Wednesday, January 3, 2007

  • At the Dental School , repair work on the building elevators continued.  The basement elevator doors should be installed by the end of this week.
    • The mechanical sub-contractor continued working on their punch list items.
    • Siemens ran the communications line for the Energy Management System. 
  • At 1542 Tulane Ave. , the contractor is installing electrical panels.
  • The installation of the new ceiling tile in the 3rd floor halls in the MEB is nearing completion.
  • The new ceiling framing in the MEB atrium is nearing completion.