Louisiana State University Health Sciences Center Administration & Finance
 

Monday, June 04, 2007

Dental School :

  • Zimmer has finished the cleaning of the 6th floor of the Clinic Building and have sealed it off.
    • The major cleaning of every office on the 7th floor has also been completed. 
    • They have started the duct cleaning on the 2nd floor of the Administration Building.
  • Firetrol is working throughout the whole Clinic Building installing new sprinkler heads and re-positioning old ones as part of the project to replace ceiling tiles.
    • Landis started the lay out of the new ceiling tile grid on the 2nd floor of the Clinic Building. 
    • Frischhertz followed behind Landis installing the existing light fixtures into the newly installed grid.
    • MCC followed behind Frischhertz installing the replacement flex duct for the A/C vents. 
  • A & A started core drilling 4" holes for the new network closets in Rooms 5312, 4329b, 3312g.
  • Boe-Tel resumed work on the 3rd floor pulling network wire to each teaching bay in the Clinic Building through the Sealtite conduit previously installed.
  • York has finished the installation of the new motor for Chiller # 2.  The unit is powered up but it needs additional work to repair a flow switch. 

1542 Tulane Ave.:

  • Stratos Elevator is still installing the safety limit switches on Elevator # 3. 
  • Ordes Electrical continued to pull wire to the 480V breaker in the engine room. 

Downtown Landscaping Project: 

  • The irrigation around the CSRB is complete and final grading has started. 
  • Limited progress was made on the installation of the last two zones at the Lions/LSU Clinic Building flagpole half moon due to the recent rains.