  • The Section 406 Hazard Mitigation proposal for protection of the campus elevators has been forwarded to FEMA by the Hazard Mitigation specialist from the State Public Assistance Office. 
  • Schindler continues to make progress on the repairs to the Dental School elevators.  They were fine tuning Elevator #3 on the 8th floor of the Clinic Building today.
  • The 1542 Tulane Ave. contractor continues their work on electrical panels and the drives in the basement, while the elevator contractor was progressing with making repairs to the building elevators.
  • The pipe insulation project in the basement of 1542 Tulane Ave. is also still in progress.