  • At 1542 Tulane Ave., the contractor removed the old switchgear from the basement.
    • The design team engineers walked the building to locate all air handling units, the rooms with faucets, and all of the bathrooms.
    • Repair work continued on the freight elevator. 
  • Parking Lot #2.  The light pole bases are being finished with the sand mix.  The new light fixtures are now installed on approximately half of the poles. 
  • Parking Lot #3.  The new light fixtures are scheduled to be installed this week. 
  • The Dental School contractor started installing the pipe supports for the additional pipe that was installed for the new temporary chillers.
  • The elevator contractor working on the Gravier Parking Garage elevators will be working on repairs to the elevator cabs for the next few days.