From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #150
Posted: August 26, 2011
The contractor responsible for the permanent repairs
and mitigation at the Clinical Education Building
continued installing conduit on the 1st, 2nd and 3rd
Floors.
The steam supply line has been installed in the
basement. Workers are erecting forms and installing
steel rebar for additional grade beams in the
Lakeside Lot. The contractor poured concrete
for the grade beam nearest the basement areaway and
removed the forms when the concrete had set up.
Workers began
waterproofing the elevator pits of elevators 7 and
8. The storm drain line for the new elevated
mechanical/electrical structure is being installed. The pendant light fixtures
were removed from the 1st Floor lobby and the
controller for the front passenger elevators was
installed.
The contract to upgrade the CSRB building exhaust
system is progressing. The contractor installed the
fiberglass exhaust cone on top of Exhaust Fan EF-4C
and EF-2D. Crews installed electrical conduit on the 7th
Floor to provide power to rooftop exhaust system #3
and continued installing electrical conduit on the
7th Floor for fan systems #9 and #10. They also installed electrical conduit on the
5th Floor in Room 563. Workers installed the round exhaust ductwork
in the 2nd Floor mechanical room and exhaust risers
#9 and #10 and continued installing the round
exhaust ductwork for exhaust riser 10 from the 3rd
Floor to the 7th Floor.
The contractor sealed the ductwork seams on the 2nd
Floor and the ductwork for phase 2A passed the
pressure test. The exterior perimeter rooms on the 2nd Floor
were connected to the new exhaust ductwork in phase
2A and the ductwork was insulated. Cold water and vacuum piping on the 7th Floor
was relocated and the workers removed the ductwork
in the BSL3 lab. Crews began installing three (3) VFDs
(Variable Frequency Drives) on the roof for exhaust
system #9. The ductwork for exhaust systems #9 and #10
is being installed in Room 729. The contractor began installing the ceiling
support framing in the 2nd Floor corridors as phase
2A nears completion.
The Dental School air handling unit replacement
contractor continued insulating the heating hot
water line and supply ductwork for unit 6A in the
Clinic Building. Fire alarm wiring for units
3A, 3B, and 6A was installed. Workers began
removing the pneumatics and electrical conduits from
mechanical room 5A in the Clinic Building and the
demolition of ceilings and lights for unit 5A was
completed. The
contractor painted the plaster ceiling for the
bathroom on the 3rd Floor and installed ceiling
grids in the 6th Floor bathroom. Light fixtures were installed in the
restrooms on the 3rd and 6th Floors.
The abatement in the mechanical room for unit 5A was
completed and crews removed the old AHU 5A from the
Clinic Building. The contractor built forms and installed
rebar for the concrete pad that will support the new
AHU 5A and installed nine (9) VAV boxes on the 5th
Floor for unit 5A. The drain pan for unit 5A was installed and
workers are installing heating hot water lines for
the VAV boxes and the ductwork. The contractor finished removing light
fixtures and ceiling tiles in the Library and
relocated the VFD for unit 3A in the Administration
Building.
Here are highlights of work that has been
accomplished during the past two weeks.
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing conduit on the
1st, 2nd and 3rd Floors.
- The steam supply line has been installed in the
basement.
- Workers are erecting forms and installing steel
rebar for additional grade beams in the Lakeside
Lot.
- The contractor poured concrete for the grade beam
nearest the basement areaway and removed the forms
when the concrete had set up.
- Workers began waterproofing the elevator pits of
elevators 7 and 8.
- The storm drain line for the new elevated
mechanical/electrical structure is being installed.
- The pendant light fixtures
were removed from the 1st Floor lobby.
- The controller for the front passenger elevators was
installed.
CSRB EXHAUST UPGRADE:
- The contractor installed the fiberglass exhaust cone
on top of Exhaust Fan EF-4C and EF-2D.
- Crews installed electrical conduit on the 7th Floor
to provide power to rooftop exhaust system #3.
- Workers continued installing electrical conduit on
the 7th Floor for fan systems #9 and #10.
- They installed electrical conduit on the 5th Floor
in Room 563.
- The contractor continued installing the round
exhaust ductwork in the 2nd Floor mechanical room
and exhaust risers #9 and #10.
- Crews continued installing the round exhaust
ductwork for exhaust riser 10 from the 3rd Floor to
the 7th Floor.
- The contractor sealed the ductwork seams on the 2nd
Floor.
- The ductwork for phase 2A passed the pressure test.
- The exterior perimeter rooms on the 2nd Floor were
connected to the new exhaust ductwork in phase 2A.
- The contractor completed insulating the ductwork
that was installed in phase 2A.
- Cold water and vacuum piping on the 7th Floor was
relocated.
- The contractor removed the ductwork in the BSL3 lab.
- Crews began installing 3 VFDs (Variable Frequency
Drives) on the roof for exhaust system #9.
- Ductwork for exhaust systems #9 and #10 are being
installed in Room 729.
- The contractor began installing the ceiling support
framing in the 2nd Floor corridors as phase 2A nears
completion.
DENTAL SCHOOL AHU REPLACEMENT:
- The contractor continued insulating the heating hot
water line and supply ductwork for unit 6A in the
Clinic Building.
- Fire alarm wire is being installed for units 3A, 3B,
and 6A.
- Workers began removing pneumatics and electrical
conduits from mechanical room 5A in the Clinic
Building.
- The demolition of ceilings and lights for unit 5A is
finished.
- The contractor painted the plaster ceiling for the
bathroom on the 3rd Floor and installed ceiling
grids in the 6th Floor bathroom.
- Light fixtures were installed in the restrooms on
the 3rd and 6th Floors.
- The abatement in the mechanical room for unit 5A was
completed.
- Crews removed the old AHU 5A in the Clinic Building.
- The contractor built forms and installed rebar for
the concrete pad for unit 5A in the Clinic Building.
- Nine (9) VAV boxes were installed on the 5th Floor
for unit 5A.
- The contractor installed the drain pan for unit 5A
in the Clinic Building.
- They are installing heating hot water lines for the
VAV boxes and the ductwork for unit 5A.
- The contractor finished removing light fixtures and
ceiling tiles in the Library.
- Workers relocated the VFD for unit 3A in the
Administration Building.
We encourage you to follow the details of our progress
through the daily updates which are posted on the
web site.
|