Subject: Hurricane Katrina Recovery – Update #111
Posted: February 12, 2010

The Project Worksheet (PW 9283 Version 6) and hazard mitigation proposal (HMP) for the CSRB has cleared all of the local review queues and has moved into the $20 million queue in Washington, D.C. This is the final review and approval required before $29,346,893.00 for the project will be obligated. PW 7453 Version 5 and the associated HMP for the Medical Education Building, valued at $6,241,753.00, has moved through most of the local review queues. When it clears the insurance queue and the State queue, it will be forwarded to the $1 million queue in Washington, D.C. We have been working diligently to expedite the reviews of this package.

The contractor working on permanent repairs and mitigation at the Allied Health/Nursing Building is continuing with demolition work and has started on the permanent repairs and mitigation. Sheetrock and studs have been removed from Stairwells 2 & 3 and from the Tiger Room. Ductwork and steel was removed from the west side of the 1st Floor. The duct detectors have been removed from 1st Floor AHUs and the ceilings were removed from Rooms 2B2, 2B4 and 2B5. The plumbing in the 1st Floor restrooms was rerouted. Electrical conduit for lighting on the west side of the 1st Floor is being installed.

The permanent repair and mitigation project at the Resource Center is progressing. Restroom fixtures and tile walls were removed from the 1st Floor. A number of granite floor pavers and wall panels were removed. The studs were demolished in the Parking Office. Conduit was run between the new switchgear location and Riser B, the tap box in Room 219 and the fire pump. Copper lines for the sump pump are being run.

The site preparation has been completed at the Student Residence Hall. The contractor installed a temporary fence in the back parking lot area surrounding the construction site. Workers removed the parking lot car stops from the building site and ran temporary power to the construction site in the parking area. They removed asphalt in the parking lot to prepare for construction of the new structure that will house the critical mechanical and electrical equipment.

The next step is to drive piles to support the new elevated structure that will house critical electrical and mechanical equipment. Events related to Mardi Gras have prevented the contractor from securing the permit needed to move the pile driving equipment to the site. We anticipate that the pile driver will be onsite within the next two weeks.

The 7th Floor lab renovations in the Lions/LSU Clinic Building continue. The contractor installed hangers for the ceiling grid and patched sheetrock. The ceiling grid was installed and workers sanded the new sheetrock and primed the walls. The emergency power electrical conduit was installed in the mechanical room. Fire sprinklers were relocated in the lab area and hot water pipes are being run to the VAV boxes.

The contractor finished framing the curved storefront wall on the 8th Floor of the Lions/LSU Clinic Building and installed sheetrock around the top of the wall. They installed sheetrock in the circle part of the ceiling outside the large conference room. Door frames were installed in the large and small conference rooms. Workers taped and floated the sheetrock in the large and small conference rooms and in the reception area. They installed the ceiling grid in the Director’s office and the small conference room. Facility Services ran heating hot water pipes to the VAV boxes. The metal ductwork was installed in the large conference room.

The contractor removed the second (old) autopsy table from the MEB autopsy room. They roughed in the plumbing piping and ductwork for the second morgue table. The new autopsy table was installed and the plumbing and electrical was connected. The exhaust duct for the second autopsy table was also connected.

Crews continued installing and programming modules in the new fire alarm summary panel at the Residence Hall and shifting the new devices from the old panel to the new panel. The devices serving mezzanine and the 2nd through the 11th Floors have been shifted from the old panel to the new panel. New smoke detectors were installed on the mezzanine, the 1st through the 7th Floor of the C Tower and in the elevator shafts. The contractor completed transferring flow and tamper switches for the A and B towers to the new panel.

The contractor responsible for installing the new flashing on the front of the Residence Hall removed the window frame in apartment B34 and installed the flashing. They welded the permanent metal flashing in place in and installed new sheetrock. Workers removed the plaster wall in apartment C31.

Facility Services completed installing irrigation control valves and piping for the main irrigation lines on the field side of the horseshoe drive, in the island and on the Clinic Building side of the horseshoe. They installed the control wiring to valves around the horseshoe. Workers trenched for the new irrigation piping in front of the Administration Building and backfilled the trenches nearest the backflow preventer on the field side of the horseshoe. The station piping and sprinklers were installed on the right side of the Administration Building front steps and between the Administration Building front steps and the Clinic Building steps. Crews completed the irrigation station piping and sprinkler heads along the Clinic side of the horseshoe drive. Irrigation station piping was installed between the Clinic Building steps and Florida Avenue. Trenches were dug for irrigation stations in the center island of the horseshoe drive. They installed piping for first of two stations in the center island and buried the irrigation station piping in the center of the horseshoe island. The contractor responsible for the fence replacement installed framing and rebar for the 35 monumental fence columns.

Here are highlights of work that has been accomplished during the past two weeks.

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor removed sheetrock and studs from Stairwell 2 and Stairwell 3.
  • Crews removed sheetrock and metal studs from the Tiger Room.
  • Workers removed ductwork and steel from the (west) Bolivar St. side of the building.
  • The contractor rerouted plumbing piping in the 1st Floor restrooms.
  • Electrical receptacles were installed on the west side of the 1st Floor.
  • The contractor ran electrical conduit for the light fixtures on the west side of the 1st Floor.
  • Crews removed the duct detectors from the AHUs on the 1st Floor.
  • The ceilings were removed from Rooms 2B2, 2B4 and 2B5.
  • Crews removed the Bolivar Street side of electrical room 115.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor removed restroom fixtures and the tile walls from the 1st Floor facilities.
  • Crews ran conduit on the 1st Floor between the new switchgear location and riser B.
  • They ran conduit on the 1st Floor between the new switchgear location and the fire pump.
  • The contractor is installing conduit between the new switchgear location and the tap box in Room 219.
  • The contractor began to run the copper lines for the sump pump on the 1st Floor.
  • The metal studs were removed from the parking office area.
  • The contractor removed 9 of 17 granite floor pavers and 14 of 25 granite wall panels on the 1st Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed a temporary fence in the back parking lot area surrounding the construction site.
  • Workers removed the parking lot car stops from the building site and ran temporary power to the construction site in the parking area.
  • They removed asphalt in the parking lot to prepare for construction of the new structure that will house the critical mechanical and electrical equipment.

MEB MDL 4 RENOVATIONS:

  • The renovations are substantially complete. The contractor began working on the punch list items.
  • The contractor programmed the A/V equipment and continued working on punch list items.

LIONS/LSU CLINIC BLDG. 7th FLOOR LAB RENOVATIONS:

  • The contractor continued installing hangers for the ceiling grid and patching sheetrock.
  • Workers installed emergency power electrical conduit in the mechanical room.
  • They are running heating hot water pipes to the VAV boxes.
  • The contractor installed emergency power electrical conduit in the mechanical room.
  • The ceiling grid has been installed.
  • They sanded the sheetrock wall and primed the walls.
  • The contractor installed the forty metal ceiling panels on the 6th Floor that were removed to do plumbing work.
  • Crews relocated fire sprinklers in the lab area and removed the wall adjacent to the lab to make room for the window.

LIONS/LSU CLINIC BLDG. 8th FLOOR RENOVATIONS:

  • The contractor finished framing the curved storefront wall.
  • Facility Services ran heating hot water pipes to the VAV boxes.
  • The contractor installed sheetrock around the top of the curved storefront wall.
  • Metal ductwork was installed in the large conference room. .
  • Workers taped and floated the sheetrock in the large and small conference rooms and the reception area and installed the ceiling grid in the Director’s office.
  • The ceiling grid and supply grilles were installed in the small conference room.
  • The contractor installed sheetrock in the circle part of the ceiling outside the large conference room.
  • Workers installed electrical receptacles for the 56 inch LCDs in the Director’s office.
  • They installed door frames in the large and small conference rooms.

MEB AIR HANDLING UNIT REPLACEMENT:

  • Facility Services removed the temporary air conditioning serving the cafeteria kitchen area.
  • The contractor completed pipe labeling for all AHUs on the 2nd and 3rd floors.

MEB 2ND FLOOR AUTOPSY EXHAUST UPGRADE:

  • The contractor removed the second (old) autopsy table.
  • They roughed in the plumbing piping and ductwork for the second morgue table.
  • The contractor installed the second autopsy table and connected the plumbing and electrical.
  • The exhaust duct for the second autopsy table was connected.

FENCE REPLACEMENT PROJECT:

  • The contractor installed framing and rebar for the 35 monumental fence columns.

RESIDENCE HALL FIRE ALARM SYSTEM UPGRADE:

  • The contractor continued installing and programming modules in the new fire alarm summary panel and shifting the new devices from the old panel to the new panel.
    • They completed shifting the devices serving 3rd through the 11th Floor from the old panel to the new panel.
  • New smoke detectors were installed on the mezzanine and the 1st through the 7th Floor of the C Tower.
  • Workers installed new smoke detectors in the elevator shafts.
  • All of the new devices on the mezzanine and 2nd Floor have been connected to the new panel.
  • The contractor completed transferring flow and tamper switches for the A and B towers to the new panel.

RESIDENCE HALL LOBBY ROOF FLASHING:

  • The contractor removed the window frame in apartment B34 and installed the flashing.
  • They welded the permanent metal flashing in place in apartment B34 and installed new sheetrock.
  • The contractor removed the plaster wall in apartment C31.

EXTERIOR/LANDSCAPING:

  • Facility Services completed installing irrigation control valves and piping for the main lines on the field side of the horseshoe drive, in the island and on the Clinic Building side of the horseshoe.
  • They completed installing all control wiring to valves around the horseshoe.
  • Workers trenched for the new irrigation piping in front of the Administration Building and backfilled the trenches nearest the backflow preventer on the field side of the horseshoe.
  • Facility Services completed burying and backfilling trenches for the 2-inch main irrigation piping around the horseshoe drive.
  • They installed station piping and sprinklers on the right side of the Administration Building front steps and between the Administration Building front steps and the Clinic Building steps.
  • Irrigation station piping was installed between the Clinic Building steps and Florida Avenue.
  • Trenches were dug for irrigation stations in the center island of the horseshoe drive.
  • Facility Services completed the irrigation station piping and sprinkler heads along the Clinic side of the horseshoe drive.
  • They installed piping for first of two stations in the center island and buried the irrigation station piping in the center of the horseshoe island.

We encourage you to follow the details of our progress through the daily updates which are posted on the web site.