  • The installation of the large steam generators in the CSRB Animal Care area has been completed and the contractor has begun trouble shooting the systems. Additional problems have been identified with one of the steam generators and replacement parts are on order and expected early next week.
  • The needed repairs to the fire alarm system at the Resource Center have been identified and a contract has been issued to the fire alarm system maintenance contractor.
  • The contractor responsible for the removal of flood damaged carpet and building materials from the 1st floors has completed the punch list items at the MEB and the Lion's Eye Center.