has been placed on the exterior of the new
stairwell. The 1st and 6th Floor glass doors from
the building to the stairwell are in place. The
flood proofing of the freight elevator is
progressing.
Another project that is approaching
completion is the renovations to the MEB
Pharmacology lab. The concrete subfloor was leveled
in both the lab and administrative area and floor
tiles are being installed. The peninsular casework
and countertops have been installed. Ceiling lights
are in place in both the lab and the administrative
areas. Fume hoods have been put in place and are
being connected. The vinyl wall covering was applied
in the animal care room and door frames installed in
both the lab and administrative areas.
Work continues in the 2nd Floor
lobby of the MEB. Storefront windows have been
installed at the Campus Stores location. Additional
dry wall has been hung, taped and floated. The
soffit across from the elevators was framed up and
dry walled.
The focus of the work at the Dental
School Auditoriums has shifted to the preparations
for the state of the art audio/visual equipment. The
electricians have run additional overhead conduit in
both Auditoriums to handle the wiring and controls
for the projectors, speakers, computers, and the
podiums. The new IT closet has been framed up. The
State Fire Marshall inspected and passed the fire
alarm system in the 6th and 8th Floor Dental School
labs that have been renovated.
The mechanical contractor installed
plenum boxes along the storefront wall in the
extended lobby area of the Residence Hall. Sprinkler
pipes have been raised and sprinkler heads
relocated. The fur down in the expanded lobby area
has been framed up and the sheet rock is being hung,
taped and floated. The contractor roughed in for the
fire alarm devices and the old network closet was
demolished.
The roof replacement at the Allied
Health/Nursing Building has experienced a few
additional weather delays due to rain and/or high
winds. However, the crews have made excellent
progress in removing the old roofing material and
installing the temporary two-ply roof which keeps
the roof water tight during the process. They are
generally working in 30 foot wide strips and several
strips have been completed during the past two
weeks.
The re-roofing project at the
Resource Center is being re-bid, after technical
deficiencies caused all of the original bids to be
rejected. The pre-bid conference was held on April
8th and the architects reported significant interest
from several contractors. The bids will be opened on
April 21st.
Here are highlights of work that has
been accomplished during the past two weeks.
Repair Work at 1542 Tulane Ave.:
- The general contractor completed installing
doors in Room 111B.
- A crew is floating and sanding the new
drywall in the 2nd Floor lounge.
- They are making wall repairs in Rooms
235K and 235M.
- Workers are framing up new walls in
Rooms 341, 342 and 343.
- Painting:
- Workers completed painting in Rooms 235K
and 235M.
- Lounge Areas:
- A crew continued taping, floating and
sanding the drywall in the 2nd Floor lounge.
- The mechanical contractor installed the
new ductwork in the 1st Floor lounge.
- The insulation contractor insulated the
new ductwork in the 1st Floor lounge.
- Workers painted the 2nd Floor lounge.
- The ceiling grid has been installed in
the 2nd Floor lounge.
- Workers are installing ceiling tiles in
the 2nd Floor lounge.
- The mechanical contractor started
installing plumbing in the 1st Floor lounge.
- The mechanical contractor installed new fan
coil units in Rooms 345 and 345A.
- Workers installed drain lines on the new
fan coil units in Rooms 345, 343 and 342.
- The electrical sub-contractor continued
wiring fan coil units on the 3rd Floor.
- Misc.:
- The furniture vendor delivered new
furniture to the 4th Floor storage area.
- The roll-up door contractor installed
the new roll-up door door at the entrance to
the parking garage.
- The door contractor installed new
loading dock doors on the Lakeside Lot
service entrance.
- The network wiring contractor installed
new data drops on the 3rd Floor.
- The access control contractor began
installing door contacts on the emergency
exit doors on the Charity side of the 1st
Floor hallway.
- The flooring contractor installed carpet
in offices on the 2nd and 3rd Floors.
LIONS/LSU CLINIC PERMANENT REPAIRS
AND MITIGATION:
- The contractor removed existing
waterproofing sealer and applied the completed
the new waterproofing in the freight elevator
pit.
- They laminated the reception desk
countertop.
- Workers installed the metal soffit under
the main entrance.
- Metal lathe for the stairwell
overhang has been installed.
- Crews installed granite on the 5th and
6th levels of the new stairwell.
- Crews installed granite on the front
edge of the sidewalk around the stair
tower.
- The granite cap was installed at the
top of the new stairwell.
- Workers applied the 1st layer of
stucco under the canopy of the exterior
stairwell.
- Crews installed break metal interior
trim for the windows of the new
stairwell on the 1st level.
- The contractor patched and placed floor
tile in the rear of the building and
installed tile around the computer lounge.
- Workers installed VCT in the 6th
Floor elevator lobby, adjacent storage
room and housekeeping closet.
- The contractor grouted floor tile in
the computer lounge.
- Cove base was installed around the
6th Floor reception desk.
- The contractor installed VCT in the
2nd Floor entry way to the new build
out.
- A crew plastered the soffit in the
computer lounge.
- Crews installed new countertops in
the computer lounge.
- The contractor installed wall
covering in the 6th Floor computer
lounge.
- Ceiling tiles were installed in the 1st
Floor elevator lobby.
- Crews installed ceiling grid on the
6th Floor, Gravier/S. Prieur Street
side.
- Crews installed windows on the 5th Floor
of the exterior stairwell.
- Crews installed trim at the header of
marker boards in Rooms 671,673, 675,
676,677, 678, 681, 682, and 683.
- Workers installed cove base on the
Gravier St. side of the 6th Floor.
- Workers painted on the 1st Floor near
the freight elevator and installed the stair
door on the 1st Floor near the passenger
elevator.
- Crews continued painting on the 1st
Floor, S. Prieur/CSRB side.
- They installed the stairwell glass doors
on the 1st and 6th Floors.
- The electrical contractor began installing
lights in the 1st Floor stairwell.
- Electricians connected electrical wire
to the Stryker equipment.
- Crews installed wire mold on the 6th
Floor.
- The old feeder cable has been removed
from the switchgear room.
- The electrical contractor roughed in for
new exit lights on the 5th Floor, Gravier
Street side.
- They installed lights and receptacles on
the S. Prieur St. and Gravier St. sides of
the 1st Floor.
- Electricians installed ceiling lights on
the 6th Floor and stairwell lights on the
1st and 2nd Floors.
- They installed wire for the sump pump
for the elevator on the 1st Floor, Bolivar
Street side.
- The mechanical contractor installed a sink
in the 6th Floor break room.
- Workers connected Stryker equipment to
the medical air/gas/vacuum lines in the 6th
Floor simulation rooms.
- They installed a storm drain grate on
the stairwell roof and installed copper
lines to chilled water valves on the 1st
Floor.
- Stryker continued to install wires and
equipment on the 6th Floor.
- Stryker continues to install their A/V
equipment in the simulation rooms.
- Stryker installed speakers in the large
lecture room and installed routers in the
network closet on the 6th Floor.
- Stryker tested the medical equipment
system.
- AT&T continues to install the new telephone
feeder.
- AT&T is installing wires in the new room
on the 2nd Floor to allow for the transfer
of the phone line connections from the 1st
Floor to the 2nd Floor.
LIBRARY COMMONS PROJECT:
- The contractor installed metal base around
the display cases.
- They installed network cabling in the
display cases.
- Facilities Services electricians
completing the installation of the display
case receptacles.
- The contractor completed work on the
custom furniture and display cases.
- The contractor installed trim on the wood
covered columns.
- Facilities Services electricians installed
light switches in the multimedia rooms.
- The contractor installed wall covering in
the large and small multimedia rooms.
- Workers installed wall covering along
the window wall and in the restrooms.
- LSUHSC Facility Services electricians
installed egg lights and receptacles in the
multimedia rooms.
- LSUHSC Facility Services electricians
installed new exit signs.
- The fire alarm devices are being installed.
MEB PHARMACOLOGY LAB RENOVATIONS:
- The contractor installed ceramic tile around
the opening of Room 5220.
- Ceramic tile was installed around the
door openings in the administrative area.
- Workers floated the floors in the lab
and administrative areas.
- VCT was installed on the floor in the
administrative area being converted to lab
space.
- A crew installed black tile around the
doorways in the administrative area.
- The light fixtures in the lab and
administrative areas have been installed.
- Workers installed fireproofing at all the
core drill locations.
- Workers installed the peninsular casework in
Room 5219, 5219A and 5262.
- The casework contractor installed
countertops in Rooms 5219, 5219A and 5262.
- The contractor replaced the four fume hoods.
- The mechanical contractor started
connecting the fume hoods.
- The contractor installed four door frames in
the administrative area.
- Door frames were installed in the lab
area.
- The contractor installed vinyl wall covering
for the animal care room.
- The contractor heat welded the vinyl
wall covering for the animal care room.
MEB 2nd FLOOR LOBBY RENOVATIONS:
- The contractor taped, floated and sanded the
new exteriors of the storefront walls.
- The storefront windows for the Campus Stores
location were installed.
- Workers installed sheetrock near the granite
columns.
- The contractor framed and the soffit across
from the elevator and hung the sheetrock.
- The contractor re-installed the window
frames for the store fronts.
DENTAL AUDITORIUMS A & B
RENOVATIONS:
- The electrical contractor ran the conduit
for the multi-media equipment in Auditorium B.
- They installed the overhead conduit for the
podium and the A/V connections in Auditoriums A
& B.
- Electricians installed additional overhead
conduit for the podium, speaker, and projector
connections in Auditorium B, extending the
conduit into the lobby area.
- The electrical contractor installed Unistrut
in the elevator lobby for the additional
overhead conduit.
- The contractor framed the raised stage area
underneath Auditorium C (for the IT closet).
DENTAL 6th & 8th FLOOR LAB
RENOVATIONS:
- The architect held the inspection by the
State Fire Marshall.
- Both the 6th & 8th Floor fire alarms
passed inspection.
RESIDENCE HALL LOBBY EXPANSION:
- The mechanical contractor installed plenum
boxes along the storefront wall in the extended
lobby area.
- The mechanical contractor raised the
sprinkler pipes in the expanded lobby area.
- The contractor patched and skin coated the
plaster walls by the B and C Tower elevators.
- Crews roughed in the fire alarm devices in
the expanded lobby area.
- The interior contractor framed the fur down
in the mezzanine level between the B & C Towers.
- They installed sheetrock, taped and
floated the fur down in the mezzanine level
between the B & C Towers.
- The contractor framed up the fur down in the
expanded lobby area.
- They are installing sheetrock and taped
and floated the fur down in the expanded
lobby area.
- The contractor relocated fire sprinkler
heads between A and B Tower.
- The old network closet was demolished.
ALLIED HEALTH/NURSING ROOF
REPLACEMENT:
- The contractor removed a 30 foot section of
the old light weight concrete and Styrofoam
insulation along the Bolivar Street side of the
roof.
- They installed a two-ply temporary
roofing system that will keep the building
watertight.
- The contractor removed another 30 ft section
of the roof parallel to Bolivar Street and
applied the two-ply roof.
- The contractor removed another 30 ft section
of the roof parallel to Bolivar Street and
applied the two-ply temporary roof.
- The contractor is now past the elevator
penthouse.
- The contractor removed the roof section
parallel to Gravier St around the elevator
penthouse and applied the two-ply temporary
roof.
- The contractor removed a 30-foot roof
section of the old roof parallel to Roman St. at
the MEB side of the elevator penthouse and
applied the two-ply temporary roof.
EXTERIOR/LANDSCAPING:
- LSUHSC Facility Services completed
installation of the irrigation piping in the
rear of the Resource Center along S. Prieur.
- Workers graded the planting bed in the rear
of the Resource Center along S. Prieur St. and
installed shrubs.
- They completed installing all piping and
sprinklers for station # 11 on the S. Roman St.
side of the MEB.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|