Thursday, April 6, 2006 - The State elevator inspector completed his inspection of the elevators in the Lions/LSU Clinic Building today. We expect to have his reports on these elevators on Friday.
- The heating hot water pumps for both the CSRB and the MEB were connected to the building plumbing systems.
- The emergency generator contractor delivered the rebuilt stator (the motor which generates the electricity) for the Resource Center generator. Installation will begin shortly.
|