Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, March 29, 2007

Dental School:

  • Premier Equipment serviced the air compressors on the 2nd level of the power plant.
  • Zimmer has completed ceiling grid removal on the 2nd floor of the Clinic Building. They have started removal on the 2nd floor on the breezeway and in the Admin Building.
  • Schindler worked on elevator #3 at 1st floor level in the Clinic Building.
  • Action Restoration visited the building for another look at the buildings for a possible bid on the mold remediation due to open on Monday, April 2.

1542 Tulane Ave:

  • Stratos Elevators was installing the cab on # 3 elevator.
  • Mechanical Insulation continues insulating chilled water piping in the basement.
  • Siemens visited the site checking the locations of existing fire alarm components.