Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, May 16, 2006

  • The contractor continues to make good progress finishing the tile replacement and has began sealing the tiles in the Residence Hall. Additionally, the emergency generator is now in place at the Residence Hall. A 2 hour power outage will be planned this weekend to test the automatic transfer switch.
  • The remediation contractor continues to make good progress on the 8th floor of 1542 Tulane
  • The elevator contractor completed repairs at Stanislaus
  • Carpet and tile work is complete at Medical Center Stores, and they will begin moving operations back into their normal space