Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, December 28, 2006

  • At the Dental School , the elevator contractor continues to work on the freight elevator; installing the gate operators and linkage.
    • The mechanical sub-contractor is working on a variety of punch-list items in the Clinic Building .  All of the old sinks, toilets, and plumbing fixtures have been removed on the 1st floor and in the basement. 
    • The inspection of Boilers #2 & #3 to determine what damage was done by the storm also continues. 
  • The contractor working at 1542 Tulane Ave. has finished connecting the starter disconnects and the electrical feeds on the 1st floor for the basement sump pumps. 
  • Work on the contract to make the final electrical repairs to various parking lots is underway. 
    •  At Parking Lot #1, the contractor is working on building a rack four feet above the trough to house the power feeds that run from the electrical panel to the gate.