From: Ronnie
Smith, Vice Chancellor, Administration and Finance
Subject: Hurricane Katrina Recovery – Update #152
Posted: September 23, 2011
The Office of Facility Planning and Control has
published the bid advertisements for the project to
make permanent repairs to the 1st Floor
of the Dental School Administration Building. The contract will restore the food service
area and create enhanced seating and study areas. The Dental Bookstore will remain in its
current location instead of being moved back to the
pre-Katrina 1st Floor location which will
allow a new coffee kiosk to be provided. Much of the 1st Floor space will
remain open for use by faculty, staff and students
when the food services are not in operation and
after normal working hours and wireless Internet
connectivity will be available. The bids are scheduled to be opened on
October 13, 2011.
Work continues on the permanent repairs and
mitigation at the Clinic Education Building. The installation of the elevator car rails
for the front passenger elevators is complete and
the sump pump for the elevator pit has been
connected. Crews continued installing formwork and steel
reinforcement for the flood wall around the parking
garage.
Galvanized steel bollards were installed in the
Lakeside lot and workers completed the installation
of the motor starters for the parking garage exhaust
fans in Room 131. The contractor is erecting steel for the new
elevated mechanical/electrical building in the
Lakeside lot. They installed exterior stairs for the new
building and roughed in for exterior lighting to
serve the new loading dock area. Crews continued installing conduit on the
main lobby and the center corridor of the 1st
Floor.
The contractor working on the upgrade of the CSRB
exhaust system finished plastering and painting the
ceilings in the 2nd Floor corridors. They installed light fixtures, diffusers and
sprinkler heads in the new ceilings and began
cleaning the corridors. The VFDs for exhaust systems #2 and #4 were
installed and the contractor continued installing
ductwork on the 3rd Floor for Exhaust
System #9. The duct riser for fan system #4 was pressure
tested and crews continue insulating the duct risers
for exhaust systems #9 & 10. Workers rerouted electrical conduit and a
plumbing vent line around exhaust riser #1. The contractor continues to insulate the duct
riser for exhaust system #4 and the existing duct
riser for exhaust system #3 was removed. Ductwork is being installed in Room 722.
The air handling unit replacement contractor
finished running the heating hot water lines to the
VAV boxes for unit 5A in the Dental School Clinic
Building and pressure tested the lines. The chilled water lines for unit 5A have been
painted.
The ductwork on the 2nd and 5th
Floors and the heating hot water lines on the 5th
Floor of the Clinic Building are being insulated.
Crews continue installing the main supply and return
ductwork adjacent to the 5th Floor air
handling unit. The contractor continues the
installation of the VAVs and the insulation of the
ductwork for unit 2A in the Clinic Building.
The new AHU 2A was set in place and a sprinkler head
was relocated on the 2nd Floor.
The contractor removed the fresh air ductwork
connected to the 2nd Floor (Clinic Bldg.)
units and the heating hot water lines on the 2nd
Floor were pressure tested. Workers started
installing new supply duct on the 2nd
Floor of the Clinic Building. Door frames were installed for the 2nd
and 5th Floor mechanical rooms and crews
are installing the ceilings in the 5th
Floor restrooms. Plastic laminate wall panels
on the 6th Floor were replaced.
Unit L3A in the Administration Building was started
up and workers continued installing control wire to
the VAVs. The
contractor continued to install the ceilings in the
3rd Floor restrooms.
They finished
insulating the heating hot water lines and
installing the ceiling in the Library and the duct
transitions were installed.
Electrical
conduit and electrical whips were installed for the
new light fixtures in the Library and the fixtures
were installed. The 1st phase of
the Library renovation is complete.
Here are highlights of work that has been
accomplished during the past two weeks.
CEB PERMANENT REPAIRS & MITIGATION:
- The installation of the elevator car rails for the
front passenger elevators is complete.
- The sump pump for the front passenger elevators pit
has been connected.
- Crews continued installing formwork and steel
reinforcement for the 2nd section of the flood wall
around the parking garage.
- The contractor installed the galvanized steel
bollards in the Lakeside lot.
- Workers completed the installation of the motor
starters for the parking garage exhaust fans in Room
131.
- The contractor is erecting steel for the new
elevated mechanical/electrical building in the
Lakeside lot.
- They installed exterior stairs for the new building
and roughed in for exterior lighting to serve the
new loading dock area.
- Crews continued installing conduit on the main lobby
and the center corridor of the 1st Floor.
CSRB EXHAUST UPGRADE:
- The contractor finished plastering the ceiling in
the 2nd Floor corridors and painted the
ceilings.
- They installed light fixtures, diffusers and
sprinkler heads in the 2nd Floor corridor
ceilings and began cleaning the corridors.
- The VFDs for exhaust systems #2 and #4 were
installed.
- The contractor continued installing ductwork on the
3rd Floor for Exhaust System #9.
- The contractor pressure tested the duct riser for
fan system #4.
- Crews continued insulating the duct risers for
exhaust systems #9 & 10.
- Workers rerouted electrical conduit and a plumbing
vent line around exhaust riser #1.
- The contractor continued to insulate the duct riser
for exhaust system #4 and remove the existing duct
riser for exhaust system #3.
- Ductwork is being installed in Room 722.
DENTAL SCHOOL AHU REPLACEMENT:
- The contractor finished running the heating hot
water lines to the VAV boxes for unit 5A in the
Clinic Building and pressure tested the lines.
- The chilled water lines for unit 5A have been
painted.
- The ductwork on the 2nd and 5th
Floors and the heating hot water lines on the 5th
Floor of the Clinic Building are being insulated.
- Crews continued installing the main supply and
return ductwork adjacent to the 5th Floor
air handling unit.
- The contractor continued to install the VAVs and
insulate the ductwork for unit 2A in the Clinic
Building.
- The new AHU 2A was set in place.
- A sprinkler head was relocated on the 2nd
Floor of the Clinic Building.
- The contractor removed the fresh air ductwork
connected to the 2nd Floor (Clinic Bldg.)
units.
- The heating hot water lines on the 2nd
Floor of the Clinic Building were pressure
tested.
- The contractor started installing new supply duct on
the 2nd Floor of the Clinic Building.
- Door frames were installed for the 2nd
and 5th Floor mechanical rooms.
- Crews are installing the ceilings in the 5th
Floor restrooms.
- Plastic laminate wall panels on the 6th
Floor were replaced.
- The contractor finished insulating the heating hot
water lines and installing the ceiling in the
Library.
- Duct transitions were installed in the Library.
- Electrical conduit and electrical whips were
installed for the new light fixtures in the Library
and the fixtures were installed.
- The 1st phase of the Library renovation
is complete.
- Unit L3A (Administration Building) was started up
and workers continued installing control wire to the
VAVs.
- The contractor continued to install the ceilings in
the 3rd Floor (Administration Building)
restrooms.
We encourage you to follow the details of our progress
through the daily updates which are posted on the
web site.
|