From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #118
Posted: May 21, 2010
Work on the permanent repairs
and mitigation at the Allied Health/Nursing Building
continues. The contractor insulated and installed studs
over the windows along Gravier Street. Crews hung 3 of 16 support beams and
installed 2 of the 3 structural steel columns for
the new auditorium on the 2nd Floor. Three pieces of cross bracing for the
auditorium structural steel were also installed.
Fire alarm
lines were re-routed to make way for the auditorium
structural steel. Crews removed metal ductwork and a CMU wall
in preparation for the next phase of steel
installation.
The contractor poured the concrete
shaft walls for Elevators 3 & 4 at the Resource
Center and the concrete forms were removed. One of five automatic transfer switches was
installed on the 2nd Floor and an electrical panel
box was installed in the pump room on the 2nd Floor. Crews ran conduit from the new ATS room to
the pump room on the 2nd Floor. Four shut off valves were installed in the
chilled water system in preparation for the
installation of the elevated equipment. Six of the eight floor penetrations have been
made in the 2nd Floor pump room. Workers ran conduit from the 1st Floor
emergency circuits to the 2nd Floor ATS room.
The Residence Hall contractor
removed the wooden forms from the concrete
structural columns. Additional underground conduit and piping was
run in the utility chases and electrical conduit was
run from the underground trench to the Entergy
vault.
Crews installed underground conduit and piping
underneath the grade beam. Both utility chases were backfilled. Workers core drilled through the parking
structural grade beam for plumbing piping and they
ran the storm drain pipe from the plumbing utility
chase underground.
The renovation project on the 8th
Floor of the Lions/LSU Clinic Building continues. The contractor relocated sprinkler heads in
both conference rooms. Additional conduit was run in the large
conference room and the main door was installed. Workers installed the storefront door near
the glass curved wall. The AV contractor installed fiber cable for
the speakers, microphone and projector in the large
conference room, and for the dimmer panel in the AV
room.
Light fixtures were installed in the Director’s
office and the hallway. The project to renovate the 7th Floor lab is
complete.
The contractor established the
abatement containment area for the CEB covered
walkway project. The
asbestos abatement of the abandoned steam lines has
been completed and the abatement of the active steam
lines is in progress.
Facility Services completed the
final grading and installed the edging around the
planting beds on the Florida Avenue side of the
School of Dentistry Clinic Building. They also completed the final grading on the
parking lot side of the building. Shrubs were planted on the Florida Avenue
side of the parking lot side of the Clinic Building. Mulch was placed on the beds and crews laid
sod on the Florida Avenue side and the parking lot
side of the Clinic Building. Irrigation piping was installed on the field
side of the horseshoe drive at the School of
Dentistry.
Here are highlights of work
that has been accomplished during the past two
weeks.
ALLIED HEALTH/NURSING BLDG
PERMANENT REPAIRS & MITIGATION:
- The contractor insulated and installed studs over
the windows along Gravier Street.
- They hung 3 of 16 beams and installed 2 of the 3
structural steel columns.
- Fire alarm lines were re-routed to make way for the
auditorium structural steel.
- Crews removed metal ductwork and a CMU wall in
preparation for the next phase of steel
installation.
- The contractor installed three pieces of cross
bracing for the auditorium structural steel.
RESOURCE CENTER PERMANENT REPAIRS
& MITIGATION:
- The contractor poured the concrete shaft walls for
Elevators 3 & 4.
- The concrete forms were removed from the new
waterproof walls.
- One of five automatic transfer switches was
installed on the 2nd Floor.
- An electrical panel box was installed in the pump
room on the 2nd Floor.
- Crews ran conduit from the new ATS room to the pump
room on the 2nd Floor.
- The contractor installed four valves in the chilled
water system in preparation for the installation of
the elevated equipment.
- Six of the eight floor penetrations have been made
in the 2nd Floor pump room.
- Workers ran conduit from the 1st Floor emergency
circuits to the 2nd Floor ATS room.
RESIDENCE HALL PERMANENT REPAIRS &
MITIGATION:
- The contractor removed the wooden forms from the
concrete structural columns.
- Additional underground conduit and piping was run in
the utility chases.
- Electrical conduit was run from the underground
trench to the Entergy vault.
- Crews installed underground conduit and piping
underneath the grade beam.
- The contractor back-filled both utility chases.
- They core drilled through the parking structural
grade beam for plumbing piping.
- The contractor installed storm drain pipe from the
plumbing utility chase underground.
LIONS/LSU
CLINIC BLDG. 7th FLOOR LAB RENOVATIONS:
- The contractor completed work on the various punch
list items.
- The contractor is cleaning and waxing and the
floors.
LIONS/LSU CLINIC BLDG 8th FLOOR
RENOVATIONS:
- The contractor relocated sprinkler heads in both
conference rooms.
- Additional conduit was run in the large conference
room.
- The main door for the large conference room was
installed.
- Workers installed the storefront door near the glass
curved wall.
- The AV contractor installed fiber cable for the
speakers, microphone and projector in the large
conference room, and for the dimmer panel in the AV
room.
- Light fixtures were installed in the Director’s
office and the hallway.
CEB COVERED WALKWAY:
- The contractor established the abatement containment
area.
- The asbestos abatement of the abandoned steam lines
has been completed.
- The abatement of the active steam lines is in
progress..
DENTAL SCHOOL NORTH FIELD GRADING:
- The contractor completed hydro-seeding the north
field.
EXTERIOR/LANDSCAPING:
- Facility Services completed the final grading and
installed edging on the Florida Avenue side of the
School of Dentistry Clinic Building.
- They completed the final grading on the parking lot
side of the building.
- Shrubs were planted on the Florida Avenue side the
parking lot side of the School of Dentistry Clinic
Building.
- Crews finished the final grading and installed mulch
on the Florida Avenue side and the parking lot side
of the School of Dentistry Clinic Building.
- Facility Services laid sod on the Florida Avenue
side and the parking lot side of the School of
Dentistry Clinic Building.
- Irrigation piping was installed on the field side of
the horseshoe drive at the School of Dentistry.
We encourage you to follow the details of our
progress through the daily updates which are posted
on the web site.
|