Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, January 18, 2007

  • At the Dental School site, some basic grounds work is underway.  The grass lot across from the Administration Building was cut from the parking lot to the bayou.
  • The elevator contractor has begun installing the elevator doors on the 1st floor of the Dental Clinic Building.
  • The elevator contractor at 1542 Tulane Ave. continued their repair work to equipment located in the penthouse. 
  • The mechanical subcontractor is tracing drain pipes in the 1542 Tulane Ave. building.  They also received the four sumps pumps that will be installed in the basement.
  • The contractor received two new transfer switches for the emergency generators located at 1542 Tulane Ave. and they are installing them at this time.
  • Approximately 80 percent of the new ceiling tile grid has been installed in the MEB atrium.
    • LSUHSC Facility Services personnel raised some additional conduit that was in the way of the new ceiling.
    • The installed sheet rock has been prepped for painting.