  • Contractor who is removing flood damaged equipment and furnishings continues to work the punch list of remaining items.
  • The LSUHSC Facilities staff has completed the cleaning of the boilers at the MEB.
  • The remaining domestic water pump at the Residence Hall has been removed and sent for rebuilding.
  • The new gas trains for the MEB boilers have been completed. The contractor is waiting on delivery of the new gas regulators to complete the installation at the MEB.