From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #109
Posted: January 15, 2010
On Thursday, January 7th
the mandatory pre-construction conferences were held
for the three new permanent building repair and
mitigation projects that are getting underway. These
projects address the Allied Health/Nursing Building,
the Student Residence Hall and the Resource Center.
All three projects encompass the permanent repairs
to the flood damaged 1st Floors and the elevation of
critical mechanical, electrical and plumbing
equipment to protect it from damage in the future.
The project in the Allied Health/Nursing Building
also includes LSUHSC funded enhancements on the 2nd
Floor which will convert existing offices into a
large lecture hall and relocate the faculty and
staff offices to the 1st Floor. The demolition phase
of work on the 1st Floor of the Allied
Health/Nursing Building has recently begun. The
projects at the Student Residence Hall and the
Resource Center should get underway shortly.
The Resource Center
roofing crews have completed the installation of the
3-ply roof and are now focused on completing the
flashing and trim work. They installed the walkway
pads and removed the caulk joints from the main
penthouse. The metal flashing around the base of the
atrium and mech./elec. equipment room penthouse was
installed. The contractor completed the wall panel
installation. Crews installed the counter-flashing
around the atrium and on the parapet walls along
Gravier St., S. Prieur St, and Tulane Ave. They
installed the parapet wall cap on the Tulane Street
stairwell penthouse. The contractor completed the
parapet wall cap on the main elevator penthouse and
continued installing the parapet wall cap and metal
panels for the Tulane Ave. penthouse. Workers sealed
the vertical glass panels on the sides of the
atrium.
The MEB air handling
replacement contractor completed the duct work,
electrical piping, and insulation for AHU 2-B and
the duct detectors for were installed. They
completed installation of duct work for AHU 2-D.
Crews installed isolator springs on the exhaust fans
for AHU 2-B and AHU 4-A. The freeze-stats were
relocated on the AHUs throughout the building to
prevent false tripping. The subcontractor completed
the control work on AHU 2-D.
Facility Services
relocated and installed the
temporary air conditioning serving the cafeteria
kitchen area. The contractor removed AHU 2-A and set
the new housekeeping pads. They
installed the new AHU 2-A, installed ductwork
for AHU 2-A and demolished
the old AHU 3-A.
The contractor installed the
new AHU 3-A components and ductwork.
The chilled water, hot water and drain piping
for AHUs 2-A and 3-A and sealed ductwork on AHU 2-A
were completed.
Workers continue the electrical and controls work on
AHU 2-A and AHU 3-A.
The renovations to MDL #4
are nearing completion. The contractor finished
installing lab furniture (casework) in the main MDL
room and the countertops in the main MDL room and in
Room 4210. New sinks were installed in the
countertops and crews installed the cantilever arms
and panels for the lab furniture. The contractor
installed and connected the electrical receptacles,
medical air/gas/vac lines and acid waste lines to
the new lab furniture. Network cables were run to
the new furniture and the contractor installed
partition panels. Workers primed and applied the
first and second coats of paint in Room 4210 and
installed the new ceiling tiles and light fixtures.
The audio/visual
subcontractor has completed most of his work in MDL
#4. The speakers were installed in the main MDL
room. Workers pulled A/V wiring in the main MDL room
and the 42" and 65" LCD monitors were installed.
They are programming the A/V equipment, installing
the controllers and testing the system.
The contractor continued
roughing in electrical conduit and boxes for
lighting in the spaces being renovated on the 7th
Floor of the Lions/LSU Clinic Building. They ran
electrical conduit from the electrical room to the
new lab area and above the ceiling in the adjacent
lab (Room 795). Conduit was run from the Bolivar
Street side electrical room to the new lab area.
Crews ran new drain lines on the 6th Floor and the
old waste lines were removed. They framed up the
concrete curb for the ice machine and poured the
base. Workers hung sheetrock in the lab and
adjacent office spaces and installed a door frame in
Room 796. Crews taped and floated the interior
walls.
The 8th Floor renovations
in the Lions/LSU Clinic continue. The
contractor continued running lighting conduit and
pulling wires in the small conference room. They
hung sheetrock on the curved wall,
in the conference room and
on the front fur down in the main conference
room. Workers began hanging
brackets for the large
conference room lights and the
electrical subcontractor
ran conduit for the A/V equipment.
Work continues on the A/V
upgrades to the 3rd Floor Seminar Rooms in the
Medical Education Building. The contractor assembled
and programmed the five new podiums. Podiums were
installed in Seminar Rooms 4, 5, 6 and 10.
Electrical conduit was installed in Seminar Room 4.
The contractor continued patching the sheetrock wall
in Seminar Room 4 and installed the ceiling tile and
grid in Seminar Room 7/8.
The upgrades to the
exhaust and HVAC systems supporting the MEB Autopsy
room and Morgue continue. The embalming tank
relief vent was connected to
the building's acid vent piping. Workers installed lights and ceiling tiles in
the Autopsy Room. They ran
ductwork on the 1st Floor for the down-draft autopsy
tables. The fire alarm junction box for the pull
station by the stairwell was relocated. The spiral duct was connected to the exhaust
duct by the stairwell chase.
The contractor installed grilles in the Morgue and
the Women’s restroom and secured the exhaust fan to
the roof deck. Crews removed
one autopsy table from the
room in preparation for installing the new table
and core drilled in the autopsy room for the
plumbing and ductwork that
will connect to the new table.
Other small projects
continued around campus. The contractor installed
the new exterior signage on the front of the
Clinical Education Building. A bypass valve for the
wet vacuum tank located in the School of Dentistry
Clinic Building basement was installed. Work on that
project is complete except for the installation of a
timer. The fencing contractor installed swing gates
along Florida Avenue and Castine Street. They
installed light bollards near the Power Plant and
laid the base block for four monumental fence
columns along Moss Street. Crews completed the final
grading for the new sod to be laid on both sides of
the Residence Hall and laid new sod.
Here are highlights of
work that has been accomplished during the past two
weeks.
RESOURCE CENTER ROOF
REPLACEMENT:
- The contractor installed the walkway pads,
and touched up the flashing along the exterior
of the building.
- Workers removed the caulk joints from the
main penthouse.
- The metal flashing around the base of the
atrium and mech./elec. equipment room penthouse
was installed.
- The contractor completed the wall panel
installation except for sections near both roof
penthouses.
- Crews installed the counter-flashing around
the atrium and started installing the
counter-flashing along Gravier Street.
- They installed the parapet wall cap on the
Tulane Street stairwell penthouse.
- The contractor installed the
counter-flashing along the S. Prieur Street and
the parapet wall near Tulane Avenue.
- Workers sealed the vertical glass panels on
the Perdido, Bolivar and Prieur Street sides of
the atrium. This completes the
sealing of the glass panels.
- The contractor completed the parapet wall
cap on the main elevator penthouse and continued
installing the parapet wall cap and metal panels
for the Tulane Ave. penthouse.
MEB AIR HANDLING UNIT
REPLACEMENT:
- The contractor completed duct work,
electrical piping, and insulation for AHU 2-B
and the duct detectors for were installed.
- The contractor completed installation of
duct work for AHU 2-D.
- Crews installed isolator springs on the
exhaust fans for AHU 4-A.
- They continued installing isolator springs
on the exhaust fan for AHU 2-B.
- The contractor and control subcontractor
relocated freeze-stats on units throughout the
building to prevent false tripping.
- The control subcontractor completed the
control work on AHU 2-D.
- Facility Services relocated
and installed the temporary air
conditioning serving the cafeteria kitchen area.
- The contractor removed AHU 2-A and set the
new housekeeping pads.
- They installed the
new AHU 2-A, installed ductwork for AHU 2-A,
demolished the old AHU
3-A
- The contractor installed AHU 3-A components
and ductwork.
- The chilled water, hot water and drain
piping for AHUs 2-A and 3-A and sealed
ductwork on AHU 2-A were
completed.
- Workers continue the electrical and controls
work on AHU 2-A and AHU 3-A.
MDL 4 RENOVATIONS:
- The contractor finished installing lab furniture
(casework) in the main MDL room.
- The contractor installed countertops in the
main MDL room and in Room 4210
and new sinks in the countertops.
- The contractor installed cantilever arms and
panels for the lab furniture.
- They installed ceiling tiles and light
fixtures in Room 4210.
- The contractor completed installing the
electrical receptacles and acid waste lines in
the new lab furniture.
- They completed
connecting the medical air/gas/vac lines to the
new lab furniture and the acid waste lines to
the lab sinks.
- Network cables were run to the new lab
furniture.
- The speakers were installed in the main MDL
room.
- Workers pulled A/V wiring in the main MDL
room.
- The 42" and 65" LCD monitors were installed.
- They began programming A/V equipment,
installing controllers
and testing the system.
- The contractor installed partition panels.
- Workers primed and applied the first and
second coats of paint in Room 4210.
LIONS/LSU CLINIC BLDG. 7th
FLOOR LAB RENOVATIONS:
- The contractor continued
roughing in electrical conduit and boxes for
lighting.
- They installed electrical conduit from the
electrical room to the new lab area and ran
electrical conduit above the ceiling in the
adjacent lab (Room 795).
- Conduit was run from the Bolivar Street side
electrical room to the new lab area.
- Crews ran new drain lines on the 6th Floor
and the old waste lines were removed.
- They framed up the concrete curb for the ice
machine and poured the base.
- Workers hung sheetrock in the lab and
adjacent office spaces and installed a door
frame in Room 796.
- Crews taped and floated the interior walls.
LIONS/LSU CLINIC BLDG. 8th
FLOOR RENOVATIONS:
- The contractor continued running lighting
conduit and pulling wires in the small
conference room.
- They hung sheetrock on the curved wall and
began installing sheetrock in the conference
room.
- The contractor installed sheetrock on the
front fur down in the main conference room.
- Workers began hanging
brackets for the large
conference room lights.
- The electrical contractor ran conduit for
the A/V equipment.
MEB SEMINAR ROOM AV
INSTALLATION:
- The contractor installed the ceiling tile
and grid in Seminar Room 7/8.
- The contractor assembled and programmed the
five new podiums. Podiums were installed in
Seminar Rooms 4, 5, 6 and 10.
- Electrical conduit was installed in Seminar
Room 4.
- The contractor continued patching the
sheetrock wall in Seminar Room 4.
MEB AUTOPSY EXHAUST
UPGRADE:
- The contractor connected the embalming tank
relief vent to the building's acid vent piping.
- Workers installed lights and ceiling tiles
in the Autopsy Room.
- They ran ductwork on the 1st Floor for the
down-draft autopsy tables.
- The contractor insulated the HVAC duct in
the Women’s bathroom.
- The fire alarm junction box for the pull
station by the stairwell was relocated.
- The spiral duct was connected to the exhaust
duct by the stairwell chase.
- The contractor installed grilles in the
Morgue and the Women’s restroom and secured the
exhaust fan to the roof deck.
- The contractor began installing the plaster
ceiling in the Women’s bathroom.
- Crews removed one autopsy table
from the room in
preparation for installing the new table.
- The contractor core drilled in the autopsy
room for the plumbing that will connect to the
new table.
1542 TULANE AVE. EXTERIOR
SIGNAGE:
- The contractor installed the new exterior
signage.
WET VACCUM TANK
REPLACEMENT:
- The contractor installed a bypass valve for
the tank located in the School of Dentistry
Clinic Building basement. Work is complete
except for timer installation.
FENCE REPLACEMENT PROJECT:
- The contractor installed swing gates along
Florida Avenue and Castine Street.
- They installed light bollards near the Power
Plant.
- Workers laid the base block for four
monumental columns along Moss Street.
EXTERIOR/LANDSCAPING:
- Crews completed the final grading for the
new sod to be laid on both sides of the
Residence Hall.
- Facility Services laid sod along Bolivar and
South Roman Streets adjacent to the Residence
Hall.
We encourage you to follow
the details of our progress through the daily
updates which are posted on the web site.
|