Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, May 30, 2007

Dental School :

  • Zimmer continues to work around the clock on floors 4 through 7 of the Clinic Building.
  • Boe-Tel is terminating all of the network cable installed on the 6th floor and continues to run new cable on the 7th floor.
  • AT&T spliced in the cable in the sub-basement that connects the telephone cables from the 5th floor to the wires to the manhole outside the building.
  • Schindler continues their progress on the Administration Building elevators.
  • A pre-construction meeting for the Central Sterilization project was held with Landis and MCC by Mathis Verges.

1542 Tulane Ave.:

  • Ordes Electrical is installing disconnect panels for the condensation pumps and air driers in old engine room.
  • Stratos Elevator is continuing to install the safety chain on Elevator #3.
  • Arc Mechanical is running pipe to the condensation pumps in the old engine room.

Downtown Landscaping Project: 

  • The irrigation valve wiring for the Lions/LSU Clinic and the CSRB has been completed and 23 of the 25 valves installed.