|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #100
Posted: August 28, 2009
The 4th anniversary of
Hurricane Katrina has arrived and this is our
centennial (100th) issue of our biweekly updates. It
seems appropriate to pause and reflect on all that
has been accomplished since Katrina struck the Gulf
Coast.
Within a month of the
disaster, temporary facilities had been established
in Baton Rouge and every class in every School had
been resumed. By early October, 2005 the Finn Jet
had arrived and was moored on the west bank of the
Mississippi. Faculty, staff and students were moving
on board and settling into their interim housing.
The mobile home site on River Road was soon opened
to accommodate families with children and those with
physical challenges that couldn’t be accommodated on
the ocean going ferry.
Within the first few
weeks, millions of dollars of temporary repairs to
the campus buildings were begun. A plan quickly
developed to make the necessary repairs to allow the
upper floors of the main buildings to be reoccupied
and put back into use as quickly as possible. By
June, 2006 every major building on the downtown
campus, with the exception of the Clinical Education
Bldg., was back in use and the temporary facilities
in Baton Rouge began to be shut down.
The damages to the three
main buildings at the Dental School and to the
Clinical Education Building were much more severe
and temporary repairs were significantly more
complex and time consuming. The School of Dentistry
was able to return their operations to New Orleans
for the start of the fall semester, 2007. The front
portions of the Clinical Education Building have
been reoccupied by clinical faculty and staff over
the past year as work on individual floors has been
completed.
While the extensive
temporary repairs were being completed around
campus, the planning and design work for the
permanent building repairs and hazard mitigation was
underway. The complexities of FEMA’s hazard
mitigation program posed challenges to the
architects and periodic changes in FEMA
interpretations delayed much of the design work. The
Lions/LSU Clinic project was the first major repair
and mitigation project to be approved and
contracted. Work on that project was completed
earlier this year.
During the past few
months, we have received FEMA approval and funding
for 4 additional permanent repair and mitigation
projects. Bid documents have been prepared for the
Allied Health/Nursing Building, the Student
Residence Hall and the Resource Center. We expect
these projects to be advertised by the Office of
Facility Planning and Control within the next
several weeks. The final construction and bid
documents for the Clinical Education Building are
being finalized and the project will go to bid
shortly after the documents are complete.
Recent communications with
FEMA and GOHSEP indicate that we are close to having
an acceptable permanent repair and mitigation
project that will jointly address the CSRB and the
MEB. The elevation of flood damaged animal care
functions from the 1st Floors of both buildings into
an addition to the CSRB will restore the pre-storm
capabilities to house research animals on the
downtown campus. Critical building equipment will be
elevated above flood water levels in both buildings.
Significant emergency generator capacity will be
provided in the addition to power emergency circuits
in the surrounding buildings and provide basic
conditioning of the interiors. This will minimize
damages to building contents and mold growth in a
similar future event.
Our proposal to jointly
address the Dental Clinic Building, the
Administration Building and the Power Plant will be
submitted to FEMA shortly. The construction of an
annex to the Clinic Building will allow the
elevation of the critical building equipment out of
the shared basement. It will also house the flood
damaged clinical and research functions that were
housed on the 1st Floor and the basement prior to
Katrina. Animal care space will be provided to
replace the space lost in the basement.
We took advantage of the
delays in getting other major repair and mitigation
projects approved to address Katrina damaged roofs.
Contracts to replace the roofs of several buildings
were bid and awarded. The roofs of the Medical
Education Building, the Dental Clinic Building, the
Dental Administration Building, the Dental Power
Plant, and the Allied Health/Nursing Building have
been completely replaced. The Resource Center roof
replacement project has been awarded and work is
underway.
Finally, we have received
approval and funding from FEMA for well over 100
Project Worksheets that address the repair and/or
replacement of building contents damaged by the
storm. The obligated value of these PWs exceeds $20
million and the Schools and Departments are making
use of these crucial resources.
Four years is a long time,
yet the time seems to have passed very quickly. Our
efforts haven’t been restricted to storm-related
recovery during that time. We’ve made major efforts
to enhance campus safety and security through major
initiatives on exterior lighting of the campus and
expansion of access control. Projects to modernize
the Multi-Disciplinary Labs and research labs
utilized by Physiology and Pathology in the MEB have
been initiated and largely completed. The morgue
facilities were substantially upgraded.
Major renovation projects
to the MEB cafeteria, the MEB 2nd Floor elevator
lobby and the lobby of the Student Residence Hall
have been completed. The atrium that connects the
Allied Health/Nursing Building and the MEB was
modernized. A new Commons area has been created in
the Resource Center Library. Major renovations and
upgrades to the audio/visual systems have been made
to the MEB Auditoriums and to the Dental School
Auditoriums A and B. A major project to modernize
the interiors of building elevators has been
underway for some time and work on many of the
elevators is complete.
A complete overhaul of the
landscaping on the downtown campus is nearing
completion. Student parking lots that had been
gravel-covered were paved and the nearby sidewalks
were replaced. Fences that surround the perimeter
parking lots have been replaced and decorative
elements have been added to enhance the sense of
"campus". Since Hurricane Katrina stuck four years
ago our intention has never been to merely restore
the institution to its pre-storm condition. Rather,
our vision has been and continues to be to emerge
from the recovery period as a better, stronger, and
more modern institution; able to withstand a similar
future hurricane/flood event with minimal damage.
The work to fulfill that vision continues.
Here are highlights of
work that has been accomplished during the past two
weeks.
RESOURCE CENTER ROOF
REPLACEMENT:
- The contractor mobilized equipment on the
roof.
- The contractor removed the existing
stairwell penthouse roof on the Tulane side.
- They lowered one roof drain and applied
a two ply roofing system.
- The contractor removed the existing UPS
penthouse roof on the Tulane Ave. side of the
building.
- They lowered two roof drains and applied
a two-ply roofing system.
- The contractor removed the existing
mechanical room penthouse roof on the Tulane
Ave. side.
- They lowered three roof drains and
applied a two-ply roofing system.
- The contractor removed the existing
mechanical room penthouse roof on the Gravier
St. side of the building.
- They lowered three roof drains and
applied a two-ply roofing system to the
penthouse roof.
Repair Work at 1542 Tulane
Ave.:
- The plumbing contractor made the final
connections for the 3-compartment sink and
grease trap, the hand-wash sink, and ice maker
that serve the coffee kiosk in the 1st Floor
lounge.
- They made final connections for the coffee
maker and espresso machine for the 1st Floor
coffee kiosk.
- The electrical contractor installed the
electrical outlets for the espresso machine,
coffee maker, ice machine, bakery case, and air
curtain.
- Facility Services replaced the automatic
double-doors on the 1st Floor.
- The painter painted the walls in the 1st
Floor lounge.
- Crews cleaned the coffee kiosk area on the
1st Floor.
- The contractor painted the door frames that
lead into the hallway behind the coffee kiosk
and cleaned the kiosk area.
- The contractor prepped the floor in Room
122F (Women’s restroom) to receive new VCT.
- The contractor installed lounge furniture
and tables in the 1st Floor lounge.
- The contractor pulled and connected the
network cables for the 1st Floor lounge coffee
kiosk.
- Facilities Services installed locks on all
kiosk cabinets.
- The contractor installed metal studs for the
access panels in the Women’s restroom.
- In preparation for the creation of an ADA
compliant entrance, the contractor removed
conduit from the garage entrance.
- The contractor replaced cracked window glass
in 3rd and 6th Floor offices.
- Workers replaced cracked window glass in
Stairwell #1 and #3.
- New doors and frames were installed for the
parking garage pipe chase.
- The contractor prepped Rooms 203 and 203A
for mastic and insulation removal.
ALLIED HEALTH/NURSING ROOF
REPLACEMENT:
- The contractor flashed in the front of the AHSON
entrance.
- They finished trimming the roof covering the
entrance roof to the building.
- Workers installed aluminum flashing on the
4th Floor roof.
- The contractor removed his trailer from the
440 Lot.
DENTAL AUDITORIUMS A & B
RENOVATIONS:
- The mechanical contractor programmed the
sequencing for the 2nd Liebert unit in the A/V
Room.
- The electrical contractor certified the
additional network cables installed in
Auditoriums A and B.
- The fire alarm contractor tested the fire
alarm system for proper operation.
- The broken window glass on the 4th Floor
crosswalk was replaced.
- The A/V contractor configured connections
from the A/V rack to the Access Grid rack.
- They installed the projectors and the podium
monitors in Auditorium B.
- Crews installed and configured additional
components for the podium in Auditorium B;
podium 95% complete.
- The A/V contractor programmed the Creston
display panel in Auditorium B and continued
programming in the rack room.
- The contractor relocated a smoke detector in
Auditorium B.
- Facility Services installed furniture in the
auditorium lobby.
- The Auditorium project successfully passed
the State Fire Marshall Inspection.
MEB AIR HANDLING UNIT
REPLACEMENT:
- The contractor finished testing and
balancing air handling units 6-A and 7-A.
- Facility Services completed shifting the
temporary A/C units to the 4th and 5th Floor
Quadrant D (corner of Bolivar Street and Perdido
Street) and monitored performance.
- The contractor demolished the old air
handling units 4-D and 5-D.
- They installed new ductwork and installed
new AHUs 4-D and 5-D.
- Air handling units 4-B and 5-B were
delivered to the 440 Lot storage area.
- The contractor continuing installing new
piping for AHU 5-D.
- They completed chilled water piping and
insulation for AHU 4-D.
MEB 7th FLOOR PHYSIOLOGY
LAB RENOVATIONS:
- The contractor installed vinyl flooring in
Room 7207 (the walk-in cooler).
- The rough-in electrical for Rooms 7221,
7241, 7244, and 7250 was completed.
- Workers laid VCT tiles in Rooms 7221, 7241,
and 7250.
- Crews patched, taped and floated walls in
Rooms 7221, 7241, and 7250.
- The contractor painted the walls in Room
7221 and 7244.
- The contractor completed installing the
ceiling grid in Rooms 7241 and 7250.
- Crews are installing the ceiling grid in
Rooms 7244 and 7250.
RESIDENCE HALL LOBBY
EXPANSION:
- The flooring contractor installed carpet in
the A Tower lobby area and on both mezzanine
floors.
- The network contractor pulled network wires
in the C Tower lobby area.
- The contractor taped and floated the walls
adjacent to the TV cabinet area.
- They installed corner guards throughout the
2nd Floor lobby.
- Crews installed mini blinds in the
recreation room.
- The floor contractor installed and grouted
porcelain bases on the vertical wall across from
the A, B, and C Tower elevators.
- The contractor trimmed out the floor boxes
and ran network wires for the security desk.
- The painters painted the walls perpendicular
to the window wall across from Elevators A and
B.
- They applied a second coat of paint to the
walls of the entire 2nd Floor lobby.
- The contractor completed installing a metal
screen on the security desk and the TV enclosure
cabinet.
- The contractor installed the ceiling mount
bracket for the 65 inch LCD TV in front of the
mailbox area.
- The contractor roughed in the electrical
service in the new security desk.
- They installed the countertop and cabinet
for the security desk.
- The digital signage LCD screen was installed
in the TV enclosure cabinet.
- The contractor began the final clean-up.
MEB 2nd FLOOR LOBBY
RENOVATIONS:
- The wall panel contractor installed the
first and second sets of the metal wall panels.
- The contractor completed installing the
electrical door hardware.
- They installed a register above the digital
sign.
LANDSCAPING:
- Facility Services completed planting sod and
shrubs on the Tulane Avenue side of the Roman
Street Garage.
- Facility Services completed installing
irrigation piping on the Gravier Street side of
the Roman St. Garage.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|