Louisiana State University Health Sciences Center Administration & Finance
 

Friday, October 14, 2005

  • Liquid nitrogen is being delivered weekly to support the continued preservation of research samples remaining on campus.
  • The interior wash down of MEB mechanical/electrical rooms is underway. The power washing of the "T" lot has been completed and power washing of the Lakeside lot has begun.
  • The environmental assessment consultant has delivered written reports for five of the major downtown campus buildings; Stanislaus Hall, the Residence Hall, Nursing/Allied Health, MEB, and the Resource Center.
  • The contractor walk thru was held today for two open solicitations; 1) for the removal and disposal of movable equipment and furnishings, and 2) for the provision of emergency air conditioning to the Dental Admin and Clinic buildings. Responses to both solicitations are due on Tuesday, 10/18.