Monday, June 11, 2007 Dental School :
- Edmondson Equipment is removing the debris from the 3rd floor areas that have been demolished for the new Central Sterilization room.
- Landis has all of the new ceiling tile installed on the 2nd floor of the Clinic Building except at the sprinkler heads.
- They have started the installation of the border tiles on the 3rd floor.
- Frischhertz is reinstalling the existing lights on the 3rd floor following Landis who is installing the ceiling grid and ceiling tile.
- Firetrol continues to reposition and add sprinkler heads as necessary to accommodate the new ceiling grid.
1542 Tulane Ave. :
- Arc Mechanical continues installing the domestic hot water pumps.
- Stratos Elevator is running the final tests on Elevator #3 in preparation for the visit by the State Elevator Inspector.
- Ordes Electrical continues running wire to the transformers in vault.
|