Louisiana State University Health Sciences Center Administration & Finance
 

Friday, April 13, 2007

Dental School :

  • Schindler continues to install 2 inch conduit in the penthouse of the Administration Building for the new elevator motors.
  • ADC is putting the finishing touches on the installation of the new network equipment on the 5th floor.  Work should be completed in the next few days. 
  • MCC continues with the installation of the chemical treatment center.  They installed 1/2" copper lines on the system at the chill water supply lines. 
  • Chris Cole with Mathis Verges Architects surveyed the grounds to assist in aligning the damage estimates with FEMA.

 1542 Tulane Ave.:

  • Ordes Electrical continues to work on sump pump controls # 1 and #2.  If the new controls work properly, it is possible that a test will soon be run on the pumps.
  • Stratos Elevators continued working on repairs to Elevator #3. 
  • ISE Electrical continues to install alarms in Elevators # 1, #2 and #3. 
  • Arc Mechanical continued working on repairing the condensate steam station.  The condensate station should be finished by the close of business today if all goes well. 
    • They are also installing a steam trap in the pipe chase.