From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #102
Posted: September 25, 2009
We have recently initiated
three new projects on campus. Work has begun on the
renovations to the last of the Multi-Disciplinary
Labs; MDL 4. The improvements will model the work
completed in the three other labs with a new layout,
new lab casework and countertops and state of the
art audio/visual systems. The second is a project to
modernize the ventilation and HVAC systems serving
the Morgue Autopsy in the MEB. The third new project
will replace old fencing at the City Park Campus.
The initial demolition work has begun at all three
sites.
The bid process for the
permanent repair and mitigation projects at the
Allied Health/Nursing Building, the Residence Hall
and the Resource Center continues on schedule. The
bids for all three projects have been advertised.
Pre-bid conferences are scheduled to be held during
the next two weeks. Unless addenda to the bid
documents are needed late in the process, the bids
will be received and opened 30 days after the dates
of the respective advertisements.
Inclement weather
continues to slow progress on the Resource Center
roofing project. The contractor is still beginning
work in the middle of the night in an attempt to
avoid the typical summer afternoon thunderstorms,
but the rainy weather patterns have frequently
produced night time and early morning showers. Crews
have continued to remove the old roofing and place
the temporary two-ply system along the Gravier St.
side of the roof as weather permits.
The contractor demolished
walls and ceilings in Rooms 203 and 203A at 1542
Tulane for the new 2nd Floor garage/building
entrance. The electrical utilities (lights and
outlets) were removed in Rooms 203 and 242B. Crews
framed up the wall for the 2nd Floor entrance and
for the opening for the utility access panel in Room
203. The ductwork for the existing fan coil unit in
Room 203 was removed and the mechanical contractor
installed isolation valves on the heating and
chilled water lines; allowing them to remove the
existing fan coil unit and piping. The new walls
were framed in Rooms 203 and 242B and workers
created a rough opening between Rooms 202A and 203.
Work on the 1st Floor
garage/building entrance also continues. Crews
installed a new door in the main lobby. The
contractor taped and floated the new walls on the
1st Floor and cut the opening for the new 1st Floor
entryway. They primed the sheetrock for the 1st
Floor garage entrance and the sheetrock wall in the
main lobby.
Other work at the Clinical
Education Building included the installation of the
replacement air curtain surround for the kiosk.
Workers installed mini-blinds and wall angle for the
curtain wall in the 1st Floor lounge. The vending
machines were relocated to the 1st Floor lounge and
wiring for the security cameras at the coffee kiosk
was run. The glass contractor replaced the damaged
window glass in Room 102 and the door glass in Room
108.
The current phase of the
AHU replacement project at the Medical Education
Building continued on schedule. The contractor
demolished the old AHU 4-C and 5-C and installed the
new AHU 4-C and 5-C. They finished installing
ductwork, piping and insulation for both units.
Workers continue completing the electrical and
control work for AHU 4-C and 5-C. Workers installed
ceiling tiles in the hallway outside of Mechanical
Room 5-C. AHU parts for 4-A, 4-B, 5-A and 5-B were
moved to the T-lot for temporary storage. The next
phase is scheduled to begin in another week.
The contractor continues
to complete the final tasks in the Residence Hall
lobby expansion project. They installed the door
frame and door by the telephone panel. The
countertop for the security desk has been installed.
Decorative panels were installed by the mailboxes
area and additional chairs and stools were
delivered. The contractor completed troubleshooting
the fire alarm panel. They are working punch list
items at this time.
The Facility Services
landscaping crew completed the demolition in and
around the T-lot in preparation for new landscaping.
They completed installation of the irrigation piping
and electrical wiring around the T-lot. Workers
continue placing topsoil in the planting areas
around the lot. At the City Park Campus, a
contractor removed stumps in the field between
Florida Avenue and the railroad tracks.
Here are highlights of
work that has been accomplished during the past two
weeks.
ALLIED HEALTH/NURSING
PERMANENT REPAIRS AND MITIGATION:
- Bids were advertised on 9/11/2009
- The Pre-Bid Conference will be held on
9/28/2009 in the Chancellor’s Conference Room.
- Bids will be opened on 10/7/2009.
STUDENT RESIDENCE HALL
PERMANENT REPAIRS AND MITIGATION:
- Bids were advertised on 9/16/2009
- The Pre-Bid Conference will be held on
10/1/2009 in the Chancellor’s Conference Room.
- Bids will be opened on 10/14/2009.
RESOURCE CENTER PERMANENT
REPAIRS AND MITIGATION:
- Bids were advertised on 9/23/2009
- The Pre-Bid Conference will be held on
10/8/2009 in the Chancellor’s Conference Room.
- Bids will be opened on 10/21/2009.
RESOURCE CENTER ROOF
REPLACEMENT:
- The contractor removed additional sections
of the roof along Gravier Street and applied the
two-ply roofing system.
1542 TULANE GARAGE
ENTRANCES:
- The contractor demolished walls and ceiling
in Rooms 203 and 203A for the 2nd Floor
garage/building entrance.
- They demolished the electrical utilities
(lights and outlets) in Rooms 203 and 242B.
- Crews framed up the wall for the 2nd Floor
Parking Garage Entrance and the opening for the
utility access panel in Room 203.
- The contractor removed the ductwork for the
existing fan coil unit in Room 203.
- The mechanical contractor installed
isolation valves on the heating and chilled
water lines and removed the existing fan coil
unit and piping in Room 203.
- The contractor framed the new walls in Rooms
203 and 242B and created a rough opening between
Rooms 202A and 203.
- They installed metal stud walls on the 2nd
Floor.
- Crews installed a new door in the main
lobby.
- The contractor taped and floated the walls
on the 1st Floor.
- They cut the opening for the new 1st Floor
entryway.
- The contractor primed the sheetrock for the
1st Floor Garage Entrance and the sheetrock wall
in the main lobby.
1542 TULANE AVE. REPAIRS:
- Facility Services installed the replacement
air curtain surround for the kiosk.
- The contractor installed mini-blinds and
wall angle for the curtain wall in the 1st Floor
lounge.
- The vending machines were relocated to the
1st Floor lounge.
- Wiring for the security cameras at the
coffee kiosk was installed.
- The damaged window glass in Room 102 and the
door glass in Room 108 was replaced.
DENTAL AUDITORIUMS A & B
RENOVATIONS:
- The contractor roughed in for the access
control components.
MEB AIR HANDLING UNIT
REPLACEMENT:
- Facility Services monitoring the temporary
A/C units serving the 4th and 5th Floor Quadrant
C (corner of Bolivar Street and MEB loading
dock).
- The contractor demolished the old AHU 4-C
and 5-C.
- They installed the new AHU 4-C and 5-C and
began connecting new ductwork and new piping.
- The contractor completed installing
ductwork, piping and insulation for both AHU 4-C
and AHU 5-C.
- Workers installed ceiling tiles in the
hallway outside of Mechanical Room 5-C.
- AHU parts for 4-A, 4-B, 5-A and 5-B were
moved to the T-lot for temporary storage.
- Workers continued with the electrical and
control work for AHU 4-C and 5-C.
MEB 7th FLOOR PHYSIOLOGY
LAB RENOVATIONS:
- The contractor installed the new countertops
in Rooms 7221, 7241, 7244 and 7250.
- They installed sinks and plumbing fixtures
in Rooms 7241, 7244, and 7250.
- The contractor installed laboratory
furniture and countertops in Room 7244.
- Network wires were run in Rooms 7221, 7241
and 7250.
- The contractor trimmed out the electrical in
Rooms 7241 and 7250.
- Workers installed electrical raceway and
receptacle outlet for the center islands in
Rooms 7221, 7241, and 7250.
- The contractor installed the door and frame
in Room 7244.
- Crews installed fume hoods and connected the
exhaust ducts in Rooms 7241 and 7244.
- Crews began installing ceiling tiles in
Rooms 7221 and 7250.
MEB MORGUE AUTOPSY HVAC
UPGRADE:
- A new project has started to upgrade the
ventilation and HVAC systems serving the MEB
Morgue.
- The contractor removed the existing exhaust
duct on the 1st Floor.
MDL 4 RENOVATION:
- The project to renovate the last of the
Multidisciplinary Labs in the Medical Education
Building has begun. The work will model the
renovations made in the other labs.
- The contractor removed the old plumbing and
lab furniture.
DENTAL SCHOOL FENCE
REPLACEMENT:
- The contractor started removing the chain
link fence along Moss and Florida Avenue.
RESIDENCE HALL LOBBY
EXPANSION:
- The contractor installed a door frame and
door by the telephone panel.
- The countertop for the security desk has
been installed.
- The contractor completed troubleshooting the
fire alarm panel.
- Decorative panels were installed by the
mailboxes area.
- Chairs and stools were delivered.
- The contractor is completing the punch list
items.
LANDSCAPING:
- Facility Services completed the demolition
in and around the T-lot in preparation for
landscaping.
- Facility Services completed installing the
irrigation piping and electrical wiring around
the T-lot.
- Workers continued placing topsoil in the
planting areas around the lot.
- The contractor removed stumps in the field
between Florida Avenue and the railroad at the
City Park Campus.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|