Louisiana State University Health Sciences Center Administration & Finance
 

Tuesday, May 15, 2007

Dental School :

  • Zimmer is working in Auditorium B jack hammering the floor to remove the concrete that forms the slope in the floor.
  • Zimmer started coating/encapsulating the insulation that lines the duct work on the second floor and have started preparing the third floor for remediation.
  • Boe-Tel finished installing the cable tray on the 7th floor of the Clinic Building .
  • C&R Network continues working on the 4th floor pulling installing and connecting network drops.

Cafeteria Project:

  • The initial demolition work continued.   Most of the wall separating the dining room from the 3rd floor hallway has been removed.