Dental School :

  • Boe-Tel is working on the 1st floor of the Clinic Building running the new network cable. 
    • The 6th floor is completely wired and wire mold installed.  The jacks are awaiting testing of the lines.
    • Boe-Tel has moved to the 7th floor installing the new jacks and wire mold.
  • Frischhertz is working on the 2nd floor of the Clinic Building removing the light fixtures as part of the ceiling project.
  • Zimmer is testing the 3rd floor of the Clinic Building today to verify that the remediation has been successfully completed. 
    • They continue the clean on the 4th, 5th and 6th floors and the demolition work in the small auditorium is moving quite well. 
    • The duct cleaning has begin on the 7th floor.
  • Schindler is working in the elevator pits in the Administration Building removing the damaged equipment.
  • MCC had a 60 ft. crane put in place to start work on the replacement of the cooling tower in the Power Plant.

1542 Tulane Ave. :

  • Stratos Elevator is installing the safety limit switches on Elevator # 3.
  • Ordes Electrical is continuing to pull wire to the 480V breaker in engine room.