Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, November 02, 2005

  • The contractor completed the cleaning on the 2nd floor of the Residence Hall that was added to the contract. Work has also continued in the MEB cafeteria and is almost complete.
  • Work has continued on removing the corrosion from the Medical Education Bldg. switchgear. A test of the power is tentatively planned for Monday, 11/7.
  • Triton Mechanical has completed the temporary wiring of the Dental School Clinic Building's air handling units, in preparation for providing temporary A/C to the main buildings.
  • The contract documents have been executed for the emergency removal of flood-damaged movable equipment and furnishings from the basements and 1st floor spaces. The initial job site visit is scheduled for 11/3.