Friday, May 04, 2007 Dental School :
- Frischhertz
Electric continues to install the 2 ½ inch conduit in the elevator penthouse of
the Administration Building for the three disconnects.
- Boe-Tel
is running conduit through the drain thimble next to the drain pipe of the sink
for the connection of the network cable on the 3rd floor at every teaching bay.
- The
installation of the cable trays is complete on the 2nd and 3rd
floors and continues on the 4th floor.
- Coastal
Air Balance checked the air balance of the 7th and the 8th floor air handling
units today.
- Schindler
took Elevators #3 and #4 out of service to change out the interior of the units. They will also be installing new controllers.
- BellSouth/AT&T
continued their work in the telephone room on the 5th floor.
- GVA
visited to look at the maintenance auto shop, Auxiliary Enterprise warehouse
and the safety room in order to address FEMA scope alignment questions.
1542
Tulane Ave.:
- Ordes
installed the starters for the hot water circulating pumps.
- Stratos
Elevator was running power to all three elevators.
|