Monday, October 31, 2005 - Fisk Electric is completing the removal of corrosion discovered on the Resource Center switchgear.
- Triton Mechanical has connected chilled water piping to the temporary chillers and has repaired a chilled water leak, as they work to provide temporary air conditioning to the Dental School.
- The rebuilt domestic water pumps for the Resource Center and the MEB have arrived and are being installed.
|