|
From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #113
Posted: March 12, 2010
Next week, a contractor
will begin construction of a new covered walkway
connecting the South Claiborne Street entrance of
the Gravier Street Garage with the Lakeside Lot
entrance of the Clinical Education Building (1542
Tulane Avenue). The new walkway will provide a
covered and lighted pathway between the Gravier
Street Garage and the CEB. During construction,
access through the construction zone will be
blocked. Alternate pathways to and from the CEB will
be provided and signage will be posted to aid in
getting to the entrances that are to be used during
construction. Pedestrians may gain access to the
Clinical Education Building through the front doors
on Tulane Avenue and through the rear doors in
stairwell number one (by the rear elevator bank).
The Lakeside Lot entrance will be closed during
construction, and the front doors of the CEB will be
accessible by ID card entry 24 hours a day and 7
days a week.
The contractor continued
demolition in Rooms 211, 212, 233 and 236 of the
Allied Health/Nursing Building and began demolition
in Room 244. The controls contractor demolished
pneumatic tubing in the 1st Floor mechanical room
and the metal ductwork was removed. Four holes
needed for re-routed plumbing utilities were cored
on the 2nd Floor. The contractor ran cast iron roof
drain pipe on the 1st Floor. Crews are installing
electrical conduit in the main corridor of the 1st
Floor.
The two electrical
transformers located on the 1st Floor of the
Resource Center were raised to a height that will
prevent damage from a future flood event. Crews
installed conduit on the 1st Floor between the new
switchgear location and the backup power tap box in
Room 219 and for the new ATS room. Conduit was
installed for the electrical receptacles on the 1st
Floor. New isolation valves were installed for both
of the restroom water risers and plumbing lines in
the 1st Floor restrooms were capped. The plumbers
raised the water lines for the new ADA toilets in
the 1st Floor restrooms and installed new copper
lines for the sump pump on the 1st Floor. Workers
removed 4 granite pavers in the front of the
elevators and 4 granite pavers by the old security
desk location. Crews surveyed core locations for
post tension cables in the 3rd-8th Floor electrical
rooms. The new concrete masonry unit (CMU) walls
were laid out on the 1st Floor.
The contractor delivered
the wood piles to the Student Residence Hall
construction site and began driving piles to support
the new structure that will elevate and house
critical mechanical and electrical equipment. They
drove the 50 wood piles needed for the new structure
and the pile driving rig was removed. Workers
excavated in preparation for pouring four of eight
concrete pile caps and wood forms for the four pile
caps were erected.
Renovations on the 7th
Floor of the Lions/LSU Clinic Building are
continuing. The contractor installed studs and the
the window storefront between the adjacent labs and
the frames for the storefront system adjacent to the
main corridor. One of the three storefronts was
installed. Electricians pulled wire from the
electrical room to the lab. The contractor relocated
sprinkler heads in the renovated spaces.
Sheetrock
was installed underneath the storefront
joining the two labs.
On the 8th Floor of the
Lions/LSU Clinic Building, the contractor
installed junction boxes for the large pendant light
fixtures in the large conference room
and the linear diffusers were installed. Crews
started installing hangers for the ceiling
grid in the large conference room. They installed the
ceiling grid trim in the lobby area. The storefront system is
being installed.
The State Fire Marshal’s
Office completed their inspection of two recently
completed projects. All four of the renovated
Multi Disciplinary Labs located in
the Medical Education Building passed
as did the 2nd Floor Autopsy Exhaust system upgrade.
The project to replace the
fire alarm system in the Student Residence Hall is
substantially complete. Crews installed smoke
detectors in the elevator penthouses, installed pull
stations in the stairwells and installed relay
modules for the roll-up doors in the garage. The old fire panel was removed from the 1st
Floor University Police office. The contractor installed duct detectors for
air handling units 1, 2, 3,
4, 5 and 6. The inactive fire
alarm wiring associated with the old fire alarm
summary panel was removed. All
of the new devices have been
transferred to the new fire alarm summary
panel and the panel has been
activated. The contractor
finished programming the new fire alarm panel
and the new panel is fully operational.
The contractor has begun testing the new
system.
The contractor
responsible for the fence
replacement project around the Dental School
formed up and poured the remaining
monumental fence columns. All
25 monumental columns have
now been formed up, poured and the
forms removed. The crew completed installing
all of the fence hats.
Facility Services
completed placing and grading topsoil in the center
island of the horseshoe drive at the
School of Dentistry and finished grading the
planting beds on the Administration
and Clinic Building sides
of the horseshoe. Crews
planted shrubs in the beds on the Administration
and Clinic Building sides
of the horseshoe and installed
plants by the Administration Building handicapped
ramp. Two irrigation stations
were connected to the
controller and programmed.
They installed landscape edging and
spread mulch in the planting bed between the
Clinic Building steps and the Administration
Building steps. The center
island was graded, landscape
edging was installed and
shrubs were planted in the
center island.
Here are highlights of
work that has been accomplished during the past two
weeks.
ALLIED HEALTH/NURSING BLDG
PERMANENT REPAIRS & MITIGATION:
- The contractor continued demolition in Rooms
211, 212, 233 and 236.
- Demolition began in Room 244.
- The controls contractor demolished pneumatic
tubing in the 1st Floor mechanical room.
- Workers removed metal ductwork from
mechanical room 1A.
- Four holes needed for re-routed
plumbing utilities were cored
on the 2nd Floor.
- Crews removed the sheetrock ceiling near the
American flag on the 1st Floor.
- The contractor ran cast iron roof drain pipe
on the 1st Floor.
- Crews are installing
electrical conduit in the main corridor of the
1st Floor.
RESOURCE CENTER PERMANENT
REPAIRS & MITIGATION:
- The two electrical transformers
located on the 1st Floor were raised to a height
that will prevent damage from a future flood
event.
- Crews installed conduit on the 1st
Floor between the new switchgear location and
the backup power tap box in Room 219.
- The contractor installed conduit for
receptacles on the 1st Floor.
- Workers continue to run conduit for the new
ATS room.
- New isolation valves
were installed for both of the restroom
water risers.
- The plumbing lines in the 1st Floor
restrooms for the toilets that are being removed
were capped.
- The contractor raised the water lines for
the new ADA toilets in the 1st Floor restrooms.
- They installed new copper lines for the sump
pump on the 1st Floor.
- New copper lines and hangers for the
new domestic water lines were
installed on the 1st Floor.
- They removed 4 granite pavers in the front
of the elevators and 4 granite pavers by the old
security desk location.
- The contractor surveyed core locations for
post tension cables in the 3rd-8th Floor
electrical rooms.
- The new concrete masonry unit (CMU)
walls were laid out on
the 1st Floor.
- Workers removed ceiling grid on the 1st
Floor, Bolivar Street side.
RESIDENCE HALL PERMANENT
REPAIRS & MITIGATION:
- The contractor delivered the wood piles to
the site and began
driving piles to support the new structure that
will elevate and house critical mechanical and
electrical equipment.
- They drove the 50 wood piles needed
for the new raised structure and the pile driving rig was removed.
- Workers excavated in
preparation for pouring four of eight
concrete pile caps
- The contractor erected wooden forms for the
four pile caps.
LIONS/LSU CLINIC BLDG. 7th FLOOR
LAB RENOVATIONS:
- The contractor installed
studs and the the window storefront
between the adjacent labs.
- Workers installed the frames for the
storefront system adjacent to the main corridor.
- Electricians pulled wire from the
electrical room to the lab.
- The contractor relocated sprinkler heads.
- Sheetrock was
installed underneath the storefront
joining the two labs.
- The contractor installed 1 of 3 storefronts
adjacent to the center hallway.
LIONS/LSU CLINIC BLDG. 8th
FLOOR RENOVATIONS:
- The contractor installed junction boxes for
the large pendant light fixtures in the large
conference room.
- They installed the
ceiling grid trim in the lobby area.
- The linear diffusers in the large
conference room have been
installed.
- Crews started installing hangers for
the ceiling grid in the large conference room.
- The storefront system is
being installed.
MEB MDL RENOVATIONS:
- All four of the renovated Multi Disciplinary
Labs passed the State Fire Marshal Inspection.
MEB 2ND
FLOOR AUTOPSY EXHAUST UPGRADE:
- The morgue passed the State Fire Marshal
Inspection.
FENCE REPLACEMENT PROJECT:
- The contractor formed up and
poured 9 additional monumental columns.
- All 25 monumental
columns have now been formed up,
poured and the forms removed.
- The contractor completed installing all of
the fence hats.
RESIDENCE HALL FIRE ALARM
SYSTEM UPGRADE:
- Crews installed smoke detectors in the
elevator penthouses, installed pull stations in
the stairwells and installed relay modules for
the roll-up doors in the garage.
- The old fire panel was removed from the 1st
Floor University Police office.
- The contractor installed duct detectors for
air handling units 1, 2, 4, 5 and 6.
- They installed duct detectors for air
handling unit 3 and removed inactive fire alarm
wiring associated with the old fire alarm
summary panel.
- The contractor finished
programming the new fire alarm panel.
- All of the new devices
have been transferred to
the new fire alarm summary panel and the panel
has been activated.
- The new fire alarm panel is fully
operational and the
contractor has begun testing the new system.
EXTERIOR/LANDSCAPING:
- Facility Services completed placing and
grading topsoil in the center island of the
horseshoe.
- They finished grading the planting beds on
the Administration and Clinic
Building sides of the
horseshoe.
- Crews planted shrubs in the beds on
the Administration and Clinic
Building sides of
the horseshoe.
- They installed
plants by the Administration Building
handicapped ramp.
- Two irrigation stations
were connected to the
controller and programmed.
- They spread mulch in the section to the
right of the Administration Building steps and
adjusted the sprinklers.
- They installed landscape edging and
spread mulch in the
planting bed between the Clinic Building steps
and the Administration Building steps.
- Facility Services graded
the center island,
installed landscape edging and planted shrubs in
the center island.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|