Louisiana State University Health Sciences Center Administration & Finance
 

Monday, November 21, 2005

  • The contractor removing flood-damaged equipment and furnishings completed their work at the MEB today.
  • The elevator contractor at the CSRB completed a temporary repair of one of the building freight elevators. The contractor at the Resource Center received some of the parts needed to begin making permanent repairs.
  • The States Architect Selection Board has selected Duplantier & Meric as the architect for the major renovation project for the downtown campus. The award decision for the Dental School campus was deferred until the December 13th meeting.