Thursday, December 28, 2006- At the Dental School ,
the elevator contractor continues to work on the freight elevator; installing the
gate operators and linkage.
- The
mechanical sub-contractor is working on a variety of punch-list items in the Clinic Building . All of the old sinks, toilets, and plumbing
fixtures have been removed on the 1st floor and in the basement.
- The
inspection of Boilers #2 & #3 to determine what damage was done by the
storm also continues.
- The contractor working at 1542 Tulane Ave. has finished connecting
the starter disconnects and the electrical feeds on the 1st floor for the basement
sump pumps.
- Work on the contract to make the final
electrical repairs to various parking lots is underway.
- At
Parking Lot #1, the contractor is working on building a rack four feet above
the trough to house the power feeds that run from the electrical panel to the
gate.
|