Louisiana State University Health Sciences Center Administration & Finance
 

Monday, April 10, 2006

  • The bids on the 3rd environmental remediation package for the downtown campus have been received and the bid responses are currently being evaluated.
  • The air conditioning units in the Residence Hall apartments are being cleaned by the environmental remediation contractor. The replacement floor tile for the building has not been delivered yet.
  • The three elevators at Stanislaus Hall have been certified for general use by the State elevator inspector.
  • The traveler and governor cables are being replaced on the "A" and "C" tower elevators in the Residence Hall.