  • The new circuit breaker panels for the Student Parking Lot Lighting project were delivered today.  Unfortunately, the continued rain prevented the crews from working on the lots today. 
  • The Phase 2 mechanical contractor continued to complete the inspection of the HVAC system in the Dental School Administration Building.  So far, 12 additional broken thermostats have been identified within the Admin Building.  The mechanical contractor will be shifting his efforts to the 4th floor of the Admin Building .