Wednesday, June 13, 2007 Dental School :
- Landis continued working on the installation of the ceiling grid and tile on the 3rd and 4th floors of the Clinic Building.
- The following is the status of the remediation and duct cleaning work as of this morning:
- Clinic Building:
- 1st - Clean and clearance samples passed. Duct viable samples taken yesterday and results are expected next week. AHU to remain off until then.
- 2nd - Clean and clearance samples passed. All AHU viable samples passed and both units operational.
- 3rd - Clean and clearance samples passed. North AHU (E3B) viable samples passed and the unit is operational. AHU E3A failed viable test and coils are being re-cleaned and will be sampled when the re-cleaning is complete.
- 4th - Clean and clearance samples passed. AHU viable samples for both units expected by the end of this week.
- 5th - Clean and clearance samples passed. AHU viable samples for both units expected by the end of this week
- 6th - Clean and clearance samples passed. AHU viable samples for both units expected early next week.
- 7th - Clean and clearance samples passed. AHU viable samples for both units expected early next week.
- 8th - Duct cleaning in progress.
- Admin Building :
- 2nd - AHUs and ducts cleaned and viable samples taken yesterday (6/12). Final area cleaning will continue when power is restored to the building.
- 3rd - AHUs and ducts cleaned and viable samples taken yesterday (6/12). Final area cleaning will continue when power is restored to building.
- 4th - AHUs and ducts cleaned and ducts are being re-coated today. Viable samples expected to be taken today or tomorrow. Final area cleaning will continue when power is restored to building.
1542 Tulane
Ave.:
- Ordes Electrical is installing disconnect panels for the domestic hot water circulating pump.
- Stratos Elevators continues installing the floor call buttons.
- Arc Mechanical is installing the heat exchangers for domestic hot water.
Landscaping Project:
- 26 Savannah holly trees were planted around the CSRB and the Lions/LSU Clinic Building.
- All of the irrigation zones have the underground pipe installed and terminated.
|