Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, October 19, 2006

  • The Temporary Power Project contractor at 1542 Tulane continued to check the electrical panels on upper floors to insure that power has been properly restored.
  • The new filter has now been connected to the VFD and the motor in the Central Utility Plant.  
    • On Friday, 10/20 the refurbished motor will be shut down and the original motor will be tested.
    • The sub-contractor will make their adjustments to the refurbished motor's VFD controls while the other system is being tested.   
  • The new light poles for the Student Parking Lot Project were delivered this morning.
    • The contractor began working to get more wires pulled from each new pole location to the electrical panels.  However the return of heavy rains interrupted the work.
  • At the Dental School , the architect/engineering team met with the Phase 2 contractor to plan and coordinate the testing, maintenance and/or needed repairs of the air handling units throughout the Clinic and Administration buildings.
    • The negative air machines and dehumidifiers are set-up and operating properly on floors 2 - 5 of the Clinic Building .
  • The Phase 1 electrical contractor was on site at the Dental School continuing to prepare their list of materials required for the connection of the remaining light fixtures on the 1st floor.